Don’t Kick the Claim Until the End of the Project: Timely Give Notice and Preserve Your Claims on Construction Projects
December 10, 2015 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday, we welcome
Tara L. Chadbourn. Tara is an attorney with
ReavesColey PLLC in Chesapeake, VA, where she concentrates her practice on construction law, litigation and commercial litigation. Tara counsels owners, contractors, subcontractors and materials suppliers in various government and commercial construction matters. Tara can be reached at tara.chadbourn@reavescoley.com.
You may have experienced and have certainly heard of the scenario in which a contractor waits to address a claim as part of project closeout, only to realize the applicable deadline has already passed. While there may have been discussions about claims during the course of the project, contractors cannot rely upon oral conversations about outstanding claims. Instead, contractors must be vigilant in satisfying notice requirements and preserving claims. While entitlement must still be proven, a contractor’s chances of recovery increase greatly if the contractor abides by notice requirements and consciously preserves claims in the following ways.
Contractors Must Acquaint Themselves with Contractual Notice Provisions:
Many prime and subcontract agreements contain stringent notice provisions that require the contractor to give notice within a certain time period or else the claim is expressly waived. The deadline for notice is often only a few days after the occurrence giving rise to the claim or the contractor becoming aware of the claim. To avoid waiver, contractors must carefully review their contracts for provisions requiring notice of a claims for adjustment for a variety of situations to include unforeseen site conditions, trade sequencing changes, project delay or scope of work changes.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
As California Faces Mandatory Water Use Reductions How Will the Construction Industry be Impacted?
May 07, 2015 —
Garret Murai – California Construction Law BlogEarlier this month, Governor Jerry Brown issued Executive Order B-29-15, which imposes mandatory water use reductions for the first time in the history of California.
The Executive Order, issued as the state enters its fourth year of severe to exceptional drought, directs the State Water Resources Control Board (“State Water Board”) to impose a 25% reduction on the state’s 400 local water supply agencies which serve 90% of California residents, over the coming year.
The State Water Board has already issued proposed regulations based on informal comments received from the public, and in a “Fact Sheet” issued this weekend, has indicated that it is seeking additional informal comments no later than April 22, 2015, with final proposed emergency regulations to be released on April 28, 2015, which will then be considered by the State Water Board at its meetings on May 5 and 6, 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Court Says No to Additional Lawyer in Las Vegas Fraud Case
October 14, 2013 —
CDJ STAFFLeon Benzer, who has been accused of being one of the masterminds of the Las Vegas HOA scam, has been denied in his bid to add an additional attorney to his publicly-funded defense. Daniel Albregts, Benzer’s court-appointed attorney, made the request due to the large amount of evidence in the case. Federal prosecutors have provided the defense with more than 3.4 million pages of documents. According to U. S. Magistrate Judge George Foley Jr., “defendant’s counsel should be able to prepare and provide an adequate defense with the assistance of appropriate paralegal and other support services.”
Mr. Albregts is currently assisted by Russell Aoki, whose role is that of technical consultant on matters regarding electronic distribution. Federal prosecutors opposed Mr. Albregts hiring Franny Forsman, a former federal public defender. Had Ms. Forsman been hired, the government would have paid $110 per hour for her services. The government is seeking $25 million in restitution from Mr. Benzer.
Read the court decisionRead the full story...Reprinted courtesy of
Shoring of Problem Girders at Salesforce Transit Center Taking Longer than Expected
November 14, 2018 —
Nadine M. Post - Engineering News-RecordThe Transbay Joint Powers Authority announced on Oct. 10 that emergency remedial work at the 4.5-block-long Salesforce Transit Center in San Francisco, on the closed Fremont Street between Howard and Mission streets, will continue into early next week. The block, which crosses under the hub, will reopen to traffic and the public on Wednesday, Oct. 17, rather than Oct. 12, as previously announced, says TJPA. The transit center itself, which opened in August, is temporarily closed.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, ENRMs. Post may be contacted at
postn@enr.com
Just Because You Caused it, Doesn’t Mean You Own It: The Hooker Exception to the Privette Doctrine
March 06, 2023 —
Garret Murai - California Construction Law BlogWe’ve written before about the Privette doctrine, which establishes a presumption that a hirer of an independent contractor delegates to the contractor all responsibility for workplace safety. In other words, if a general contractor hires a subcontractor, the subcontractor is solely responsible for the safety of its workers.
There are two major exceptions to the Privette doctrine. The first, the Hooker exception, holds that a hirer may be liable when it retains control over any part of the independent contractor’s work and negligently exercises that retained control in a manner that affirmatively contributes to the worker’s injury. The second, the Kinsman exception, holds that a hirer may be liable for injuries sustained by a worker of an independent contractor if the hirer knew, or should have known, of a concealed hazard on the property that the contractor did not know of and could not have reasonably discovered and the hirer failed to warn the contractor of the hazard.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Sometimes you Need to Consider the Coblentz Agreement
January 19, 2017 —
David Adelstein – Florida Construction Legal UpdatesSince insurance, particularly liability insurance, is such an important component when it comes a construction project, understanding certain nuances such as a
Coblentz Agreement (a what kind of agreement agreement?!?—keep reading) becomes helpful.
If there is a construction defect claim / lawsuit, the implicated parties (e.g., contractor, design professional, subcontractor, sub-consultants) are going to tender the claim / lawsuit to their respective liability insurer. This is what they should be doing – notifying the insurer so that the insurer can defend them from the claim / lawsuit and indemnify them from covered damages associated with the claim / lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Will COVID-19 Permanently Shift the Balance between Work from Home and the Workplace?
April 13, 2020 —
Adam Weaver - Gravel2Gavel Construction & Real Estate Law BlogOn March 15, 2020, the Center for Disease Control and Prevention (CDC) issued formal guidance to combat the spread of the coronavirus by recommending against gatherings of 50 or more people for the next eight weeks (CDC guidance), which includes nearly every office building in America. Thus, began the most significant work from home experiment this country has ever seen.
With the majority of the workforce working from home, many employees see this as an opportunity to finally prove that, “yes, that meeting could have been an email.” However, while workers will not be distracted by constant (and potentially unnecessary) meetings, a number of issues and questions arise with working from home.
Most importantly, is this working from home experiment a temporary opportunity for businesses to test remote work ideas or is this the new normal? And how will this affect commercial real estate moving forward?
Read the court decisionRead the full story...Reprinted courtesy of
Adam Weaver, PillsburyMr. Weaver may be contacted at
adam.weaver@pillsburylaw.com
Identifying and Accessing Coverage in Complex Construction Claims
September 29, 2021 —
Jeffrey J. Vita & Michael V. Pepe - Saxe Doernberger & Vita, P.C.I. Introduction
First-party, third-party, builder’s risk, professional liability, commercial general liability, wrap-ups, and additional insured status are all potential sources of insurance coverage for a large construction loss. Therefore, it is critical for construction industry participants, from owners and developers to general contractors and their subcontractors, to have a functional knowledge of the different types of insurance coverage available to them and how those coverages intersect to respond to a loss. This paper presents a brief overview of the various types of coverage available to contractors, construction managers, and owners in a large construction loss and the risks each coverage is designed to insure.
In general, there are two forms of coverage: (1) First-party liability coverage, which protects an insured’s own losses on a project during construction; and (2) Third-party liability coverage, which insures the project participants for losses that become the subject of claims or suits brought against the project participants by third parties. When a loss occurs, such as property damage, both types of coverage can be implicated. For example, if a fire burns down a building under construction, the contractor likely would incur first-party losses such as cleanup costs. The contractor may also have third-party exposure if the owner alleges that the contractor was responsible for the fire. On the other hand, when a bodily injury occurs, all losses to the contractor will be third-party losses. A broad overview of each of these policies is provided below.
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita and
Michael V. Pepe, Saxe Doernberger & Vita
Mr. Vita may be contacted at JVita@sdvlaw.com
Mr. Pepe may be contacted at MPepe@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of