New York Court of Appeals Addresses Choice of Law Challenges
August 20, 2018 —
Grace V. Hebbel - Saxe Doernberger & Vita, P.C.In June, the New York Court of Appeals examined the application of a New York Choice of Law provision in a contract – a determinative issue for the case. In Ontario, Inc. v. Samsung C&T Corp., the issue was whether the plaintiff’s claims were subject to Ontario, Canada’s 2-year statute of limitations or New York’s 6-year statute of limitations for breach of contract where the contract contained a broad New York Choice of Law provision. The court found that pursuant to New York’s borrowing statute, Ontario’s more restrictive statute of limitations applied. The action was dismissed as time-barred, serving as a harsh reminder of the potential effects of choice of law and limitations periods.
The suit arose out of the following facts. In 2008, an Ontario renewable energy developer, SkyPower Corp. (“SkyPower”), entered into a Non-Disclosure Agreement (NDA) with the defendants which allowed the defendants to review SkyPower’s confidential and proprietary information. The review was conditioned on restricted disclosure and the requirement that the information would be destroyed after review.
Read the court decisionRead the full story...Reprinted courtesy of
Grace V. Hebbel, Saxe Doernberger & Vita, P.C.Ms. Hebbel may be contacted at
gvh@sdvlaw.com
Hawaii Federal District Court Rejects Insurer's Motion for Summary Judgment on Construction Defect Claims
November 06, 2018 —
Tred R. Eyerly - Insurance Law HawaiiTaking into consideration a "Revised Occurrence Endorsement," the federal district court determined the insurer had a duty to defend. Gemini Ins Co. v. Constrx Ltd., 2018 U.S. Dist. LEXIS 163453 (D. Haw. Sept. 24, 2018).
Constrx Ltd. (CRX) contracted with the AOAO to perform remedial construction repairs to condominium buildings and apartment units. CRX asserted that it completed all work, including charge orders and punch list items and it left the site. CRX was paid less that the contract amount and demanded arbitration against the AOAO. In the arbitration the AOAO relied upon a report by Posard Brock & Associates (PBA) Report which set forth the AOAO's claims against CRX, including corrective work, remaining punch list work, construction delay costs, cost overruns, and other items justifying its payment than less that the contract amount.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Predicting Our Future with Andrew Weinreich
May 03, 2017 —
Aarni Heiskanen - AEC BusinessIn this podcast episode, my guest is Andrew Weinreich. We talk about the future of homebuilding against the backdrop of Andrew’s new podcast Predicting Our Future.
Is construction ripe for disruption? Andrew believes that homebuilding is much closer to a tipping point than ever before. In this interview, he explains why.
“In the United States, modular construction significantly lags behind what we see elsewhere around the world,” Andrew reminds. “When everything you can imagine today, from the paperclip to your smartphone is made in a factory, why is it that -certainly in this country- we associate homes made in factory with the lowest of low end homes.”
“The first question is: why is that? And the second question is: could that change? Could we be on the precipice of looking at the next Tesla; not for car-building, but for homebuilding.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Trucks looking for Defects Create Social Media Frenzy
July 23, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Willits News, slow-moving trucks with cameras attached rolled through Fort Briggs, attracting attention from homeowners in the community. People began mentioning the trucks on social media sites, with questions regarding what the cameras on the trucks were recording.
Osmose Utilities General Manager, Jason Milligan, told Willits News that the trucks were “surveying overhead power poles and lines for PG&E.”
"We're not looking for anything but what's overhead," Mulligan said, according to Willits News. "We find defects or issues with construction ... 20 or 30 feet off the ground, which are safety issues. We don't scan anything down towards people's homes."
Read the court decisionRead the full story...Reprinted courtesy of
Trump Order Waives Project Environment Rules to Push COVID-19 Recovery
June 15, 2020 —
Debra K. Rubin, Mary B. Powers & Jim Parsons - Engineering News-RecordCiting the "national emergency" spurred by the COVID-19 pandemic's economic hit, President Donald Trump has signed an executive order that directs federal agencies to bypass environmental laws to expedite infrastructure projects, including those on federal lands, as a stimulus.
Reprinted courtesy of Engineering News-Record attorneys
Debra K. Rubin,
Mary B. Powers and
Jim Parsons
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Hunton Policyholder’s Guide to Artificial Intelligence: SEC’s Recent AI-Washing Claims Present D&O Risks, Potential Coverage Challenges
July 08, 2024 —
Geoffrey B. Fehling, Michael S. Levine & Alex D. Pappas - Hunton Insurance Recovery BlogWe have previewed in prior posts the ways artificial intelligence is rapidly changing the way business operate, including the many ways AI has influenced the insurance market, creating both opportunities and risks for policyholders. We later highlighted, based on a recent securities lawsuit, how corporate management may be at risk for the alleged use or misuse of AI and how companies should evaluate their directors and officers (D&O) and management liability policies to ensure that they are prepared to respond to and mitigate AI-driven risks, including claims alleging that a company or its officers and directors made misrepresentations about AI.
That potential risk now has regulatory teeth, as the US Securities and Exchange Commission recently charged the founder of an AI hiring startup with fraud based on claims about using AI to help clients find diverse and underrepresented candidates to fulfill diversity, equity, and inclusion hiring goals.
Reprinted courtesy of
Geoffrey B. Fehling, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Alex D. Pappas, Hunton Andrews Kurth
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Pappas may be contacted at apappas@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Design and Construction Defects Not a Breach of Contract
February 14, 2013 —
CDJ STAFFThe California Court of Appeals tossed out a breach of contract award in Altman v. John Mourier Construction. The decision, which was issued on January 10, 2013, sent the construction defect case back to a lower court to calculate damages based on the conclusions of the appeals court.
The case involved both design issues and construction issues. According to the plaintiffs’ expert, the design plans did not make the buildings sufficiently stiff to resist the wind, and that the framing was improperly constructed, further weakening the structures, and leading to the stucco cracking. Additionally, it was alleged that the roofs were improperly installed, leading to water intrusion. The contractor’s expert “agreed the roofs needed repair, but disputed what needed to be done to repair the roofs and the cost.”
The jury rejected the plaintiffs’ claims of product liability and breach of warranty, but found in their favor on the claims of breach of contract and negligence. The plaintiffs were awarded differing amounts based on the jury’s conclusions about their particular properties.
Both sides sought new trials. JMC, the contractor, claimed that the jury’s verdicts were “inconsistent in that the relieved JMC of liability for strict products liability and breach of warranty, but found JMC liable for breach of contract and negligence.” The plaintiffs “opposed the setoff motion on the ground that the jury heard evidence only of damages not covered by the settlements.” Both motions were denied. After this, the plaintiffs sought and received investigative costs as damages. JMC appealed this amended judgment.
The appeals court rejected JMC’s claims that evidence was improperly excluded. JMC sought to introduce evidence concerning errors made by the stucco subcontractor. Earlier in the trial, JMC had insisted that the plaintiffs not be allowed to present evidence concerning the stucco, as that had been separately settled. When they wished to introduce it themselves, they noted that the settlement only precluded the plaintiffs from introducing stucco evidence, but the trial court did not find this persuasive, and the appeals court upheld the actions of the trial court. Nor did the appeals court find grounds for reversal based on claims that the jury saw excluded evidence, as JMC did not establish that the evidence went into the jury room. Further, this did not reach, according to the court, a “miscarriage of justice.”
The court rejected two more of JMC’s arguments, concluding that the negligence award did not violate the economic loss rule. The court also noted that JMC failed to prove its contention that the plaintiffs were awarded damages for items that were covered in settlements with the subcontractors.
The appeals court did accept JMC’s argument that the award for breach of contract was not supported by evidence. As the ruling notes, “plaintiffs did not submit the contracts into evidence or justify their absence; nor did plaintiffs provide any evidence regarding contract terms allegedly breached.”
The court also did not allow the plaintiffs to claim the full amount of the investigative costs. Noting that the trial court had rational grounds for its decision, the appeals court noted that “the jury rejected most of the damages claimed by plaintiffs, and the trial court found that more than $86,000 of the costs itemized in plaintiffs’ invoices ‘appear questionable’ as ‘investigation’ costs/damages and appeared to the trial court to be litigation costs nonrecoverable under section 1033.5.”
Read the court decisionRead the full story...Reprinted courtesy of
Jury Could Have Found That Scissor Lift Manufacturer Should Have Included “Better” Safety Features
January 02, 2024 —
Garret Murai - California Construction Law BlogA few years ago I listened to an NPR segment called “
What Can Kids Learn by Doing Dangerous Things?” It was about a summer program called the Tinkering School where kids can learn to build things, using tools of course, including power tools.
The founder of the program, Gever Tulley, also wrote a book entitled
50 Dangerous Things (You Should Let Your Children Do), in which he argued that while well-intentioned, children today are overly protected, and that giving children exposure to “slightly” dangerous things can help foster independence, responsibility, and problem-solving as well as a healthy dose of caution.
The plaintiff in the next case might have benefitted from that program.
In
Camacho v. JLG Industries Inc., 93 Cal.App.5th 809 (2023), the Court of Appeals examined whether the manufacturer of a scissor lift should have incorporated “better” safety features when a construction worker fell from the lift.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com