Surety’s Several Liability Under Bonds
March 20, 2023 —
David Adelstein - Florida Construction Legal UpdatesWhen a payment or performance bond is issued on behalf of its bond-principal, the surety is jointly and severally liable with its bond-principal. This means the surety has several liability under the bond, i.e., you don’t need to pursue the principal of the bond to pursue liability under the bond, which is a separate written intrument. Thus, if you are claiming damages of $500,000, by way of example, you can sue both the principal and surety under the bond, you can ONLY sue the principal under the bond (which is rarely practical), or you can ONLY sue the surety under the bond (which, oftentimes, is very practical). In many instances where I am pursuing a bond claim on behalf of a client, particularly a payment bond claim, I only sue the surety and do not sue the bond-principal unless there are certain strategic reasons in doing so. This is because of the surety’s several liability under the bond and there may be solvency issues with the principal or contractual reasons that, strategically, make much more sense to exclude the principal from the action.
In MJM Electric, Inc. v. National Union Fire Ins. Co. of Pittsburgh, PA, 2023 WL 2163087 (M.D.Fla. 2023), an electrical subcontractor was hired to perform electrical work by the prime contractor. The prime contractor had a payment bond. The project was delayed for two years. The electrical subcontractor claimed the prime contractor failed to compensate it for significant delays and out of scope work.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Laborers Sue Contractors Over Wage Theft
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFAspen Journalism reported that “[f]our laborers who worked on the Burlingame Phase II affordable housing project financed by the city of Aspen are suing three of the project’s contractors, alleging they weren’t paid for some of their work and were never paid overtime when they worked more than 40 hours per week.”
Towards Justice, nonprofit legal services group, filed suit in August on behalf of Fernando Villalobos, Sergio Roman, Ramon Gonzalez and Hugo Esqueda, and against construction companies Haselden Construction, LLC of Centennial, Continental Constructors, LLC of Littleton, and JMS Building of Glenwood Springs.
Both sides have agreed that “the men were paid for some, but not all, of their work,” but dispute “the value of the work done by the laborers.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Insurance Rates Up in the United States
November 20, 2013 —
CDJ STAFFA new report says that construction firms paid from three to seven percent more on average during the first six months of 2013 than they had in the last half of 2012. Firms with poor loss histories paid even more, reaching double-digit increases.
Michael Anderson, of Marsh’s U.S. Construction Practice said that “U.S. construction firms are grappling with a firming insurance market, especially when it comes to liability insurance where underwriters continue to tighten coverage terms and seek rate increases to make up for reduced investment income.” He did note that “the good news for well-managed construction firms is they can still generally find competitive pricing and terms.”
Read the court decisionRead the full story...Reprinted courtesy of
With Historic Removal of Four Dams, Klamath River Flows Again Unhindered
October 21, 2024 —
Tim Newcomb - Engineering News-RecordIn a period of 16 months, four dams built between 1903 and 1962 came down as part of a monumental effort to clear 35 miles of the Klamath River spanning Oregon and California. The project owner, the Klamath River Renewal Corp., describes it as the largest dam removal effort in U.S.—and possibly world—history.
Reprinted courtesy of
Tim Newcomb, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Global Emissions From Buildings, Construction Climb to Record Levels
November 28, 2022 —
Gautam Naik - BloombergCarbon-dioxide emissions from building construction and operations hit an all-time high in 2021, according to the most recent data, a sign that the push to decarbonize the industry by 2050 may be slipping out of reach.
Energy-related emissions from the operation of buildings reached 10 gigatonnes of CO2 equivalent, 5% higher than 2020 levels and 2% more than the pre-pandemic peak in 2019, according to data compiled by the Global Alliance for Buildings and Construction. Operational energy demand in buildings for heating, cooling, lighting and equipment rose about 4% from 2020 levels, the group said.
While investments in building energy efficiency increased 16% last year to $237 billion, the growth in floor space outpaced efficiency efforts. As a result, “the gap between the climate performance of the sector and the 2050 decarbonization pathway is widening,” the report concluded.
Read the court decisionRead the full story...Reprinted courtesy of
Gautam Naik, Bloomberg
Indemnity Provision Provides Relief to Contractor; Additional Insured Provision Does Not
January 06, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court found that the contractor was entitled to relief under the contractual indemnity provision, but not the policy's additional insured clause. Chatelain v. Fluor Daniel Constr. Co., 2015 La. App. LEXIS 2257 (Ct. App. La. Nov. 10, 2015).
Following Hurricanes Katrina and Rita, FEMA retained Fluor Enterprises, Inc. as a contractor to transport and install FEMA trailers. Fluor entered a Blanket Ordering Agreement (BOA) with Bobby Reavis Contracting, Inc. to transport and install the trailers. The BOA provided Reavis would defend and indemnify Fluor from all liability arising from the subcontractor's work. Reavis also agreed to name Fluor as an additional insured under its CGL policy.
Reavis installed a FEMA trailer for Connie Chatelain. Ms. Chatelain was injured when she fell exiting her FEMA trailer. She sued Fluor and Reavis. Fluor tendered the suit to Reavis and Reavis' insurer, Guilford Insurance Company. The tender was rejected and Fluor filed a third-party action demanding indemnification, reimbursement of all legal expenses and damages for insurer misconduct.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
City of Birmingham Countersues Contractor for Incomplete Work
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in December of 2013, WVTM News reported that Chris Woods, a contractor, filed a lawsuit against the City of Birmingham, Alabama, demanding $1.5 million for the West Police Precinct and two other projects he had been contracted on. However, “Birmingham claimed Woods was fired for not completing projects on time and other contract breaches.”
On March 7th, WVTM News reported that the City of Birmingham has filed a counterclaim against Woods, alleging that he “owes $1.2 million for incomplete work.” The city listed his “inability to meet specific construction deadlines and finish either project on time as factors for his termination.” Woods, however, blamed the city for delays, citing multiple design changes requested by Birmingham.
The city’s counterclaim also alleged that “Star Insurance Company, ‘identified major, numerous defects in the work that Woods had performed prior to the termination of the West Precinct Project.’”
Read the full story, December 2013 Article...
Read the full story, March 2014 Article... Read the court decisionRead the full story...Reprinted courtesy of
Court Makes an Unsettling Inference to Find that the Statute of Limitations Bars Claims Arising from a 1997 Northridge Earthquake Settlement
April 15, 2015 —
David W. Evans and Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Britton v. Girardi (No. B249232 – Filed 4/1/2015), the Second Appellate District upheld the trial court’s dismissal due to the statute of limitations based on an inference it drew from a letter attached to the complaint, while reaffirming its prior application of the limitations period in Probate Code section 16460 for fraud claims in the related case of Prakashpalan v. Engstrom, Lipscomb & Lack (2/27/2014) 223 Cal.App.4th 1105.
In Britton, just as in Prakashpalan, the plaintiffs sued the attorneys who had represented them in connection with claims against their insurer arising out of the Northridge earthquake. In 1997, the attorneys had settled that litigation for more than $100 million. The plaintiffs allege that the attorneys breached their fiduciary duty by (1) failing to provide an accounting for the settlement, (2) failing to obtain their informed consent to the settlement, and (3) concealing their misappropriation of the settlement funds. They claim that they did not discover this wrongdoing until nearly fifteen years later, in 2012, when the Prakashpalans contacted them about their settlement. Significantly, the plaintiffs attached as an exhibit to the complaint a page of the November 3, 1997 letter to the Prakashpalans (rather than the plaintiffs), which stated that a retired judge who presided over the settlement had determined the allocations and the attorneys could not distribute the proceeds until the plaintiffs signed the “Master Settlement Agreement” by which the plaintiffs agreed to its terms and to give up all claims against the insurer.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of