Mandatory Arbitration Isn’t All Bad, if. . .
August 13, 2019 —
Christopher G. Hill - Construction Law MusingsIn the past week or so mandatory arbitration has been all the rage. From those that argue that arbitration is becoming more burdensome than litigation, to my friend and fellow construction attorney Scott Wolfe who gives great advice on how to make arbitration worth it again. You can place me in the camp of those that think that mandatory arbitration clauses of the type typically found in contracts can add a layer of expense that can be unnecessary.
However, if an arbitration clause is carefully drafted, and properly used, these clauses an be helpful in assuring that the streamlining effect for which arbitration was created actually occurs. Because the contract is king in Virginia, these provisions can essentially create the rule of civil procedure used to resolve any dispute relating to the project.
Anything from the number and method of appointing the arbitrators, to the ability to use attorneys, to the time between notice and arbitration hearing and whether mediation is a requirement, to the documents and other pre-arbitration exchanges can and should be specifically outlined. The construction contract can also state who decides between court or arbitration. This can be one party or both. The possibilities are almost endless.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
How Robotics Can Improve Construction and Demolition Waste Sorting
September 11, 2023 —
Emily Newton - Construction ExecutiveCommercial construction projects generate a lot of waste. Managing this debris is crucial to minimizing the industry’s environmental impact, but it’s often a time-consuming and error-prone process. Robotic waste sorting provides a better alternative.
Why C&D Waste Management Must Improve
The current state of construction and demolition (C&D) debris management leaves considerable room for improvement. Nearly all C&D waste takes
decades to break down in landfills—and the sector generates hundreds of millions of tons of it annually.
More efficient debris management would help firms protect the environment and their bottom line. Poor waste management practices also take an economic toll. Recycling extends materials’ useful life, helping minimize resource costs. Inefficient waste sorting may additionally lead to unnecessarily high workforce expenses and incur lost business from firms’ lack of sustainability.
Reprinted courtesy of
Emily Newton, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Contract Change #9: Owner’s Right to Carry Out the Work (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaIn prior versions of the General Conditions, if a contractor defaulted and the Owner (after giving notice) opted to cure by carrying out the work itself, an appropriate Change Order would be issued. However,
a Change Order is a contract that requires an agreement by both the Owner and Contractor, and, obviously, Contractors were reluctant to agree that they were in default and responsible for a deductive change order.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
The Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 —
Shaun McParland BaldwinThe Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury or “property damage” be caused by an occurrence and that the “bodily injury or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury” or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivanrsquo;s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing, including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Read the court decisionRead the full story...Reprinted courtesy of
The Colorado Supreme Court holds that loans made to a construction company are not subject to the Mechanic’s Lien Trust Fund Statute
February 21, 2013 —
W. Berkeley Mann, Jr. — Higgins, Hopkins, McLain & Roswell, LLCIn a prior blog post, we summarized the Court of Appeals decision in the case of AC Excavating, Inc. v. Yale, ___ P. 3d. ___, 2010 WL 3432219 (Colo. App. Sept. 2, 2010) which provided an interpretation of the Colorado Mechanic’s Lien Trust Fund Statute, C.R.S. § 38-22-127 (hereafter “the Trust Fund Statute”). A divided Court of Appeals reversed the trial court, and held that capital loans infused into a limited liability company which performed construction could be subject to the provisions of the Trust Fund Statute.
The Court of Appeals reasoned that this determination was necessary because the statute was considered applicable to “all funds disbursed on a construction project.” Additionally, the Court of Appeals held that the intent of the provider of funds was not relevant, and that the statute applied “irrespective of the [originator of the funds]’s intended use of the funds.”
This decision was reviewed by the Colorado Supreme Court in an opinion released on February 4, 2013, and it reversed the Court of Appeals’ decision. See, Yale v. AC Excavating, Inc., ___ P. 3d. ___, 2013 WL 441895 (Colo. Feb. 4, 2013). The Supreme Court strongly disagreed that loaned or infused capital funds which were obtained by the general contractor entity were “funds disbursed on a construction project,” simply because some of the infused monies were used for operational purposes to pay down specific project obligations.
Read the court decisionRead the full story...Reprinted courtesy of
W. Berkeley Mann, Jr.mann@hlmrlaw.com
Court Provides Guidance on ‘Pay-When-Paid’ Provisions in Construction Subcontracts
July 13, 2020 —
Ted R. Gropman & Cindy J. Lee - ConsensusDocsOn April 17, the California Court of Appeal decided Crosno Construction, Inc. v. Travelers Casualty & Surety Company of America,1 effectively narrowing the scope of enforceable “pay-when-paid” provisions in construction subcontracts to the extent the subcontractor seeks recovery against a general contractor’s payment bond surety. Although the Crosno case involved a public works project, the rationale and holding should apply with equal force to private works projects. Basing the bulk of its decision on the Wm. R. Clarke Corp. v. Safeco Insurance Co.2 case, the court found that an open-ended “pay-when-paid” provision in a subcontract is not enforceable against a subcontractor that seeks to recover on a public works payment bond claim. This article discusses the Crosno decision and the implications for contractors on both sides of the contract moving forward.
Brief Case Summary
In Crosno, general contractor Clark Bros., Inc. contracted with the North Edwards Water District (the District) to build an arsenic removal water treatment plant. Clark hired steel storage tank subcontractor Crosno Construction, Inc. to build and coat two steel reservoir tanks. Clark and Crosno’s subcontract included a “pay-when-paid” provision, which stated that Clark would pay Crosno within a “reasonable time” of receiving payments from the owner, but “in no event less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against Owner or other responsible party to obtain payment.” After Crosno completed its work, a dispute arose between Clark and the District, and the District withheld payment from Clark (including the monies earmarked for Clark’s subcontractors). Clark sued the District for payment, and Crosno filed its own action against Travelers Casualty and Surety Company of America, the surety on Clark’s statutory public works payment bond, for recovery of the unpaid subcontract balance. Travelers rejected Crosno’s bond claim as premature, invoking the “pay-when-paid” subcontract language and pointing to Clark’s pending payment action against the District. The issue on appeal was whether the “pay-when-paid” provision in the subcontract blocked Crosno from recovering under the payment bond from Travelers while Clark’s lawsuit against the District was still pending.
Reprinted courtesy of
Ted R. Gropman, Pepper Hamilton LLP and
Cindy J. Lee, Pepper Hamilton LLP
Mr. Gropman may be contacted at ted.gropman@troutman.com
Ms. Lee may be contacted at cindy.lee@troutman.com
Read the court decisionRead the full story...Reprinted courtesy of
When Do You Call Your Lawyer?
October 08, 2014 —
Craig Martin – Construction Contractor AdvisorThe National Association of Home Builders recently conducted a survey asking its members about the legal issues they faced in the last 12 months and whether they consulted their attorney to deal with the problem. Below are some highlights of the survey.
Legal Issue % of Homebuilders % Contacted Counsel
Warranty/call back claims 34% 51%
Contract disputes 22% 84%
Defective Install/Workmanship 20% 83%
OSHA Issues 13% 33%
CGL Coverage Questions 11% 73%
Construction Liens 10% 57%
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Sioux City Building Owners Sue Architect over Renovation Costs
December 04, 2013 —
CDJ STAFFAccording to the architects, it should have cost a few hundred thousand dollars to strengthen the floors of Sioux City’s Badgerow Building. Instead, the upgrades cost somewhere between $3 and $5 million, which Mako One, the builder’s owners, said would have dissuaded them from starting had they known. Mako is suing M Plus Architects, for this and for its recommendation that the building’s windows be changed. That change ran foul of historic preservation guidelines, and the windows will have to be replaced.
M Plus is, in return, suing Mako One over $150,000 in unpaid bills. Meanwhile, a data center is moving in on the fourth floor.
Read the court decisionRead the full story...Reprinted courtesy of