CDJ STAFFA judge has ruled that a plaintiff can go forward with her suit that she was injured by a defective archway during a birthday party. A three-judge panel of the California Court of Appeals issued this ruling on January 23, 2012, in the case of Trujillo v. Cosio.
Ms. Trujillo attended a birthday party at the home of Maria Cosio and Joel Verduzco. A piñata was hung between a tree and a brick archway. Ms. Trujillo went to get candy that had fallen from the piñata, during which the archway fell on her hand. Subsequent examination of the archway showed that it had not been “properly anchored to the supporting pillars to protect the arch from falling.”
Ms. Cosio and Mr. Verduzco argued that they could not have been aware of the defective nature of the archway’s construction, as it had been built at the request of the prior property owner. The structure was constructed without building permits. Mark Burns, a civil engineer testifying for the plaintiff, said that “a reasonable property owner would have thoroughly tested the archway to ensure it was capable of withstanding such horizontal forces before allowing children to enter into the area.” Mr. Burns noted that twenty rope pulls would have been sufficient to demonstrate the structure’s instability.
The trial court rejected Mr. Burn’s statements, finding that the respondents did not have any knowledge of the defect and that a visual inspection should have sufficed. The court noted that this a triable issue, whether visual inspection suffices, or whether the property owners should have done as Mr. Burns suggested and yank a rope twenty times. The court noted that “although a jury may ultimately disagree with Burn’s opinion, it was supported by sufficient foundation and was not speculative.”
The opinion was written by Judge Flier, with Judges Rubin and Grimes concurring.
Read the court’s decison…
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Launches Program to Combat Trenching Accidents
October 16, 2018 —
Tom Ichniowski – Engineering News-RecordIn the wake of a recent rise in fatal trenching cave-ins, the federal Occupational Safety and Health Administration has begun a targeted education and enforcement program to try to reverse the trend.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Ichniowski, ENRMr. Ichniowski may be contacted at
ichniowskit@enr.com
Carrier Has Duty to Defend Claim for Active Malfunction of Product
October 19, 2020 —
Tred R. Eyerly - Insurance Law HawaiiRejecting that the underlying claim was based solely on faulty workmanship, the Third Circuit held the insurer had a duty to defend allegations of a malfunctioning product. Nautilus Ins. Co. v. 200 Christina Street Partners LLC, 2020 U.S. App. LEXIS 22118 (3d Cir. July 16, 2020).
The insureds were sued by homeowners in two separate suits alleging defects in the construction of their homes. Nautilus defended under a reservation of rights. Nautilus filed suit in District Court and moved for judgment on the pleadings. The District Court denied the motion, finding Nautilus had a duty to defend because the underlying claims sufficiently alleged product--related tort clams that could fall within the scope of coverage under the relevant policies.
The Third Circuit affirmed. There was a distinction between a claim of faulty workmanship, for which the insurer did not have a duty to defend, and a claim of "active malfunction" of a product, for which an insurer did have such a duty. An active malfunction was sufficiently fortuitous as to constitute an "occurrence."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Aarow Equipment v. Travelers- An Update
January 16, 2024 —
Christopher G. Hill - Construction Law MusingsPreviously here at Musings, I discussed the application of pay if paid clauses and the Miller Act. The case that prompted the discussion was the Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co. case in which the Eastern District of Virginia Federal Court determined that a “pay if paid” clause coupled with a proper termination could defeat a Miller Act bond claim. However, as I found out a couple of weeks ago at the VSB’s Construction Law and Public Contracts section meeting, the 4th Circuit Court of Appeals reversed and remanded this case in an unpublished opinion (Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co.)
In it’s opinion, the 4th Circuit looked at some of the more “interesting” aspects of this case. One of these circumstances was that Syska (the general contractor) directed Aarow to construct sedimentary ponds and other water management measures around the project (the “pond work”), which both agreed was outside of the scope of the work defined in their subcontract. Syska asked that the government agree to a modification of the prime contract and asked Aarow to wait to submit its invoice for the pond work until after the government issued a modification to the prime contract and Syska issued a change order to the subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Georgia Appellate Court Supports County Claim Against Surety Company’s Failure to Pay
August 30, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPIn 2015, Hall County (Georgia) brought legal action against Selective Insurance Company of America, Inc., the surety company for contractor Ruby Forrest. Hall County had contracted Ruby Forrest to complete and maintain sidewalk systems within three residential subdivisions that Ruby Forrest owned and was developing. Ruby Forrest did not complete the work as promised, and Hall County brought action against the contractor’s surety to recover under performance / maintenance bonds for uncompleted work and to assert bad faith claim for punitive damages and attorney fees.
Selective Insurance did not dispute that it had issued the bonds, that Ruby Forrest did not complete the sidewalk systems within the bond periods or their extensions, or that Hall County provided Selective Insurance with timely notice of Ruby Forrest’s failure to complete the work. Instead, Selective Insurance asserted that the original claim by Hall County was time-barred under a provision in the bonds that stated that “the Issuer will have no more liability after” the expiration date of the bond.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Meet Your Future Team Members: AI Agents
December 10, 2024 —
Aarni Heiskanen - AEC BusinessIf you’ve been following the discussion around AI, you’re familiar with the concept of AI agents.
AI agents can be understood as intelligent automation that operates independently, monitoring its environment and taking action without constant human input. Unlike traditional software requiring specific inputs to produce predictable outputs, AI agents can adapt to varying conditions and user needs.
AI agents can be based on various technologies, including Large Language Models. They can also be constructed using other AI technologies, such as rule-based systems, machine learning algorithms, and specialized models tailored to specific tasks.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
California Court of Appeal Affirms Trial Court’s Denial of anti-SLAPP Motion in Dispute Over Construction of Church Facilities
March 27, 2023 —
Garrett A. Smee & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPOn February 28, 2023, the California Fourth District Court of Appeal, Division One, issued an opinion in Billauer v. Escobar-Eck (D079835), affirming the trial court’s denial of an anti-SLAPP motion stemming from a public debate over a Church construction project.
The Appellant (Billauer) ran several social media sites as a “neighborhood activist.” The Respondent (Escobar-Eck) ran a land use and strategic planning firm in San Diego. The “All People’s Church” had hired Escobar-Eck’s company in 2019 to obtain City approval for a Church campus. During a Zoom presentation by Escobar-Eck to a Church planning group on November 11, 2020, Billauer, as a participant in the meeting sent a chat to Escobar-Eck stating: “I’m going to make sure you get sent back to where you came from.” Over the span of the next six months, from November 11, 2020 to April 8, 2021, Billauer continued the onslaught through a series of five posts on Instagram and Facebook, attacking Escobar-Eck. On December 10, 2020, Escobar-Eck fired back with a Twitter post to Billauer’s employer, Wells Fargo, labeling Billauer as a cyberbullying racist.
Reprinted courtesy of
Garrett A. Smee, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Smee may be contacted at gsmee@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Housing-Related Spending Makes Up Significant Portion of GDP
February 05, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Molly Boesel on the Insight Blog, “housing-related spending makes up 17.3 percent of the GDP.” Boesel explained: “To calculate the portion of domestic spending that is related to housing, CoreLogic looks at three expenditures from the release: residential investment (the construction of new single- and multi-family houses), spending on housing services (rent, owner’s equivalent rent and utilities) and spending on furnishings and durable goods. Together, these expenditures made up 17.3 percent of total real GDP in the fourth quarter of 2013.”
Read the court decisionRead the full story...Reprinted courtesy of