Enhanced Geothermal Energy Could Be the Next Zero-Carbon Hero
June 10, 2024 —
Sidney L. Fowler, Robert A. James & Clarence H. Tolliver - Gravel2Gavel Construction & Real Estate Law BlogHydrogen, solar, wind—and even microwave beams from outer space—are a few of the alternative energies being explored as the world strives to cut the cord on carbon emissions. Recently, advancements in geothermal energy technologies appear poised to significantly expand geothermal’s reach. These new methods, varyingly referred to as enhanced, engineered or advanced geothermal systems (collectively referred to here as EGS), have recently made strides in scalability and grabbed the attention of changemakers. If successful, EGS may play a major role in the clean energy transition. The technique creates no emissions and is virtually limitless (it pulls from heat generated by the Earth’s core), and can provide constant baseload power, making it appealing to green-minded investors. This article calls attention to the progress and variety of EGS projects and proposals that Pillsbury sees as part of the ongoing energy transition.
People have long been drawn to geothermal energy, with Paleo-Americans settling at hot springs some 10,000 years ago. In 1892, Boise, Idaho, became the first town to establish a district heating system that piped naturally occurring hot water from underground and into homes. It would take another 70 years for other cities to replicate the feat, but now 17 U.S. districts use such systems, along with dozens more worldwide.
Reprinted courtesy of
Sidney L. Fowler, Pillsbury,
Robert A. James, Pillsbury and
Clarence H. Tolliver, Pillsbury
Mr. Fowler may be contacted at sidney.fowler@pillsburylaw.com
Mr. James may be contacted at rob.james@pillsburylaw.com
Mr. Tolliver may be contacted at clarence.tolliver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Shea Homes CEO Receives Hearthstone Builder Humanitarian Award
February 12, 2014 —
Beverley BevenFlorez-CDJ STAFFBert Selva, Shea Homes CEO, received the Hearthstone Builder Humanitarian Award at the 2014 NAHB International Builders’ Show in Las Vegas, Nevada, according to Big Builder. Selva “has served for 11 years on HomeAid's board of directors,” and “is a big supporter of the nonprofit that works to provide housing for homeless families, victims of natural disasters, and veterans.” Furthermore, “Shea Homes has built eight HomeAid shelter projects valued at more than $5.2 million and has contributed nearly $850,000 to HomeAid and its chapters, making it one of the group's largest benefactors.” Not only does Selva actively support HomeAid, he also “serves as a national vice president of the Muscular Dystrophy Association.”
"I ask myself, 'How would it feel if that were me or my family?'" Selva told Big Builder. "When you personalize it, it becomes a lot more real and that's the motivation for me."
The award “includes recognition at an event during the 2014 International Builders' Show and a cash award to a charity of his choice.”
Read the full story, Jennifer Goodman’s Article...
Read the full story, John McManus’s Article... Read the court decisionRead the full story...Reprinted courtesy of
Smart Construction and the Future of the Construction Industry
October 11, 2021 —
Caroline A. Harcourt, James W. McPhillips & Adam J. Weaver - Gravel2Gavel Construction & Real Estate Law Blog“Smart Construction” is a loose term but generally refers to the development and use of processes and applications that improve construction planning and the management of projects (thereby potentially streamlining costs of construction).
The increased deployment of collaboration tools (e.g., Zoom, Microsoft Teams, WebEx) and other cloud-based technology solutions during the COVID-19 pandemic will invariably result in more efficient project management in construction going forward. These type of efficiencies are sorely needed, especially as the industry is trying to recover from supply chain issues, lockdown challenges and social distancing requirements resulting from the pandemic.
However, smart construction goes well beyond those basic business efficiency and collaboration tools. For example, drones are regularly used on construction projects to monitor site conditions, detect problems, and assess conditions safely. Meanwhile, newer technologies such as “programmable” cement, “self-healing” concrete, and autonomous and robotic machinery are increasingly being deployed in construction projects. And yet, these current technology solutions are just the tip of the iceberg as researchers continue to look for new ways machines and technology can be used to solve complex engineering challenges.
Reprinted courtesy of
Caroline A. Harcourt, Pillsbury,
James W. McPhillips, Pillsbury and
Adam J. Weaver, Pillsbury
Ms. Harcourt may be contacted at caroline.harcourt@pillsburylaw.com
Mr. McPhillips may be contacted at james.mcphillips@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Mississippi Floods Prompt New Look at Controversial Dam Project
March 16, 2020 —
Autumn Cafiero Giusti - Engineering News-RecordFlooding from the Pearl River in Mississippi has created a renewed sense of urgency for regional flood prevention efforts, with officials set to decide in six months whether to approve a controversial flood control plan, says an attorney for the region’s flood control district.
Autumn Cafiero Giusti, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Fixing That Mistake
October 25, 2021 —
Patrick Barthet - Construction ExecutiveSomeone once said, more people could learn from their mistakes if they weren’t so busy denying that they made them in the first place.
In the construction industry, mistakes are not uncommon. Addressing them, however, can be complicated. What should a contractor do when the project owner says some aspect of the project is not satisfactorily completed or isn’t performing as it should? Should the contractor wait, hoping it may get resolved without having to do anything? Or should the contractor take on the repair or replacement as soon as practically possible?
Doing nothing may be easy but can expose the contractor to significant subsequent liability. Dealing with the issue, on the other hand, could result in the destruction of what might later be required evidence in any litigation which develops. Considered “spoliation,” such manipulation or elimination of evidence is a consequence to be avoided. Even though done with the best of intentions to fix a problem, the process can wind up exposing one to liability and damages.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Apple to Open Steve Jobs-Inspired Ring-Shaped Campus in April
February 23, 2017 —
Adam Satariano - BloombergApple Inc. co-founder Steve Jobs’ last public event in 2011 was a city council meeting in Cupertino, California, where he presented plans for a sprawling new campus with a spaceship-shaped building and tree-filled park. Apple announced Wednesday that it will begin moving employees into the 2.9 million-square-foot facility in April.
Apple said a new 1,000-seat auditorium at the facility will be named the Steve Jobs Theater in honor of its co-founder, who died four months after his city council presentation and would have turned 62 on Feb. 24.
As with many large-scale construction projects, Apple faced budget overruns and delays. The building cost an estimated $5 billion (though Apple has never said how much), and the opening date had initially been set for 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Adam Satariano, BloombergMr. Satariano may be followed on Twitter @satariano
Safer Schools Rendered Unsafe Due to Construction Defects
February 10, 2012 —
CDJ STAFFBuilt on a program for safer school buildings, schools in Neenan County, Colorado have been shown to have mild-to-moderate structural problems, rendering some of them unsafe. The Denver Post reports that a third-party review of schools built by the Neenan Company has shown structural issues in all fifteen school buildings.
One school, Meeker Elementary, has been closed as it could collapse under high winds or during an earthquake. Sargent Junior-Senior High School is in use, but there are plans to evacuate the buildings if winds exceed 25 mile per hour. Two schools have roofs that are unable to bear expected loads of snow during the winter.
The Neenan Company says that the school buildings are not up to their standards and is working with the school districts to repair the buildings. Repairs are expected to be complete by August.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Recovering Unabsorbed Home Office Overhead Due to Delay
May 30, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn the
preceding article, I discussed the use of a retrospective as-built delay analysis in a case before the Civilian Board of Contract Appeals (CBCA). This case also discussed a damages component in certain delay claims known as unabsorbed home office overhead—a challenging damages component to recover because this deals with indirect costs as opposed to direct costs.
Unabsorbed home office overhead is a damages component when the contractor is on standby, but this is NOT as easy as just claiming standby thereby you are automatically entitled to unabsorbed home office overhead. There are requirements that MUST be met.
To obtain an equitable adjustment for unabsorbed home office overhead as compensation for being on standby, [the contractor] must initially show “[1] a government-caused delay of uncertain duration,” that “[2] the delay extended the original time for performance” or precluded the contractor from finishing earlier than scheduled, and that “[3] the contractor [was] on standby and unable to take on other work during the delay period.
CTA I, LLC v. Department of Veteran Affairs, CBCA 5826, 2022 WL 884710 (CBCA 2022) quoting Nicon, Inc. v. U.S., 331 F.3d 878, 883 (Fed. Cir. 2003).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com