Is Modular Construction Destined to Fail?
March 11, 2024 —
Aarni Heiskanen - AEC BusinessThe construction sector is a harsh environment for innovation. I’ve been following the story of one Finnish innovative contractor, Lehto Group, over the years with enthusiasm. I was saddened to hear that the group’s three significant subsidiaries joined the ranks of many Finnish contractors who have filed for bankruptcy over the last six months.
Lehto developed industrialized building concepts and had its own production facilities. The company had a promising start but eventually ran into problems. Was the industrial approach a mistake, or were other factors contributing to the firm’s fall?
Three Contributing Factors
Lehto Group’s collapse was not a surprise to its competitors, who had observed warning signs years prior. The company’s order book plummeted in 2024 despite still employing around 500 workers. Rakennuslehti, the leading construction magazine in Finland, asked three experienced industry professionals to give their views on Lehto’s failure. The interviewees spoke anonymously due to the small size of the Finnish market and the sensitive nature of commenting on a competitor’s matters.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Substituting Materials and Failure to Comply with Contractual Requirements
November 19, 2021 —
David Adelstein - Florida Construction Legal UpdatesIt is important to remember that if you are going to substitute materials from those specified, you need to make sure there is proper approval in doing so–make sure to comply with the contractual requirements to substitute materials. Otherwise, you could be in a situation where you are contractually required to remove the installed substituted materials and replace with the correct specified materials. This is not the situation you want to find yourself in because this is oftentimes a costly endeavor. This was the situation in Appeal-of-Sauer, Inc., discussed below, on a federal project. The best thing that you can do is comply with the contractual requirements if you want to substitute materials. If you are in the situation where it is too late, i.e., you already installed incorrect materials, you want to demonstrate the substituted materials are functionally equivalent to the specified materials and/or come up with an engineering solution, as required, that could be less costly then ripping out the installed material and replacing with the correct material. Even doing so, however, is not a “get out of jail free card” and does not necessarily mean there is not a strong basis to require you to install the correct specified material.
In Appeal of- Sauer, Inc., ASBCA 61847, 2021 WL 4888192 (ASBCA September 29, 2021), a federal project’s engineering requirements required cast iron piping for the above ground sanitary system. However, the prime contractor installed PVC piping instead of cast iron piping. The prime contractor believed it had the appropriate approval through its submittal. The government, through its contracting officer, directed the prime contractor to remove installed PVC piping to replace with cast iron. The government did not believe PVC piping was the functional equivalent of cast iron piping for the above ground sanitary system due to its concern with the noise level of waste materials flowing through the piping. The prime contractor submitted a claim for its removal and replacement costs which was denied by the contracting officer. On appeal with the Armed Services Board of Contract Appeals, the Board agreed with the contracting officer explaining: “While we agree that a design change could be approved by the designer of record and brought to the attention of the government before being incorporated into the design documents, the [prime contractor’s] task order required that such a design change meet the minimum requirements of the solicitation and accepted proposal. The plumbing submittal [the prime contractor] issued here, showing the use of PVC instead of cast iron for the above ground waste piping, did not meet the minimum requirements of the solicitation.” Appeal of-Sauer, Inc., supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Contractor's Agreement to Perform Does Not Preclude Coverage Under Contractual Liability Exclusion
January 31, 2014 —
Tred R. Eyerly – Insurance Law HawaiiIn a much anticipated decision, the Texas Supreme Court ruled that a general contractor who agrees to perform its work in a good and workmanlike manner does not "assume liability" for damages arising out of its defective work so as to trigger the Contractual Liability Exclusion. Ewing Constr. Co., Inc. v. Amerisure Ins. Co., 2014 Tex. LEXIS 39 (Tex. Jan.17, 2014).
Ewing signed an agreement with the School District to serve as general contractor to renovate and build additions to a school, including tennis courts. After construction was completed, the tennis courts started flaking, crumbling, and cracking. The School District filed suit, alleging breach of contract and negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Congress Addresses Homebuilding Credit Crunch
May 20, 2011 —
CDJ STAFFThe National Association of Home Builders (NAHB) reports that Representatives Gary Miller (CA), Brad Miller (NC) and twenty-nine cosponsors have put forth a bill with bipartisan support to “address the severe credit crunch for acquisition, development, and construction (AD&C) financing.” They report in addition to more than 1.4 million construction workers who have been “idled since 2006,” the housing slump has cost 3 million jobs and $145 million in wages.
NAHB reports that they worked closely with lawmakers on the bill. The association had members meet with legislators both in D.C. and in their home districts. They state that HR 1755 would help homebuilders “find the credit they need to move forward with new or existing projects.”
The bill would allow lenders to use the value upon completion when assessing loan collateral and ban the use of foreclosed or distressed sale properties in assessing values of projects. The would bill would also lessen restrictions by banking regulators, which the lead sponsors said “have hindered federal and state chartered banks and thrifts’ ability to make and maintain loans to qualified small home builders that have viable projects.”
The NAHB is urging members of Congress to cosponsor the bill and is urging the Senate to introduce a companion bill.
Read the full story…
Read HR 1755
Read the court decisionRead the full story...Reprinted courtesy of
A Contractual Liability Exclusion Doesn't Preclude Insurer's Duty to Indemnify
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Traub Lieberman Straus & Shrewsberry LLP's blog, "[I]n Crownover v. Mid-Continent Cas. Co., 2014 U.S. App. LEXIS 20737 (5th Cir. October 29, 2014), the United States Court of Appeals for the Fifth Circuit withdrew its prior ruling and held that the contractual liability exclusion did not preclude an insurer’s duty to indemnify its insured for an award resulting from the insured’s defective construction."
The case involved the Crownovers who were awarded damages for "Arrow's breach of paragraph 23.1 of the construction contract." However, Arrow then filed for bankruptcy. Mid-Continent, Arrow's insurer, denied Crownovers' demand for recovery, stating that "the contractual liability exclusion applied because the arbitrator’s award to the Crownovers was based only on Arrow’s breach of paragraph 23.1 of the construction agreement." The court agreed with Mid-Continent.
Subsequently, the fifth court of appeals "reversed the district court’s ruling and awarded summary judgment in favor of the Crownovers."
Read the court decisionRead the full story...Reprinted courtesy of
Tech Focus: Water Tech Getting Smarter
June 05, 2023 —
Pam McFarland - Engineering News-RecordIn early December 2021, the Denver International Airport made headlines across the U.S. after a hot water pipe broke a month before a major terminal expansion project was expected to complete. The scalding water spilled on floors and across the airport concourse, causing $50 million in damage and a nine-month delay to the project.
Reprinted courtesy of
Pam McFarland, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Lakewood Introduced City Ordinance to Battle Colorado’s CD Law
September 24, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Denver Post, the Lakewood City Council “introduced an ordinance that would make it more difficult for homeowners associations to sue developers for construction defects and give builders more opportunity to fix problems before litigation begins.” A hearing and final vote is scheduled for October 13th.
"If there are defects, we want to get them fixed rather than dragging this through the courts for years," Lakewood Mayor Bob Murphy told The Denver Post. Murphy believes the ordinance will bring “more diverse housing options to Lakewood, especially around stations along the Regional Transportation District’s West Rail Line.” Lakewood’s City Planner Travis Parker also declared that the defects law is to blame for the lack of condos in the area.
However, some believe that “Lakewood is overstepping its bounds as a home-rule city,” according to The Denver Post. "What they're trying to do is use an ordinance to circumvent state law in order to make it impossible for homeowners to seek redress against builders for defects," Molly Foley-Healy an attorney who serves as legislative liaison for the Community Associations Institute's Legislative Action Committee told the Post. “Mayor Murphy needs to incentivize quality construction in Lakewood instead.”
Read the court decisionRead the full story...Reprinted courtesy of
Five Issues to Consider in Government Contracting (Or Any Contracting!)
September 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesThe appeal of Appeals of – Konecranes Nuclear Equipment & Services, LLC, ASBCA 62797, 2024 WL 2698011 (May 7, 2024) raises interesting, but important, issues that should be considered. In this case, the government (in a supply contract) procured four portal cranes from the claimant. After an initial test of one of the cranes failed, the government refused to accept delivery even after the issue was addressed by the claimant. The government did not accept the manner in which the claimant addressed the issue and would only accept cranes if the claimant employed “an unnecessary alternative solution [that] caused further delay and increased [claimant’s] costs.” On appeal, it was determined the government’s decision to delay delivery based on its demand for the alternative solution was not justified, i.e., constituted a breach of contract. Below are five issues of consideration in government contracting, or, for that matter, any contracting.
Issue #1- Patently Ambiguous Specifications
The government argued that the specifications were patently ambiguous and because the claimant failed to inquire regarding the ambiguous specifications prior to performance, its interpretation of the ambiguous specifications should govern. The contractor countered that the specifications were unambiguous and it met the specifications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com