Court Affirms Summary Adjudication of Bad Faith Claim Where Expert Opinions Raised a Genuine Dispute
July 06, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn 501 East 51st Street etc. v. Kookmin Best Ins. Co., Ltd. (No. B293605, filed 4/2/20, ordered pub. 4/16/20), a California appeals court affirmed summary adjudication and dismissal of a bad faith claim based on the genuine dispute doctrine.
501 East 51st Street Long-Beach-10, LLC (501) was the owner of a 10-unit apartment complex, insured by Kookmin Best. In 2017, an underground water main alongside the building burst which, according to 501, caused the building to move and crack. 501 made a claim and supplied a geotechnical report finding cracks in the foundation walls, cracks in the stucco and significant floor deformation and tilting near the water leak. The engineer’s opinion concluded that that “existing building distress was substantially contributed to by the water main break. The water introduced to the soil medium appears to have triggered differential foundation movement causing the stress features to develop.”
Kookmin retained its own engineers to investigate, who returned an opinion that the leak had exacerbated long-term pre-existing settlement which would continue. Under the policy, damage to the building caused by earth movement and settlement were excluded, but water damage resulting from an “accidental discharge” of water was covered. Kookmin then obtained an opinion from coverage counsel, who opined that only damage allocable to the water leak would be covered.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Policy Reformed to Add New Building Owner as Additional Insured
July 10, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe lower court correctly reformed the policy to replace the prior owner with the new owner as an additional insured under the policy. Wesco Ins. Co. v. Fulmont Mut. Ins. Co., 2023 N.Y. App. Div. LEXIS 2650 (N. Y. App. Div. May 11, 2023).
Beyond was sued as owner of the building in a personal injury lawsuit. The former owners leased the building to the tenant who included the then-owners as additional insureds under the tenant's policy. When the deed to the building was transferred to Beyond, the additional insured endorsement in the tenant's policy was not updated to reflect the change in ownership.
Beyond's insurer, Wesco, tendered the lawsuit to the tenant's insurer, Fulmont. Coverage was denied because Beyond was not an additional insured under the tenant's policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Giving Insurance Carrier Prompt Notice of Claim to Avoid “Untimely Notice” Defense
June 12, 2023 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to giving your insurance carrier notice of claim, I am an advocate of providing that notice as soon as possible, i.e., prompt notice. The reason is to take away the carrier’s argument to deny coverage because you, as the insured, failed to provide it with prompt notice—the “untimely notice” defense. It doesn’t matter whether it is a first party property insurance claim or third-party liability policy claim, provide notice as soon as reasonably possible to take away that “untimely notice” defense.
The “untimely notice” defense was the issue in Benson v. Privilege Underwriters Reciprocal Exchange, 48 Fla.L.Weekly D1085a (Fla. 6th DCA 2023) dealing with a first party property insurance policy. In this case, eighteen months after Hurricane Irma, the plaintiff noticed a smell and observed brown stains on walls and ceiling in his home. The plaintiff called roofing companies to inspect the damage and perform certain repairs. However, the plaintiff still noticed the smell so he called a company to test and remediate mold. The plaintiff, then, contacted his property insurer with numerous claims relative to the leaks and damage. Although there was an initial property insurance payment made, the carrier ultimately denied coverage for subsequent claims stating that “the late notice of the claim and the prior repairs to the roof substantially prejudiced its ability to complete an inspection of [plaintiff’s] property to evaluate the claim.” Benson, supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
7 Sustainability Ideas for Modular Classrooms in the Education Industry (guest post)
June 10, 2015 —
Melissa Dewey Brumback – Construction Law in North CarolinaToday, a guest post on sustainable modular classrooms from Kathy Werder, a freelance architect by profession and a researcher by nature. According to Kathy, most of her research papers focus on promoting integration that leads to sustainable and lean design and construction practices. Kathy is obsessed with the latest rage in the construction industry – modular building solutions. She is also an avid writer, and loves blogging about green buildings and portable construction units. Welcome, Kathy!
According to Wikipedia, a sustainable building refers to “ a structure and using process that is environmentally responsible and resource-efficient throughout a building’s life-cycle from sitting, to design, construction, operation, maintenance, renovation, and demolition.”
So if we accept this definition to be true, in order to make an actual sustainable building we have to consider the entire process of building right from the blueprint stage all the way to demolition, and ensure that at every step of the way there is minimal or no negative impact on the environment, especially in terms of resource efficiency.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Buyer Beware: Insurance Agents May Have No Duty to Sell Construction Contractors an Insurance Policy Covering Likely Claims
May 20, 2024 —
David McLain - Higgins, Hopkins, McLain & Roswell, LLCConstruction contractors in the market for insurance coverage have few legal protections if their insurance agent fails to provide insurance that covers likely claims against the contractor. As construction defect lawsuits continue to be a frequent occurrence throughout Colorado, we have seen an increase in the number and complexity of coverage endorsements and exclusions in insurance policies. Some of these exclusions result in insurance policies that are essentially useless to the contractor who purchased them. For example, we have seen dirt work contractors with earth movement exclusions or an earth movement sublimit that turns their $2 million policy into a $100,000 policy. We have seen contractors who primarily build tract homes in subdivisions with tract home exclusions. We have seen general contractors whose policies state that every subcontractor must name the contractor as an additional insured or else the general contactor’s policy converts from a seven-figure policy to a five-figure policy with eroding limits (meaning that the attorney’s fees, expert fees, and litigation costs reduce the coverage limits). The list goes on and leads to an unfortunately high number of contractors who pay significant sums for their insurance policies, finding themselves uninsured or underinsured.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Construction Mediation Tips for Practitioners and 'Eyes Only' Tips for Construction Mediators
December 05, 2022 —
Stacy L. La Scala - Construction ExecutiveConstruction mediation can occur during or after construction and prior to or during arbitration or litigation. But, regardless of when a construction mediation occurs, its success often depends on the parties’ willingness to exchange critical information well in advance of the mediation session.
Tips for the Construction Practitioner
- Schedule a mandatory pre-session call.
A pre-session call with the mediator is the first and most effective opportunity to convey your client’s position and to allow the mediator to absorb and evaluate that information without distraction. On that call, counsel should describe the dispute and identify the decision-makers. Additionally, counsel should address the following questions:
- Are the parties working together and sharing information, or are they at war?
- Have the parties shared expert information?
- Have demands been published?
- Will the parties be publishing their briefs?
- What confidential information is not in the mediation brief?
- Will the decision-makers be participating? Are there any decision-makers who are not available or “behind the scenes”?
Reprinted courtesy of
Stacy L. La Scala, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mediation is (Almost) Always Worth a Shot
October 17, 2022 —
Christopher G. Hill - Construction Law MusingsAs Hurricane Ian is bearing down on Florida the economy is sputtering, it is easy to lose track of things that construction professionals (among others) can control. One of those things is how to resolve your construction dispute. When initial, and hopefully business-oriented, discussions break down and the construction lawyers get involved, often more formal means are required. One “formal” possibility that should always be considered and almost always attempted is the mediation of your dispute.
I know, I pound this particular gavel often. Why? Because not only are litigation and arbitration expensive and time-draining, you are putting your fate in the hands of a judge or arbitrator to decide. Let’s face it, most contractors (and solo construction lawyers for that matter) want as much control over their businesses and projects as possible. Mediation is the only third-party dispute resolution process that allows the parties to decide their own mutual fate. This is one of the primary reasons I almost always recommend that my clients try mediation before or after filing their lawsuit or arbitration demand.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Best Practices in Construction– What are Yours?
November 26, 2014 —
Craig Martin – Construction Contractor AdvisorThe latest Engineering News Record had an interesting article on
Best Practices in Construction written by Deron Cowan of Zurich Services Corporation. In the articles, Mr. Cowan emphasizes the importance of best practices and the methodology to develop them.
As Mr. Cowan notes, best practices are intended to eliminate, reduce and manage risks and all construction companies should be fully engaged in correctly executing and accomplishing risk analysis to meet the demands of their practices.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com