Court Concludes That COVID-19 Losses Can Qualify as “Direct Physical Loss”
September 28, 2020 —
Lorelie S. Masters & Jorge R. Aviles - Hunton Andrews KurthIn a victory for policyholders, a federal district court found that COVID-19 can cause physical loss under business-interruption policies. In Studio 417, Inc., et al. v. The Cincinnati Insurance Co., No. 20-cv-03127-SRB (W.D. Mo. Aug. 12, 2020), the court rejected the argument often advanced by insurers that “all-risks” property insurance policies require a physical, structural alteration to trigger coverage. This decision shows that, with correct application of policy-interpretation principles and strategic use of pleading and evidence, policyholders can defeat the insurance industry’s “party line” arguments that business-interruption insurance somehow cannot apply to pay for the unprecedented losses businesses are experiencing from COVID-19, public-safety orders, loss of use of business assets, and other governmental edicts.
The policyholders in Studio 417 operate hair salons and restaurants asserting claims for business interruption. In suing to enforce their coverage, the policyholders allege that, over the last several months, it is likely that customers, employees, and/or other visitors to the insured properties were infected with COVID-19 and thereby infected the insured properties with the virus. Their complaint asserts that the presence of COVID-19 “renders physical property in their vicinity unsafe and unusable.” Unlike some other complaints seeking to enforce such coverage, it also alleges that the presence of COVID-19 and government “Closure Orders” “caused a direct physical loss or direct physical damage” to their premises “by denying use of and damaging the covered property, and by causing a necessary suspension of operations during a period of restoration.”
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Jorge R. Aviles, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Aviles may be contacted at javiles@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Formal Opinion No. 2020-203: How A Lawyer Is to Handle Access to Client Confidential Information and Anticipation of Potential Security Issues
December 07, 2020 —
Bremer Whyte Brown & O'Meara LLPRecently, the California Bar Association (“CBA”) published Formal Opinion No. 2020-203[1] concerning a lawyer’s ethical obligations with respect to unauthorized access to electronically stored client information. The onset of the COVID-19 pandemic greatly accelerated the growing trend of storing and maintaining data and information online so that employees and clients can access the data from anywhere in the world at any time. Now, in today’s working world, the reality is nearly all information and data is stored and shared digitally online for ease of access, use, and dissemination.
Unfortunately, a major draw-back of this switch to a cyber paradigm is serious exposure to data breaches as a result of hacking, inadvertence, or theft. Formal Opinion No. 2020-203 outlines how a lawyer is to handle access to client confidential information and anticipation of potential security issues. This article will briefly cover the key aspects addressed in Formal Opinion No. 2020-203.
What is the duty owed by a lawyer to his or her client regarding the use of technology?
At the outset, the CBA reminds lawyers of the ongoing duty of competence (Rule 1.1) and the duty to safeguard clients’ confidences and secrets (Rule 1.6; Cal. Bus. & Prof. Code, § 6068(e)) which impose the requirement that a lawyer must have a basic understanding of the risks posed when using a given technology and (if necessary) obtain help from appropriate experts to assess those risks and take reasonable steps to prevent data breaches.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
French Laundry Spices Up COVID-19 Business Interruption Debate
April 20, 2020 —
Jeffrey J. Vita & Melanie A. McDonald - Saxe Doernberger & VitaOn March 26, 2020, Michelin-rated Napa Valley restaurants, French Laundry and Bouchon Bistro, and their celebrity chef, Thomas Keller, filed the second known
coronavirus-related declaratory judgment (DJ) lawsuit by a restaurant. The restaurants filed their DJ against Hartford Fire Insurance Company just seven days after Napa County issued a Shelter at Home Order.1 Chef Keller’s suit comes on the heels of the first such suit by a restaurant seeking to recover business income losses, filed by iconic New Orleans French Quarter restaurant Oceana Grill2 on March 17, just four days after the Louisiana governor issued an order prohibiting gatherings of more than 250 people.
As local governments seek to protect their citizens and prevent an onslaught of cases in area hospitals, they are issuing various “stay home,” “shelter at home,” and similar orders to force social distancing and to help flatten the curve of the growth in COVID-19 cases. Restaurants nationwide are especially hard hit by these orders, as many of these orders contain size limitations on gatherings, which have required that restaurants and bars limit capacity (as in the March 13th Louisiana order). Other such orders require non-essential businesses to “cease all activities in the County” (as in the Napa County Shelter at Home order). The Napa County order does not exempt restaurants as “essential businesses,” except when providing food for take-out or delivery. Other orders, still, directly address restaurants and require them to cease allowing public consumption of food and beverages (as in the subsequent, March 17th Louisiana order).
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
Melanie A. McDonald, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at jjv@sdvlaw.com
Ms. McDonald may be contacted at mam@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Statutes of Limitations May be the Colorado Contractors’ Friend
April 18, 2011 —
Beverley BevenFlorez CDJ STAFFAlbert Wolf, a principal in Wolf Slatkin & Madison P. C., has written an interesting article on statutes of limitations in construction defect claims in Colorado. While Wolf states that in most cases, “construction defect claims against construction industry participants (contractors, subcontractors, architects, engineers, etc.) requires that suits be started within two years after construction defects have been or should have been—in the exercise of reasonable diligence (care)—discovered,” if a project used the AIA General Conditions (AIA Document A2010) before the 2007 edition, the “statutes of limitations begin to run (accrue) at either substantial completion or breach by the contractor (installation of defective work), depending on the circumstances.”
“That’s a huge difference,” Wolf writes in his article. “For example, if the structural defect caused by faulty foundation work is not discovered or discoverable until walls begin to exhibit cracking more than two years after the building is completed, the owner’s claim against the contractor may be barred if the AIA provision is applied.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Ohio Court Refuses to Annualize Multi-Year Policies’ Per Occurrence Limits
June 19, 2023 —
Patricia Santelle, Adam Berardi & Lynndon Groff - White and Williams LLPWhite and Williams recently obtained summary judgment against an insured on behalf of an insurer and a guarantor, establishing that two multi-year insurance policies provide per occurrence limits on a per policy rather than a per year basis, which shielded potential exposure by over $100 million.
The insured had previously sought and obtained coverage under two policies in connection with a single occurrence arising out of massive environmental contamination claims involving a large industrial site. The issue of whether the policies provide per occurrence limits on a policy term or annual basis was not resolved in this earlier litigation.
The first policy was effective for three years and provides per occurrence limits of $40 million. The second policy was effective for up to three years and provides per occurrence limits of $15 million.
Reprinted courtesy of
Patricia Santelle, White and Williams LLP,
Adam Berardi, White and Williams LLP and
Lynndon Groff, White and Williams LLP
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Mr. Berardi may be contacted at berardia@whiteandwilliams.com
Mr. Groff may be contacted at groffl@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Project Delivery Methods: A Bird’s-Eye View
November 01, 2021 —
Levi W. Barrett, Nathan A. Cohen & Stewart Shurtleff - ConsensusDocsFor centuries the ability to construct sophisticated structures has been the yardstick for measuring civilizations. Naturally, as our knowledge and capacity to build has evolved and developed over the ages, the methods of project delivery have similarly progressed.
From Design-Bid-Build to CM-at-Risk and Design-Build to Integrated Project Delivery, each method developed to fit a very specific need—but each carries its own set of inherent risks and rewards. In this article we explore key aspects and differences among the various delivery methods that are commonly used in today’s construction industry, and provide guidance related to the obligations and risk profiles of the parties involved. Ideally, contractors and construction managers may refer to the advice provided herein when determining whether a proposed delivery method properly fits the requirements of the project under consideration.
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Nathan A. Cohen, Peckar & Abramson, P.C. and
Stewart Shurtleff, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Cohen may be contacted at ncohen@pecklaw.com
Mr. Shurtleff may be contacted at sshurtleff@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Burg Simpson to Create Construction Defect Group
November 06, 2013 —
CDJ STAFFBurg Simpson Eldredge Hersh & Jardine, P.C. has announced that the attorneys of Sullan2, Sandgrund, Perczak & Nuss, P.C. will be joining them as S2SPN Construction Defect Group of Berg Simpson. The group will be headquartered at Burg Simpson’s Engelwood offices.
The combined firms will comprise 55 attorneys. Michael Burg, founding shareholder at Burg Simpson, said that “in Colorado for the past 29 years, these lawyers have provided the highest level of construction defect representation.” His counterpart, Scott Sullan of Sullan2, Sandgrund, Perczak & Nuss said that he and his colleagues are “delighted to be a part of the Burg Simpson team.” The two firms join forces effective January 1, 2014.
Read the court decisionRead the full story...Reprinted courtesy of
Duty to Defend Bodily Injury Evolving Over Many Policy Periods Prorated in Louisiana
November 17, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Louisiana Supreme Court held that the duty to defend in long latency disease cases should be prorated between the insurer and insured when the policies cover for only a portion of the time in which the exposure occurred. Arceneaux v. Amstar Corp., 2016 La. LEXIS 1675 (La. Sept. 7, 2016).
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at