Lake Texoma, Texas Condo Case may go to Trial
February 05, 2014 —
Beverley BevenFlorez-CDJ STAFFA lawsuit that’s created a “four-year legal battle” over alleged construction defects at the Diamond Pointe Condominium Tower in Lake Texoma, Texas may soon be going to trial, according to KTEN News. A lawyer representing the Diamond Pointe condominiums stated that “he has 15 witnesses lined up for a two-week trial.”
KTEN News reported that according to court papers, “the Association alleges issues with the elevator, doors not opening properly, cracks, water leaks, and septic containment system leaks over the past decade.” Furthermore, the Association president Dan Baucum said to KTEN, “There were some foundation repairs that we needed to do and there are some problems with the building. It was not built to the specifications, at least that's what we're alleging, and that has allowed some water seepage in certain areas.”
Read the court decisionRead the full story...Reprinted courtesy of
Delaware Supreme Court Choice of Law Ruling Vacates a $13.7 Million Verdict Against Travelers
August 07, 2018 —
Gregory Capps & Zachery Roth - White and Williams LLPOn July 16, 2018, the Delaware Supreme Court held in Travelers Indemnity Company v. CNH Industrial America, LLC, No. 420, 2017 (Del. Jul. 16, 2018), that a court’s choice of law inquiry in an insurance coverage dispute should focus on the contacts most relevant to the insurance contract rather than the location of the underlying claims. In Travelers, CNH Industrial America, LLC (CNH), sought coverage for asbestos liabilities associated with J.I. Case, Inc., a subsidiary it had acquired, under policies issued to J.I. Case and its former parent company, Tenneco, Inc. The issue before the Delaware Supreme Court was whether the anti-assignment clause in three Travelers policies issued to Tenneco, Inc. precluded the assignment of the policies to CNH. The validity of the assignment turned on which state’s law governed the dispute. (Under Wisconsin law, the parties agreed that the assignment was valid, while under Texas law, the parties agreed the assignment was invalid.)
Reprinted courtesy of
Gregory Capps, White and Williams LLP and
Zachery Roth, White and Williams LLP
Mr. Capps may be contacted at cappsg@whiteandwilliams.com
Mr. Roth may be contacted at rothz@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
New Executive Orders Expedite the Need for Contractors to Go Green
August 22, 2022 —
Vince Calio - Construction ExecutiveThe importance of going green just became even more crucial for small construction companies, as President Joe Biden signed three executive orders on June 6, 2022, aimed at boosting clean energy construction projects and the use of domestically manufactured clean energy technology.
Specifically, the orders require the U.S. Department of Energy to deploy the use of the Defense Production Act of 1950 to expand American manufacturing of solar panel parts, environmentally friendly building insulation, heat pumps, equipment for making clean power-generating fuels and critical power grid infrastructure. Federal construction contracts will also require local contractors to use eco-friendly materials.
According to an announcement from the White House, the order will encourage the use of project labor agreements that offer wages “above and beyond the prevailing rate and include local hire provisions.” The order will also encourage clean construction projects in low-income areas burdened by legacy pollution.
Reprinted courtesy of
Vince Calio, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Once Again: Contract Terms Matter
May 11, 2020 —
Christopher G. Hill - Construction Law MusingsI know, you’ve heard this over and over again here at Construction Law Musings: courts in Virginia will interpret a contract strictly and in a manner that gives meaning to its unambiguous terms.
A recent case out of the Eastern District of Virginia federal court, White Oak Power Constructors v. Mitsubishi Hitachi Power Systems, reinforces this point. The basic facts of the case relevant to this discussion and the Court’s opinion are these. Old Dominion Electric Cooperative (ODEC) hired White Oak Power Constructors (White Oak) to build a natural gas power plant. The contract between ODEC and White Oak provided for liquidated damages for delay and also contained a risk of loss provision making ODEC responsible for certain losses or damages due to property damage at the plant. I highly recommend that you read the facts of the case in full to get the details of the terms of these clauses.
Needless to say (or this case wouldn’t be the subject of a construction law blog), the project ran past completion date and liquidated damages were assessed to the tune of more than $50,000,000.00. The delay was alleged to have been caused in substantial part by property damage due to weather, fire, and ice among other causes.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Law Alert: A Specialty License May Not Be Required If Work Covered By Another License
March 07, 2011 —
Steven M. CvitanovicContractors should always be sure that they understand the licensing in any Subcontract or Prime Contract before entering into any agreement. However, on March 3, 2011, in the case of Pacific Casson & Shoring, Inc. v. Bernards Bros., Inc. 2011 Cal.App.Lexis 236, the Court of Appeal determined that if a specialty license is subsumed within another license, the specialty license may not be required.
Bernards entered into a subcontract with Pacific to excavate, backfill, grade and provide geotechnical design parameters for a hospital. The Prime Contract required the bidder to maintain a Class C-12 specialty earthwork license. However, Pacific only held a Class A general engineering license which it turns out was suspended during the performance of the work. Pacific sued Bernards for nonpayment of $544,567, but the lawsuit was dismissed because the trial court found that Pacific (1) lacked a C-12 license, and (2) Pacific’s Class A license was suspended for failure to pay an unrelated judgment. Pacific was also ordered to disgorge $206,437 in prior payments.
The Court of Appeal reversed and remanded. The Court of Appeal agreed with Pacific and held that a C-12 specialty license was not required despite the Prime Contract. The Court of Appeal found that the C-12 specialty license would have been “superfluous” since it was fully encompassed within the Class A requirements. However, the Court of Appeal also remanded the case for further
Read the full story...
Reprinted courtesy of Steve Cvitanovic of Haight Brown & Bonesteel, LLP.
Read the court decisionRead the full story...Reprinted courtesy of
Do Construction Contracts and Fraud Mix After All?
October 27, 2016 —
Christopher G. Hill – Construction Law MusingsOn several occasions here at Construction Law Musings, I’ve discussed the fact that, with a few exceptions, fraud claims and written construction contract based claims do not mix. One of the exceptions to the so called “economic loss rule” that would seem to preclude both fraud and contract claims in the same lawsuit is where fraud is used to induce the contract in the first place. This exception would only apply where an independent duty, wholly outside of the duties created by the contract, is properly plead and proven to the court. For the same reason, namely a separate duty outside of the contract, the Virginia Consumer Protection Act (“VCPA”) may allow for an exception that would allow a cause of action under this statute.
Up until recently, the courts of Virginia have used these exceptions sparingly. However, the recent Loudoun County, VA Circuit Court opinion in Interbuild, Inc. v. Sayers (opinion also found at Virginia Lawyers Weekly) may signal a broadening of these exceptions. In the Interbuild case, the Court considered a claim for fraud in the inducement and breach of the VCPA. The basic facts plead by the plaintiffs were that Interbuild induced them into the contract through statements that it had been an established business since 1981, the project did not require a building permit, it had obtained all necessary subcontractor prices and would provide full-time project supervision, the project would be completed within 16 weeks, 4000 PSI concrete would be used for the project and that the project would be located in the agreed-upon area depicted and that they reasonably relied on these representations in deciding to enter into the contract to build their recreational facility.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Pandemic-Related Construction Materials Pricing Poses Challenges in Construction Lawsuits
September 20, 2021 —
Nick Stewart - Construction ExecutiveDuring the global pandemic the construction industry saw unprecedented inflation in the cost of building supplies as a result of a myriad of issues. On May 7, 2021, lumber prices hit a record high at $1,670.50 per thousand board feet. This was more than six times their pandemic low in April 2020. This significant price spike was related to closure of sawmills during the height of the pandemic, low supply, soaring demand to expand existing homes or purchase new construction, the western U.S. wildfires and tariffs.
More recently, lumber prices have fallen but they are still up nearly 100% from spring 2020. Some experts believe that the recent wildfires in the western United States and upcoming hurricane season will cause prices to jump back up in the upcoming months.
Additionally, since March 2020, steel prices are up roughly 200%. The increase in steel prices is a result of many of the same factors causing lumber pricing spikes. Many steel mills shut down production or drastically reduced production during the early days of the pandemic expecting a deep recession and/or to comply with restrictive government mandates. Despite these industry expectations, demand for steel -elated products like grills and home appliances soared. These household demands for steel-based products impacted the price of steel for construction projects. Prior to the pandemic, hot-rolled steel traded between $500 and 800 per ton but hit an all-time high of $1,825 per ton in early July 2021.
Reprinted courtesy of
Nick Stewart, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Stewart may be contacted at
nstewart@turnerpadget.com
Unpredictable Opinion Regarding Construction Lien (Reinstatement??)
January 17, 2023 —
David Adelstein - Florida Construction Legal UpdatesHere comes the discussion of an appeal I was intimately involved in dealing with a construction lien. See Suntech Plumbing and Mechanical Corp. v. Bella Isla, LLC, 2022 WL 14672765 (Fla. 3d DCA 2022). Unfortunately, it was a losing result on my end but not a losing result to the issue at-hand. You should ask what in the world does this mean. I will tell you.
Here is the fact pattern. A subcontractor files a construction lien foreclosure lawsuit against an owner for unpaid contract balance. In the same lawsuit, the subcontractor sues the general contractor for breach of contract and unjust enrichment associated with an approximate three-year delay on a construction project. The project was scheduled to be completed in 2019. It was not. The project was pushed into COVID and into 2022. (The subcontractor did not sue the general contractor for amounts subject to the lien foreclosure claim.) The general contractor, assuming the defense of the owner, moved to stay the lawsuit pending the outcome of arbitration based on an arbitration provision in the subcontract. The subcontractor did not dispute the arbitration provision, but argued that arbitration provision should not extend to the owner that was (a) not bound by the subcontract, (b) would not be a party to the arbitration, and (c) the amounts pled against the general contractor did not include the amounts subject of the lien foreclosure lawsuit. At a minimum, the lawsuit should be stayed, not dismissed. Nevertheless, the trial court dismissed the entire lawsuit in an order that states that it is a final order with language that the lien may be “reinstated” after the outcome of the arbitration (that the owner is not a party to).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com