Delays Caused When Government (Owner) Pushes Contractor’s Work Into Rainy / Adverse Weather Season
January 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesThere are a number of horizontal construction projects where a contractor’s sequence of work and schedule is predicated on avoiding the rainy season (or certain force majeure events). The reason is that the rainy season will result in delays due to the inability to work (and work efficiently) during the adverse weather (including flooding caused by the weather). If the work is pushed into the rainy season, is such delay compensable if the government (or owner) delayed the project that pushed work out into the rainy season? It very well can be.
For example, in Meridian Engineering Co. v. U.S., 2019 WL 4594233 (Fed. Cl. 2019), a contractor was hired by the Army Corps of Engineers to construct a flood control project for a channel in Arizona. Due to delays, including those caused by the government, the project was pushed into the monsoon season, which caused additional delays largely due to flooding caused by the heavy rain. One issue was whether such delays were compensable to the contractor – the government raised the argument that the contractor assumed the risk of potential flooding from the rainy season. The Court found this argument unconvincing:
[The contractor’s] initial construction schedule planned for a completion of the channel invert work, a necessary step in protecting the site from flooding, to be completed by late June 2008…[M]any issues arose in the project’s early stages that led to cumulative substantial delay, including those caused by the government’s failure….The government cannot now claim that [the contractor] assumed the risk of flooding from monsoon season when the government was largely responsible for [the contractor’s] inability to complete the project prior to the beginning of the monsoon season. Simply put, the government cannot escape liability for flood damages when the government is responsible for causing the contractor to be working during the flood-prone season.
Meridian Engineering, 2019 WL at *7 (internal citations omitted)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Court Dismisses Cross Claims Against Utility Based on Construction Anti-Indemnity Statute
August 14, 2018 —
David R. Cook - Autry, Hall & Cook, LLPWhen a plane crashed and several passengers and crew died or were injured, their representatives sued several defendants, including a nearby plant owner, Milliken & Company (“Plant Owner”), based on claims that transmission lines on Plant Owner’s property were too close to the runways, were too high, and encroached on the airport easements. Plant Owner cross claimed against utility owner, Georgia Power Company (“Utility”). Plant Owner’s claim was based on an easement it granted to Utility, which required Utility to indemnify it for any claims arising out of Utility’s construction or maintenance of the transmission lines.
In defense, Utility argued that the easement’s indemnity provision violated Georgia’s construction anti-indemnity statute.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
OSHA Advisory Committee, Assemble!
February 06, 2023 —
Rachel E. Pelovitz - Construction ExecutiveThe Occupational Safety and Health Administration (OSHA) has sourced new members for its Advisory Committee on Construction Safety and Health, which was established by the Construction Safety Act to provide “advice and assistance in construction standards and policy matters” to the assistant secretary of labor for occupational safety and health. The committee consists of 15 members, one appointed by the secretary of labor, to represent the interests of employers, employees, state safety and health agencies, in addition to the public.
Reprinted courtesy of
Rachel E. Pelovitz, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Pelovitz may be contacted at pelovitz@abc.org
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury Attorney Featured in 2022 Best Lawyers in America and Best Lawyers: Ones To Watch!
September 13, 2021 —
Wilke Fleury LLPWilke Fleury congratulates attorneys David Frenznick, Adriana Cervantes, Matthew Powell and Dan Egan on their inclusion in the 2022 Edition of Best Lawyers in America!
Since it was first published in 1983, Best Lawyers® has become universally regarded as the definitive guide to legal excellence. Best Lawyers lists are compiled based on an exhaustive peer-review evaluation. Almost 108,000 industry-leading lawyers are eligible to vote (from around the world), and they have received over 13 million evaluations on the legal abilities of other lawyers based on their specific practice areas around the world. For the 2021 Edition of The Best Lawyers in America©, 9.4 million votes were analyzed.
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury LLP
One Insurer's Settlement with Insured Does Not Bar Contribution Claim by Other Insurers
October 30, 2013 —
Tred Eyerly — Insurance Law HawaiiThe New Jersey Supreme Court held that one insurer could seek contribution from another insurer who settled with and secured a release from the insured. Potomac Ins. Co. v. Pennsylvania Manufacturers' Ass'n Ins. Co., 2013 N.J. LEXIS 847 (N.J. Sept. 16, 2013)
The township of Evesham retained Roland Aristone, Inc. to be its general contractor for construction of a new middle school. After completion of the school, the roof leaked. Evesham sued Aristone for the construction defects.
Aristone tendered to its various CGL carriers. Two insurers, Selective Way Insurance Company and OneBeacon Insurance Company, defended. Two others, Pennsylvania Manufacturers' Insurance Company (PMA) and Royal Insurance Company, denied coverage. Aristone sued PMA and Royal, and ultimately settled with PMA for $150,000 in exchange for Aristone's release from all claims, including claims for defense fees and costs.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
A Contractual Liability Exclusion Doesn't Preclude Insurer's Duty to Indemnify
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Traub Lieberman Straus & Shrewsberry LLP's blog, "[I]n Crownover v. Mid-Continent Cas. Co., 2014 U.S. App. LEXIS 20737 (5th Cir. October 29, 2014), the United States Court of Appeals for the Fifth Circuit withdrew its prior ruling and held that the contractual liability exclusion did not preclude an insurer’s duty to indemnify its insured for an award resulting from the insured’s defective construction."
The case involved the Crownovers who were awarded damages for "Arrow's breach of paragraph 23.1 of the construction contract." However, Arrow then filed for bankruptcy. Mid-Continent, Arrow's insurer, denied Crownovers' demand for recovery, stating that "the contractual liability exclusion applied because the arbitrator’s award to the Crownovers was based only on Arrow’s breach of paragraph 23.1 of the construction agreement." The court agreed with Mid-Continent.
Subsequently, the fifth court of appeals "reversed the district court’s ruling and awarded summary judgment in favor of the Crownovers."
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Information and Resources
May 04, 2020 —
Richard H. Glucksman, Esq. & Brian D. Kahn, Esq. – Chapman Glucksman Dean & Roeb BulletinINTRODUCTION
The current COVID-19 health crisis has greatly impacted nearly every aspect of our business and personal lives. The constant flow of rapidly evolving, and often contradictory information creates its own challenges for those who are responsible for ensuring compliance with relevant regulations and best practices while still moving forward with their business and family activities.
This bulletin differs from most Chapman, Glucksman, Dean & Roeb bulletins in that it does not highlight a recent case, statute or a single development, but rather acts as a resource and “links” to provide you with needed information and to simplify your search for critical information during this unusual and challenging time.
CIVIL LITIGATION: CLOSURES AND RESTRICTIONS
The State and Federal Court systems in California have drastically reduced their operations. The Governor issued Executive Order N-38-20, this suspends certain limitations on the Chief Justice’s authority, making it possible for orders to be issued adapting the Court’s operations to address the COVID-19 health crisis. As of this time, the most recent statewide order from the Chief Justice is the March 30, 2020 Order which allows Courts to utilize remote technology when possible. The March 30, 2020 Order also clarifies a prior Order suspending all trials for 60 days. As many of you are aware, civil trials in California must commence within five years of the initiation of the action, this is commonly referred to as the “five year rule”. While the five year time period was initially extended by the Chief Justice for 60 days, the Judicial Council subsequently adopted a series of Emergency Rules, including one which extends this to six months for all civil actions filed on or before April 6, 2020. The Judicial Council also adopted rules tolling the statutes of limitation for civil causes of action are tolled from April 6, 2020 to 90 days after the state of emergency has ended.
In addition to the statewide orders and rules, counties have enacted their own rules. Los Angeles Superior Court, for instance, has closed some locations while others remain open on a limited basis. On March 17, 2020 an Order was issued limiting the Court to “essential functions” through April 16, 2020. However, on April 15, 2020, a further Order extended the closure through May 12, 2020. While truly urgent Ex Partes may go forward, all regularly set hearings will be continued until after June 22, 2020. Trials will begin after June 22, 2020 with non-priority trials anticipated to start in later August or September. Notably, any deadlines imposed by current trial or hearing dates still stand until the specific dates are continued.
As with other aspects of the COVID-19 health crisis, the impact upon Civil Litigation continues to evolve, for the most up to date information we include the following links to the California Courts. The first page includes links to all the State and County Orders, the second page is for the Judicial Council Rules.
Links:
https://newsroom.courts.ca.gov/news/court-emergency-orders-6794321
https://newsroom.courts.ca.gov/news/judicial-branch-emergency-actions-criminal-civil-and-juvenile-justice
STATE AND LOCAL STAY AT HOME ORDERS
The State of California declared a state of emergency on March 4, 2020. On March 13, 2020 the President declared a national state of emergency. On March 19, 2020 Governor Newsom issued Executive Order N-33-20, also known as the “Stay at Home” order. This orders all Californian’s to stay at home, unless they are part of an essential businesses are exempt which generally includes construction and insurance. Generally, Californians are allowed to run essential errands, but they are not to congregate with those outside of their household.
In addition to the State, many cities and counties have enacted additional orders regarding whether certain types of businesses can remain open, use of parks, trails and other public amenities as well as what type of protective measures must be adhered to such as covering your face in public. As with Civil Litigation, the State and Local Government regulations continue to evolve. A link to the State’s COVID-19 page is below and we also encourage you to check your local City and County sites for additional information.
https://covid19.ca.gov/
BUSINESS AND FINANCIAL GUIDELINES
The impact of COVID-19 is unprecedented. While “essential businesses” may remain open for customers, steps must be taken to protect the health of both employees and customers. There are both State and, in many instances, Local Government regulations addressing these precautions. In addition to taking safety measures to protect the health of all involved, there are a multitude of financial concerns to be addressed. While most people have already heard about the moratorium on residential and commercial evictions, this does little to address how property owners will receive funds to pay their financial obligations, how tenants can pay their other obligations, how either can make payroll and most importantly, how employees who can no longer work due to their “non-essential” business being closed can put food on their tables.
The Coronavirus Aid, Relief, and Economic Security Act (the “CARES” act) may provide financial relief for many business by means of loans, some of which may be forgivable, and tax credits. The CARES act also modifies the Family Medical Leave Act (“FMLA”) to provide paid leave for those who cannot work due to COVID-19 as well as other benefits. The IRS has extended the deadline to file and pay taxes to July 15, 2020. Additionally, there are other Federal and State benefits which may be available for those whose jobs are impacted.
The financial impacts of COVID-19 are far reaching and continue to evolve. The Department of Insurance ordered insurance companies to return premiums for at least the months of March and April. This applies to certain lines of insurance where the risk of loss has fallen substantially. However, business interruption, environmental and pollution claims have increased exponentially. While most such policies require some physical damage in order to trigger an occurrence, there has been some discussion of legislation deeming the COVID-19 pandemic to fulfill the physical damage requirement.
If your business has been closed or impacted by COVID-19 we encourage you to review your insurance policies and key contracts to ascertain what your rights and obligations are as well as whether you may have any coverage for your losses. Just as importantly, speak with your business partners including vendors, customers and employees to ascertain their capabilities and willingness to work through this crisis.
US Department of Labor OSHA Guidelines:
https://www.osha.gov/SLTC/covid-19/
California Labor & Workforce Development Agency Resource Page:
https://www.labor.ca.gov/coronavirus2019/
California Employment Development Department:
https://www.edd.ca.gov/about_edd/coronavirus-2019.htm
CONSTRUCTION GUIDELINES
Many of our clients are involved in the construction industry. Construction has been deemed an essential activity and is exempt from many of the “stay at home” orders but certain protections and regulations still apply. In addition to the general workplace guidelines discussed above certain jurisdictions are providing guidance as to how to provide a safe construction site workplace. We have included a link the Los Angeles Department Building and Safety guidelines below.
However, in some instances work on a project may be delayed or may not be able to progress due to the project owner stopping work or the inability of subcontractors or suppliers to continue as originally intended. In this case one should review their contracts to see what justifies delay and inability to perform by either party and the impact thereof. Contracts should also be evaluated to ascertain whether the costs associated with compliance with the new COVID-19 regulations are a recoverable cost under the contract. As with the general business discussion above, contractors should review all available insurance, including builder’s risk to ascertain the existence of possible coverage.
LA DBS guidelines:
https://ladbs.org/docs/default-source/publications/misc-publications/construction-site-guidance.pdf
SUMMARY
The COVID-19 health crisis has had and, for the foreseeable future, will have a broad and severe impact on our society. The variety of evolving regulations on the Federal, State and Local Government levels make it challenging to comply, especially for businesses in operation. There are also a variety of resources available to help ensure compliance with these regulations as well as the financial and physical viability of our communities’ companies and employees. Please do not hesitate to contact us if you need any assistance in navigating these rules and resources.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean & Roeb and
Brian D. Kahn, Chapman Glucksman Dean & Roeb
Mr. Glucksman may be contacted at rglucksman@cgdrlaw.com
Mr. Kahn may be contacted at bkahn@cgdrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
DoD Will Require New Cybersecurity Standards in 2020: Could Other Agencies Be Next?
September 09, 2019 —
Alexander Gorelik - Smith CurrieThe Department of Defense (DoD) has announced a new five-tier standard for cybersecurity certification, which it calls the Cybersecurity Maturity Model Certification, or “CMMC”. Taking an unusual approach to informing the industry, the DoD has provided only limited information about the new standard through its website and a “road tour” led by the newly-appointed head of the DoD’s Chief Information Security Office (CISO), Ms. Katie Arrington.
During her recent presentation at the National Institute of Standards and Technology’s (NIST’s) Information Security and Privacy Advisory Board (ISPAB) meeting, on August 8, 2019, Ms. Arrington revealed several new details about the requirements. Outlined below are the most significant facts from that presentation and the DoD’s website:
All companies doing business with DoD (and all tiers of subcontractors) will need to obtain CMMC certifications.
DoD will require the new certifications from all contractors (including suppliers and subcontractors) that are performing under a DoD contract. Even contractors that do not process or handle Controlled Unclassified Information (CUI) must obtain CMMCs.
Read the court decisionRead the full story...Reprinted courtesy of
Alexander Gorelik, Smith CurrieMr. Gorelik may be contacted at
agorelik@smithcurrie.com