Termination for Convenience Clauses: Maybe More Than Just Convenience
June 06, 2022 —
Robert C. Shaia - ConsensusDocsA contractor begins work on a project and everything is going well, until one day the owner informs the contractor that it is being terminated for convenience. Possibly, there is no discussion about alleged defects, reasons for the termination, or any damages the owner might seek against the contractor. In that moment, the contractor may be unaware of any perceived wrongdoing or problems with its work.
The industry has typically accepted that, in this scenario, the owner implicitly waives the right to any remedies against the contractor, except those expressly set forth in the contract. Reasonable minds might assume that, if the owner believed it needed to seek further remedies, it would terminate the contractor for cause instead of convenience. And often overlooked during contract negotiations are the benefits of including an express “waiver of remedies” in the termination for convenience section.
Read the court decisionRead the full story...Reprinted courtesy of
Robert C. Shaia, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Mr. Shaia may be contacted at
rshaia@watttieder.com
Enforceability of Contract Provisions Extending Liquidated Damages Beyond Substantial Completion
April 15, 2024 —
Stu Richeson - The Dispute ResolverThis post takes a look at the enforceability of contract provisions providing for liquidated delay damages after substantial completion. Typically, the assessment of liquidated delay damages ends at substantial completion of a project. However, various standard form contracts, including some of the ConsensusDocs and EJCDC contracts, contain elections allowing for the parties to agree on the use of liquidated damages for failing to achieve substantial completion, final completion, or project milestones. The standard language in the AIA A201 leaves it up to the parties to define the circumstances under which liquidated damages will be awarded.
Courts are split on the enforceability of provisions that seek to assess liquidated damages beyond substantial completions. Courts in some jurisdictions will not impose liquidated damages after the date of substantial completion on the ground that liquidated damages would otherwise become a penalty if assessed after the owner has put the project to its intended use. Perini Corp. v. Greate Bay Hotel & Casino, Inc., 129 N.J. 479, 610 A.2d 364 (1992). When the terms are clear, other jurisdictions will enforce contract terms providing for liquidated damages until final completion, even if the owner has taken beneficial use of the facility. Carrothers Const. Co. v. City of S. Hutchinson, 288 Kan. 743, 207 P.3d 231 (2009).
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Construction Defect Suit Can Continue Against Plumber
June 28, 2013 —
CDJ STAFFThe Kansas Court of Appeals has reversed a district court ruling that a homeowner’s suit against a plumber was barred under the economic loss doctrine. However, subsequently the Kansas Supreme Court “refused to extend the economic loss doctrine to homeowner claims against construction contractors.” In light of this, the appeals court sent the case back to the lower court.
The case, Coker v. Siler, was brought by Gregory Coker, who had bought a home from J.M.C. Construction. JMC purchased an unfinished house from Michael D. Siler in August 2006. As part of the completion process, John M. Chaney, the president of JMC, installed the water line into the residence. Mr. Coker bought the home in September 2007.
Starting in April 2008, Mr. Coker noticed that his water bills had increased. Mr. Coker could find “no evidence of a leak above the ground,” so he contacted JMC Construction. Mr. Chaney had R.D. Johnson Excavation dig up the water line, after which a gap was discovered that had been allowing water to flow under the foundation. In addition to the higher water bills, an engineer determined that the water “resulted in cracks in the wall and uneven doors.”
Mr. Coker sued, Siler, J.M.C. and Chaney for negligence, breach of implied warranty, strict liability, and breach of express warranty. J.M.C. and Chaney requested a summary judgment. The court dismissed Mr. Coker’s claims of negligence, strict liability, and breach of implied warranty on the basis of the economic loss doctrine, rejecting a petition from Mr. Coker to reconsider. The court, however, allowed Mr. Cocker to proceed with his claim of express warranty. In December, 2011, Mr. Coker accepted an offer from J.M.C. of $40,000.
Mr. Coker then appealed the summary judgment, making the claim that while the court’s decision was based on Prendiville v. Contemporary Homes, Inc., this has now been overruled by David v. Hett. In this case, “the court ultimately found the rationale supporting the economic loss doctrine failed to justify a departure from a long time of cases in Kansas that establish a homeowner’s right to assert claims against residential contractors.” The appeals court concluded that “although the district court properly relied on the law as it existed at the time of its ruling, the intervening change in the law necessarily renders the conclusion reached by the district court erroneous as a matter of law.”
In sending this case back to the district court, the appeals court noted that the lower court will need to determine if the “defendant accused of negligence did not have a duty to act in a certain manner towards the plaintiff,” in which case “summary judgment is proper. Mr. Coker claims that Mr. Chaney did indeed have this duty.
Further, Mr. Coker claimed that Mr. Chaney had a duty arising out of implied warranty. The appeals court questioned whether the district court properly applied the economic loss doctrine to this claim, because despite being president of the construction company, Mr. Chaney “in his individual capacity as a plumber performing work for Coker, was not a party to the J.M.C. contract.” The court found that “Coker’s claim that Chaney breached an implied duty within such a contract fails as a matter of law.”
However, the court did uphold Cocker’s claim of a contractor liability for injury to a third party, noting that “Chaney owed Coker a legal duty independent of Coker’s contact with J.M.C.” The appeals court left it to the district court to determine if the defect that caused the damage was present when the house left J.M.C.’s possession.
The case was reversed and remanded “with directions to reinstate Coker’s claim of negligence against Chaney in his individual capacity as a plumber.”
Read the court decisionRead the full story...Reprinted courtesy of
Commonwealth Court Holds That Award of Attorney's Fees and Penalties is Mandatory Under the Procurement Code Upon a Finding of Bad Faith
October 29, 2014 —
William J. Taylor and Michael Jervis – White and Willams LLPIn a decision regarding a payment claim by a highway contractor against the City of Allentown, the Commonwealth Court of Pennsylvania has held that an award of attorney's fees and penalties is mandatory under the terms of the Pennsylvania Procurement Code, 62 Pa.C.S. § 3901 et seq., upon a finding of bad faith by the non-paying government agency, even though the statute only states that a court “may” award such fees and penalties.
In A. Scott Enterprises, Inc. v. City of Allentown, Cmwlth. Ct. No. 2163 C.D. 2013, the plaintiff, A. Scott Enterprises, Inc. (Scott), won a contract with the City of Allentown (City) to construct a one mile roadway. Several weeks after commencing work, Scott learned that soil at the construction site was potentially contaminated with arsenic, and was instructed by the City to suspend its work. Because of the soil contamination, additional work would be required to complete the project and Scott submitted proposals for the additional work plus its suspension costs. However, the City never approved the additional work and the project was never completed. The City never paid Scott for costs incurred due to the suspension of the work and Scott filed suit to recover its losses. The jury found that the City had breached the contract with Scott and had acted in bad faith in violation of the Procurement Code, and awarded damages to Scott for its unreimbursed suspension costs. However, the trial court denied Scott’s request for an award of attorney's fees and penalty interest. Both Scott and the City appealed the final judgment to the Commonwealth Court, which reversed the trial court’s refusal to award attorney's fees and penalties.
Reprinted courtesy of
William J. Taylor, White and Williams LLP and
Michael Jervis, White and Williams LLP
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com; Mr. Jervis may be contacted at jervism@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Injury to Employees Endorsement Eliminates Coverage for Insured Employer
February 01, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted summary judgment to the insurer based upon an endorsement which barred coverage for injuries to employees. Northfield Ins. Co. v. Z&J Mgt. LLC, 2020 N.Y. Misc. LEXIS 10801 (N.Y. Sup. Ct. Dec. 18, 2020).
Ravi Sooklal sued his employer, Z&J Management LLC (Z&J), for injuries at the job site. Northfield, who had issued a CGL policy to Z&L, denied coverage based upon two endorsements. The first was titled "Injury to Employees of Insureds" and the second was "Employers' Liability." Northfield sued for a declaratory judgment and now moved for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Three Construction Workers Injured at Former GM Plant
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFIn Linden, New Jersey, three construction workers were injured “when they were apparently struck by steel girders while working at the former General Motors site” police told NJ.com.
Mayor Richard Gerbounka stated that the “[s]ix struts that would support the deck or ceiling of a warehouse collapsed.” He also mentioned that the city “has been trying to redevelop the former General Motors site for years, but has run into several obstacles, including lawsuits from nearby businesses opposed to retail construction.”
Several construction vehicles were “nearly buried under” debris and “[a]t least one I-beam girder and several decking struts—all metal—remain across several heavy construction vehicles,” NJ.com reported. The owner of the vehicles stated “he was told that workers were standing around the vehicles preparing to start their day when high winds knocked down at least one I-beam and several metal decking struts.”
In another article published late afternoon on March 26th, NJ.com reported that “high winds” were the cause of the accident. “The federal Occupational Safety and Health Administration is investigating the accident and all work at the site has been suspended pending the investigation,” according to the article. “Officials said OSHA inspectors had been at the scene once before, but declined to give details because of a continuing investigation.”
Read the full story, NJ.com AM...
Read the full story, NJ.com PM... Read the court decisionRead the full story...Reprinted courtesy of
Insurer Could Not Rely on Extrinsic Evidence to Circumvent Its Duty to Defend
February 14, 2023 —
Lorelie S. Masters & Yaniel Abreu - Hunton Insurance Recovery BlogIn
First Mercury Insurance Co. v. First Florida Building Corp., et al., a federal district court ordered that an insurer had a duty to defend its insured against an underlying personal injury lawsuit. 2023 WL 23116, at *1 (M.D. Fla. Jan. 3, 2023). First Mercury is a cautionary tale about how insurers may try to circumvent their obligations by improperly considering extrinsic evidence when determining whether they have a duty to defend their insureds.
First Mercury is a coverage dispute over an underlying personal injury lawsuit that was filed against the insured, a construction company, for injuries the claimant allegedly sustained at a construction site. Id. The claimant alleged that he was at the construction site as an invitee who was “working with” the insured. Id. The insurer agreed to defend the insured against the personal injury lawsuit under a reservation of rights. Id. However, the insurer filed a coverage action seeking a declaration that coverage for the personal injury lawsuit was excluded under the policy. Id. Specifically, the insurer, on summary judgment, argued that the claimant was an employee of the insured who was injured in the course of his employment, thus falling within the employer’s liability and workers’ compensation exclusions in the policy. Id. Although the insurer acknowledged that the personal injury complaint against the insured triggered its duty to defend under the policy, the insurer argued that those exclusions relieved its duty to defend or indemnify the insured. Id.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Yaniel Abreu, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Abreu may be contacted at yabreu@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Condominium Association Files Construction Defect Suit
December 10, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to The Real Deal, “The condominium association at 15 Union Square West has filed a $5 million lawsuit against developer Brack Capital Real Estate eight years after the building first launched sales, alleging that the firm did not deliver the quality of units it promised when residents originally signed their contracts.”
Alleged problems include roof leaks, lack of terrace landscaping, and patchy electrical work, The Real Deal reported.
A spokesperson for Brack stated, “We stand behind our product and are very proud of it.”
Read the court decisionRead the full story...Reprinted courtesy of