Lost Productivity or Inefficiency Claim Can Be Challenging to Prove
May 02, 2022 —
David Adelstein - Florida Construction Legal UpdatesOne of the most challenging claims to prove is a lost productivity or inefficiency claim. There is an alluring appeal to these claims because there are oftentimes intriguing facts and high damages. But the allure of the presentation of the claim does not compensate for the actual burden of proof in proving the lost productivity or inefficiency claim, which will require an expert. And they really are challenging to prove.
Don’t take it from me. A recent Federal Claims Court opinion, Nova Group/Tutor-Saliba v. U.S., 2022 WL 815826, (Fed.Cl. 2022), that I also discussed in the preceding
article, exemplifies this point.
To determine lost productivity or inefficiency, the claimant’s expert tried three different methodologies.
First, the expert looked at industry standard lost productivity factors such as those promulgated by the Mechanical Contractor’s Association. However, the claimant was not a mechanical contractor and there is a bunch of subjectivity involved when using these factors. The expert decided not to use such industry standard factors correctly noting they provide value when you are looking at a potential impact prospectively, but once you incur actual damages and have real data, it is not an accurate measure.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Terminating Notice of Commencement Without Contractor’s Final Payment Affidavit
October 23, 2018 —
David Adelstein - Florida Construction Legal UpdatesPrior to construction work being performed on your property, a Notice of Commencement should be recorded. Among other things, construction liens will relate back in time to an effective Notice of Commencement (meaning it has not expired). For this reason, lenders or others will want the Notice of Commencement to be terminated when the job is complete by recording in the official records a Notice of Termination of the Notice of Commencement. There is a statutory procedure to terminate a Notice of Commencement pursuant to Florida Statute 713.132.
Frequently, a clerk will want the Notice of Termination of the Notice of Commencement to be accompanied with a Contractor’s Final Payment Affidavit because 713.132 says, in material part:
(2) An owner has the right to rely on a contractor’s affidavit given under s. 713.06(3)(d), except with respect to lienors who have already given notice, in connection with the execution, swearing to, and recording of a notice of termination. However, the notice of termination must be accompanied by the contractor’s affidavit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Applying Mighty Midgets, NY Court Awards Legal Expenses to Insureds Which Defeated Insurer’s Coverage Claims
February 10, 2020 —
Anthony L. Miscioscia & Timothy A. Carroll - White and Williams LLPIs an insured (or putative insured) entitled to recover its legal expenses if it is successful in coverage litigation? In some states, no. In many other states, yes – based on either a statute or the common law. In New York, an insured may recover such expenses if it was “cast in a defensive posture by the legal steps an insurer takes in an effort to free itself from its policy obligations,” and, while forced into that posture, the insured defeats the insurer’s claim. Mighty Midgets, Inc. v. Centennial Ins. Co., 389 N.E.2d 1080, 1085 (N.Y. 1979). As a corollary to that rule, the insured is not entitled to its expenses “in an affirmative action brought by [the insured] to settle its rights. . . .” Id. at 1085. Earlier this week, the New York federal court in United Specialty Ins. Co. v. Lux Maint. & Ren. Corp., 2019 U.S. Dist. LEXIS 201805 (S.D.N.Y. Nov. 20, 2019) became the latest to apply the Mighty Midgets rule, awarding several insureds their legal expenses after defeating the insurer’s declaratory judgment action.
In Lux, the CGL insurer of a façade-renovation contractor sued the contractor (its named insured) and several owners of a hospital (putative additional insureds) at which the façade-renovation work took place, claiming that the insurer did not owe a defense or indemnity to any of those companies in connection with an underlying bodily injury action brought by an employee of the contractor who was injured while performing the work. The insurer and the putative additional insureds filed cross-motions for summary judgment on the coverage issues, with the putative additional insureds also seeking to recover their legal expenses for defending against the insurer’s action. The U.S. District Court for the Southern District of New York concluded that, based on the contractor’s agreement to provide coverage for the hospital owners, and a comparison between the underlying allegations and the policy, the insurer owed the hospital owners coverage as additional insureds to the contractor’s policy; the court also concluded that the insurer owed coverage for the contractor’s contractual defense and indemnity obligations to the hospital owners. After concluding that the insurer’s claim that it did not owe coverage lacked merit, the court turned to the additional insureds’ request for their legal expenses.
The court examined the “well settled” rule under New York law “that an insured cannot recover his legal expenditure in a dispute with an insurer over coverage, even if the insurer loses and is obligated to provide coverage,” but also New York’s “limited exception” to that rule, “under which an insured who is ‘cast in a defensive posture by the legal steps an insurer takes in an effort to free itself from its policy obligations, and who prevails on the merits, may recover attorneys’ fees incurred in defending against the insurer’s action.’ ” Lux, 2019 U.S. Dist. LEXIS 201805, at *18 (quoting Mighty Midgets, 389 N.E.2d at 1085).
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams and
Timothy A. Carroll, White and Williams
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Design-build Trends, Challenges and Risk Mitigation
August 26, 2019 —
Bill Webb - Construction ExecutiveAs the commercial construction industry continues to evolve and grow, design-build methodologies are becoming increasingly popular for their ability to speed completion rates, control costs and produce an overall more efficient process under the guidance of the design-build contractor (DBC).
The Design-Build Institute of America (DBIA) predicts that “over half of owners have already or will use design-build in the next five years” due to the opportunities it provides for innovation and fast-tracking projects. The organization also expects that design build methodologies will account for approximately 45% of all nonresidential construction spending over the 2018 – 2021 forecast period.
Design-build provides many benefits to projects owners, however, holding contractual responsibility for both design and construction does accompany its fair share of challenges and risks for the DBC. Although basic risk management principles are inherent to design build through improved communication and collaboration, strong contractual language and proper insurance programs can greatly control risk exposures.
Reprinted courtesy of
Bill Webb, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Webb may be contacted at
Bill.Webb@rtspecialty.com
Owner Bankruptcy: What’s a Contractor to Do?
February 28, 2018 —
Troy R. Covington and Stephen M. Parham - Construction Executive MagazineBankruptcy of the owner or developer of a real estate construction project can be very unsettling to contractors. But a declaration of bankruptcy by the developer, in and of itself, does not constitute a breach of contract such that the contractor can stop working. Contract provisions providing that the contract is terminated if a party becomes insolvent or files for bankruptcy are generally unenforceable.
Partially-performed construction contracts are executory contracts, meaning that the obligations of the parties to the contract have not yet been fully performed. The Bankruptcy Code allows a bankruptcy trustee (in a Chapter 7 dissolution case) or the debtor-in-possession (in a Chapter 11 reorganization case) either to assume or to reject an executory contract. A debtor-in-possession has until the time of the confirmation of its plan of reorganization to decide if it will assume or reject the contract. The contractor may ask the bankruptcy court to require the debtor-in-possession to make a decision on the contract sooner, but the court will most likely give the debtor-in-possession a fair amount of time to make the decision.
Reprinted courtesy of
Troy R. Covington and
Stephen M. Parham, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Covington may be contacted at sparham@bloomparham.com
Mr. Parham may be contacted at tcovington@bloom-law.com
Read the court decisionRead the full story...Reprinted courtesy of
A Win for Policyholders: Court Finds Flood Exclusion Inapplicable to Plumbing Leaks Caused by Hurricane Rainfall
October 21, 2024 —
Kelly A. Johnson & Damian S. Barquin - Saxe Doernberger & Vita, P.C. A recent decision by a federal court helps clear the path to coverage for property owners this hurricane season. The Court deemed one property policy’s flood exclusion inapplicable to bar coverage for water damage from backed-up drainage and overflow caused by excessive rainfall. The case, styled G.E.M.S. Partners LLC v. AmGUARD Ins. Co., — F.Supp. 3d —, No. CV 22-1664, 2024 WL 3568932 (D.N.J. July 29, 2024)), involved a familiar dispute between the insured and insurer following damage to covered property after a named storm’s heavy rainfall.
Here, G.E.M.S. Partners LLC (“Insured”) obtained a commercial property policy from AmGUARD Insurance Company (“AmGUARD”) to cover three neighboring buildings in Union, New Jersey. In September 2021, intense rainfall from Hurricane Ida overwhelmed the local infrastructure and sewer system, leading to water leakage from plumbing fixtures at the insured property. To secure coverage under its AmGUARD policy, the Insured wisely relied on its “Water Back-Up and Sump Overflow Endorsement” (“Back-Up/Overflow Endorsement”). Under this endorsement, AmGUARD promised to “pay for ... damage ... caused by ... water ... which backs up through or overflows or is otherwise discharged from a sewer.”1 Indeed, a plumber that inspected the buildings following Hurricane Ida described the root cause of the water damage as a “back up” of “sewer ... water.”2
Reprinted courtesy of
Kelly A. Johnson, Saxe Doernberger & Vita, P.C. and
Damian S. Barquin, Saxe Doernberger & Vita, P.C.
Ms. Johnson may be contacted at KJohnson@sdvlaw.com
Mr. Barquin may be contacted at DBarquin@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
London Shard Developer Wins Approval for Tower Nearby
November 05, 2014 —
Neil Callanan - BloombergSellar Property Group, developer of the Shard in London, won local government approval to build a 26-story residential tower close to the skyscraper on the south bank of the River Thames.
The council for the Southwark borough voted in favor of the 148-apartment project, which also includes a 16-story tower, at a meeting yesterday, Sellar spokesman Baron Phillips said by e-mail. The project, like the Shard, will be developed in a partnership with the state of Qatar.
Developers plan to construct more than 25,000 luxury properties in London worth more than 60 billion pounds ($96 billion) over the next decade, EC Harris said in an Oct. 7 report. The homes approved yesterday at the Fielden House site are expected to sell for about 800,000 pounds each, according to a filing by the borough.
Read the court decisionRead the full story...Reprinted courtesy of
Neil Callanan, BloombergMr. Callanan may be contacted at
ncallanan@bloomberg.net
Haight Brown & Bonesteel Ranked on the 2017 "Best Law Firms" List by U.S. News - Best Lawyers
November 10, 2016 —
Haight Brown & Bonesteel LLPU.S. News – Best Lawyers® ranked Haight Brown & Bonesteel on the 2017 “Best Law Firms” list in the Metropolitan Tier 1 Ranking in Los Angeles for their defense work in insurance law and personal injury litigation.
Read the court decisionRead the full story...Reprinted courtesy of