The Court-Side Seat: FERC Reviews, Panda Power Plaints and Sovereign Immunity
April 26, 2021 —
Anthony B. Cavender - Gravel2GavelThis is a brief report on new environmental law decisions, regulations and legislation.
THE U.S. SUPREME COURT
Massachusetts Lobsterman’s Association v. Raimondo, Secretary of Commerce
On March 22, 2021, the Supreme Court rejected a petition to review a Presidential decision to invoke the Antiquities Act of 1906 to designate as a monument “an area of submerged land about the size of Connecticut” in the Atlantic Ocean. This action forbids all sorts of economic activity, which compelled the filing of litigation in the First Circuit challenging this designation. Chief Justice Roberts supported the Court’s denial of certiorari, but remarked that a stronger legal case may persuade the Court to review such liberal uses of the Antiquities Act.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Client Alert: Absence of a Court Reporter at a Civil Motion Hearing May Preclude Appellate Review
November 26, 2014 —
Angela S. Haskins & Blythe Golay - Haight Brown & Bonesteel LLPA California Court of Appeal expressed its concern over the due process implications of reviewing a trial court's decision that incorporated reasons that were not documented due to the absence of a court reporter. In Maxwell v. Dolezal (No. B254893, filed 11/4/14), the court cautioned that although the lack of a transcript did not preclude its review of an order sustaining a demurrer, the case was an exception because the operative complaint and demurrer were sufficient to permit effective appellate review.
The plaintiff in Maxwell, acting in pro per, had filed an action for invasion of privacy and breach of contract. The plaintiff alleged that the defendant had used his photograph and website without his consent and that he did not receive the money, food and housing in exchange for the intellectual property rights per their agreement. The defendant demurred on the grounds that the complaint was uncertain and it could not be ascertained from the pleading whether the contract was written, oral, or implied. At the hearing on the demurrer, no court reporter was present. Nonetheless, the trial court's minute order explicitly sustained the demurrer "[f]or the reasons stated in open court," without further elaborating. The trial court also denied the plaintiff further leave to amend on the ground that he was unable to articulate in open court a reasonable basis for any additional allegations that would remedy the deficiencies. The court of appeal noted that it was "profoundly concerned about the due process implications of a proceeding in which the court, aware that no record will be made, incorporates within its ruling reasons that are not documented for the litigants or the reviewing court."
Reprinted courtesy of
Angela S. Haskins, Haight Brown & Bonesteel LLP and
Blythe Golay, Haight Brown & Bonesteel LLP
Ms. Haskins may be contacted at ahaskins@hbblaw.com; Ms. Golay may be contacted at bgolay@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Subcontractors Have a Duty to Clarify Ambiguities in Bid Documents
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorSeveral months ago, I wrote about an escalator subcontractor that sued a general contractor, demanding payment for work completed based on approved shop drawings. The trial court agreed with the subcontractor, but the general contractor appealed. Ten months later, the Court of Appeals reversed, finding that the subcontractor had a duty to bring to the general contractor’s attention major discrepancies or errors they detect in the bid documents.
“The subcontractor failed to disclose ambiguities in the plans and must suffer the peril.”
Construction Difficulties
The subcontractor installed 32 inch escalators throughout the project, but the plans called for 40 inch escalators. The general contractor and subcontractor could not reach agreement on how the dispute should be resolved. The subcontractor sued the general to get paid for replacing the escalators and the general sued to subcontractor for concessions it had to pay to the owner.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Homebuilder Confidence Takes a Beating
October 21, 2013 —
CDJ STAFFHomebuilder confidence dropped to fifty-five percent in October, the lowest percentage seen in the last four months. The score had been rising on the strength of renewed home sales. The current slump is attributed to increases in interest rates, which have made home purchases more expensive for prospective buyers, and the uncertainty of the budget struggle in Washington.
John Stumpf, the chairman and CEO of Wells Fargo said that “home price appreciation remains strong and affordability remains excellent.” Mr. Strum has “guarded optimism” over the effects of the budget struggle.
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Breach of Contract Claims Against Contractor
March 19, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe U. S. District Court found there was no coverage for breach of contract claims against the contractor who walked off the job before completing the project. Pa. Nat'l Mut. Cas. Ins. Co. v. Snider, 2014 U.S. Dist. LEXIS 16920 (M.D. Ala. Feb. 11, 2014).
The homeowners hired Jeff Beale to build their home for an approximate cost of $650,000. Beale said the job would take six to eight months and construction would be completed in early 2005. Construction did not begin, however, until April 2005. By 2005, the homeowners were becoming increasing displeased with Beale's progress. By March 2006, construction costs were approaching $800,000 and the home was not completed. The homeowners made progress payments on a monthly basis. Beale did not return to the home after April 2006 and another contractor was hired to complete the job.
When the homeowners moved in, they discovered several construction defects, including a cracked retaining wall and water intrusion in many areas of the home. They paid over $150,000 to repair the defects, to complete work Beale left unfinished, and remove mold.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Prefabrication Contract Considerations
March 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesPrefabrication (also referred to as modular construction in instances), is a form of offsite construction where certain construction activities occur at an offsite manufacturing facility or location. Construction components or units are preassembled (prefabricated) at this offsite location prior to being delivered to the project site and then integrated into the project.
When preparing a prefabrication contract (including a prefabrication subcontract), there are a number of complex considerations that need to be weighed, and these considerations are bullet-pointed below. The purpose of these bullet-points is to give you considerations to discuss and vet when preparing, negotiating, and agreeing to a prefabrication contract or subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
“To Indemnify, or Not to Indemnify, that is the Question: California Court of Appeal Addresses Active Negligence in Indemnity Provisions”
April 05, 2017 —
Steven M. Cvitanovic & Omar Parra – Haight Brown & Bonesteel LLPIn California, it is well-established that the extent of a party’s obligation under an indemnity agreement is an issue of contractual interpretation, and it is therefore the intent of the parties that should control. What is the parties’ intent, then, when a subcontractor (indemnitor) agrees to indemnify the general contractor (indemnitee) “except to the extent the claims arise out of the general contractor’s active negligence or willful misconduct”? Does this mean the general contractor is barred entirely from recovering any indemnity if its active negligence contributed to the injury? Not according to the First Appellate District of the California Court of Appeal, which recently held that an actively negligent general contractor may still recover indemnity for the portion of liability attributable to the fault of others. Oltmans Construction Co. v. Bayside Interiors, Inc., No. A147313, 2017 WL 1179391, at *1 (Cal. Ct. App. Mar. 30, 2017).
In Oltmans Construction, an employee of O’Donnell Plastering, Inc. (“O’Donnell”), a sub-subcontractor of Bayside Interiors, Inc. (“Bayside”), which was a subcontractor to Oltmans Construction Company (“Oltmans”), sustained injuries when he fell through a skylight opening in the roof of a building under construction. The employee filed suit against Bayside, Oltmans, and the building’s owner, arguing Oltmans negligently cut and left unsecured the skylight opening. Oltmans subsequently filed a Cross-Complaint against Bayside and O’Donnell, contending it was entitled to indemnification under the governing agreements.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Omar Parra, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Parra may be contacted at oparra@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Spearin Doctrine: Alive, Well and Thriving on its 100th Birthday
January 15, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCOn December 9, 2018, United States v. Spearin, [1] a landmark construction law case, will be 100 years old. The Spearin “doctrine”[2] provides that the owner impliedly warrants the information, plans and specifications which an owner provides to a general contractor. The contractor will not be liable to the owner for loss or damage which results from insufficiencies or defects in such information, plans and specifications.
Some construction lawyers questioned whether the Spearin doctrine was still viable in Washington after the Washington Court of Appeals decided the recent case of King County v. Vinci Constr. Grand Projets.[3] Some concerned contractor industry groups even considered a “statutory fix” in the wake of the Court of Appeals Vinci decision. It is our opinion that the facts in the Vinci case are distinguishable and the Spearin doctrine is alive and thriving in Washington.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at