"My Bad, I Thought It Was in Good Faith" is Not Good Enough - Contractor Ordered to Pay Prompt Payment Penalties
February 23, 2016 —
David A. Harris & Jesse M. Sullivan – Haight Brown & Bonesteel LLPRetention clauses are almost always included in California construction contracts and permit an Owner to withhold a portion of what is owed to the General Contractor as security to ensure the proper completion of the work. General Contractors pass the withholding of retention down to the subcontractors. Thus, if the subcontractor fails to complete its work, or fails to correct deficiencies, the Owner/General Contractor can use the retention to pay the costs of completing or correcting the subcontractor’s work.
The contractor must release any retention it receives from the owner within ten days unless a “good faith dispute exists between the direct contractor and the subcontractor.” (Civil Code section 8814.) Where there is a good faith dispute, the contractor “may withhold from the retention to the subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount.” (Civil Code section 8814(c).) If the contractor wrongfully withholds retention, it must not only pay the retention but must also pay the subcontractor “a penalty of 2 percent per month on the amount wrongfully withheld.” The contractor must also pay the subcontractor’s costs and reasonable attorney’s fees incurred in collecting the retention. (Civil Code section 8818.)
Reprinted courtesy of
David A. Harris, Haight Brown & Bonesteel LLP and
Jesse M. Sullivan, Haight Brown & Bonesteel LLP
Mr. Harris may be contacted at dharris@hbblaw.com
Mr. Sullivan may be contacted at jsullivan@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Is Performance Bond Liable for Delay Damages?
October 20, 2016 —
David Adelstein – Florida Construction Legal UpdatesThere is an argument that a performance bond is not liable for delay damages UNLESS the bond specifically allows for the recovery of such damages. Keep this in mind when requiring a performance bond so that the bond covers the associated risks (and damages) you contemplate when requiring the bond. This argument is supported by the Florida Supreme Court’s 1992 decision in American Home Assur. Co. v. Larkin General Hosp., Ltd., 593 So.2d 195, 198 (Fla. 1992):
The language in the performance bond, construed together with the purpose of the bond, clearly explains that the performance bond merely guaranteed the completion of the construction contract and nothing more. Upon default, the terms of the performance bond required American [performance bond surety] to step in and either complete construction or pay Larkin [obligee] the reasonable costs of completion. Because the terms of the performance bond control the liability of the surety, American’s liability will not be extended beyond the terms of the performance bond. Therefore, American cannot be held liable for delay damages.
However, the Eleventh Circuit in National Fire Ins. Co. of Hartford v. Fortune Const. Co., 320 F.3d 1260(11th Cir. 2003), also analyzing an issue relating to the recoverability of delay-type damages against a performance bond, did not narrowly interpret the Florida Supreme Court’s decision in Larkin General Hospital.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Florida Court of Appeals Holds Underlying Tort Case Must Resolve Before Third-Party Spoliation Action Can Be Litigated
December 04, 2018 —
Lian Skaf - The Subrogation StrategistIn Amerisure Ins. Co. v. Rodriguez, 43 Fla. L. Weekly 2225 (Fla. Dist. Ct. App., Sept. 26, 2018), the Third District Court of Appeals of Florida addressed whether a third-party spoliation claim should be litigated and tried at the same time as the plaintiff’s underlying tort case. The court held that since the third-party spoliation claim did not accrue until the underlying claim was resolved, the spoliation cause of action could not proceed until the plaintiff resolved his underlying claim.
The underlying matter in Amerisure involved a personal injury claim by plaintiff Lazaro Rodriguez. While working as an employee for BV Oil, Inc. (BV), Mr. Rodriguez was knocked from the top of a gasoline tanker he was fueling at a gasoline storage warehouse owned by Cosme Investment (Cosme). Mr. Rodriguez filed a personal injury lawsuit against Cosme. He also collected worker’s compensation benefits from Amerisure Insurance Company (Amerisure), BV’s worker’s compensation carrier, while his lawsuit was pending.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White & Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Court Extends Insurer Rights to Equitable Contribution
October 28, 2015 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Underwriters of Interest v. ProBuilders Specialty Ins. Co. (No. D066615; filed 10/23/15), a California appeals court refused to enforce an “escape” other insurance clause in an insurer versus insurer contribution action, refused to enforce a Contractors Special Conditions endorsement and found that equitable tolling applied to rule that a nondefending insurer was obligated to reimburse defense costs incurred defending the two insurers’ common insured.
Certain Underwriters provided CGL insurance to Pacific Trades Construction & Development in effect between October 23, 2001 and October 23, 2003. ProBuilders Specialty insured Pacific Trades from December 9, 2002 to December 9, 2004. When Pacific Trades was sued in construction defect actions arising out of the development and construction of single family homes, Underwriters provided a defense, while ProBuilders declined to participate. The case was ultimately settled and when Underwriters sued ProBuilders for contribution to the defense costs, the trial court granted summary judgment for ProBuilders, finding its other insurance clause precluded any obligation to contribute or reimburse Underwriters.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Asbestos Confirmed After New York City Steam Pipe Blast
July 21, 2018 —
Eydie Cubarrubia - Engineering News-RecordAsbestos has been found at the site where an underground steam pipe exploded early Thursday morning near the Flatiron building in midtown Manhattan.
Read the court decisionRead the full story...Reprinted courtesy of
Eydie Cubarrubia, ENRMs. Cubarrubia may be contacted at
cubarrubiae@enr.com
Third Circuit Holds No Coverage for Faulty Workmanship Despite Insured’s Expectations
November 21, 2018 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Frederick Mut. Ins. Co. v. Hall, 2018 U.S. App. LEXIS 31666 (3d Cir. Nov. 8, 2018), the United States Court of Appeals for the Third Circuit had occasion to consider Pennsylvania’s doctrine of reasonable expectations in the context of a faulty workmanship claim.
Hallstone procured a general liability policy from Frederick Mutual to insure its masonry operations. Notably, when purchasing the policy through an insurance broker, Hallstone’s principal stated that he wanted the “maximum” “soup to nuts” coverage for his company. Hallstone was later sued by a customer for alleged defects in its masonry work. While Frederick agreed to provide a defense, it also commenced a lawsuit seeking a judicial declaration that its policy excluded coverage for faulty workmanship. The district court agreed that the business risk exclusions applied, but nevertheless found in favor of Hallstone based on the argument that Hallstone had a reasonable expectation that when applying for an insurance policy affording “soup to nuts” coverage, it this would include coverage for faulty workmanship claims.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub Lieberman Straus & Shrewsberry LLPMr. Margolies may be contacted at
bmargolies@tlsslaw.com
Prompt Payment More Likely on Residential Construction Jobs Than Commercial or Public Jobs
May 02, 2022 —
LevelsetNEW ORLEANS, May 02, 2022 (GLOBE NEWSWIRE) -- In construction, no line of work guarantees prompt and in-full payments, but contractors working on residential jobs say their rate of prompt payment is significantly better than commercial or public jobs, according to the
2022 Levelset Cash Flow and Payment Report. However, the report revealed that residential construction jobs require increased communication to improve the chance of prompt payment when compared to commercial or public jobs.
Contractors working on residential projects are more than twice as likely as those working on public projects to report getting paid within 30 days, with residential construction contractors saying they are paid in 30 days or less 48% of the time and public construction contractors saying that only happens 21% of the time.
Significantly slow payments of 60 days or more are three times more likely on public construction projects than on residential construction projects, according to the survey participants. Residential contractors say it happens rarely, just 6% of the time, while public project contractors say it happens nearly one out of five times (18%).
For more information about the report and a detailed summary of findings, please visit: www.levelset.com/survey
About Levelset
Levelset's mission is to empower contractors to always get what they earn. Levelset's products help millions in the construction industry each year to make payment paperwork and compliance easier, get cash faster, monitor the risk on jobs and contractors, and better understand payment processes and rules. The results are faster payments, access to capital, and fewer surprises. Founded in 2012, Levelset is based in New Orleans, Louisiana, with offices in Austin, Texas, and Cairo, Egypt, and is owned and operated by Procore Technologies, Inc. For more information, visit www.levelset.com.
Read the court decisionRead the full story...Reprinted courtesy of
Housing Starts in U.S. Little Changed From Stronger January
March 19, 2014 —
Jeanna Smialek – BloombergHousing starts in the U.S. were little changed in February after declining less than previously estimated a month earlier, indicating the home-building industry is stabilizing after bad winter weather curbed construction.
The 0.2 percent decrease to 907,000 homes at an annualized rate last month followed a revised 909,000 pace in January, figures from the Commerce Department in Washington showed today. The median estimate in a Bloomberg survey called for a 910,000 rate after a previously reported 880,000 in January.
Warmer temperatures, a pickup in demand during the spring selling season and limited housing supply may help fuel further gains in new residential construction. The outlook for the industry later this year depends on whether hiring picks up enough to overcome higher mortgage rates and home prices.
Read the court decisionRead the full story...Reprinted courtesy of
Jeanna Smialek, BloombergMs. Smialek may be contacted at
jsmialek1@bloomberg.net