Garret Murai - California Construction Law BlogA rather short case for a short week.
In Gerlach v. K. Hovnanian’s Four Seasons at Beaumont, LLC, 82 Cal.App.5th 303 (2022), the 4th District Court of appeals examined provisions of the Right to Repair Act (Civ. Code §§895 et. seq), also known as “SB 800” after its original bill number, as it applies to roofs.
The Gerlach Case
Lynn Gerlach and Lola Seals are homeowners who purchased their homes in the Four Seasons at Beaumont adult community, for those 55 year old and older, located in Beaumont, California. Gerlach purchased her home when it was built in 2006. Seals purchased her home from the original owners in 2015.
In 2015 and 2016, Gerlach and Seals served the developer, K. Hovnanian’s Four Seasons at Beaumont, LLC, with claim notices under the Right to Repair Act. The Right to Repair Act, as its name implies, provides notice requirements and repair rights by developers of new single-family homes. The Right to Repair Act also includes construction standards, the violation of which, provides homeowners with a statutory basis for bringing construction defect claims.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Traub Lieberman Team Obtains Summary Judgment in Favor of Client Under Florida’s Newly Implemented Summary Judgment Standard
August 23, 2021 —
Heather Fleming & Gregory H. Lercher - Traub LiebermanOn July 27, 2021, the Circuit Court of the Ninth Judicial Circuit in and for Osceola County, Florida granted summary judgment in favor of a client insurer defended by Traub Lieberman Partner Heather M. Fleming and Associate Gregory H. Lercher in connection with a first party property lawsuit arising from Hurricane Irma that involved multiple, comingled claims, in part resolved via prior appraisal.
As of May 1, 2021, Florida state courts have applied a new summary judgment standard after Florida’s longstanding rule was amended by the Supreme Court of Florida. The amendment aligns Florida’s standard with that of the federal courts and the supermajority of states that have already adopted the federal summary judgment standard codified in Rule 56 of Federal Rules of Civil Procedure. The Supreme Court of Florida’s stated goal in adopting the new standard across the Sunshine State was to improve the fairness and efficiency of Florida's civil justice system, to relieve parties from the expense and burdens of meritless litigation, and to save the work of juries for cases where there are real factual disputes that need resolution.
Reprinted courtesy of
Heather Fleming, Traub Lieberman and
Gregory H. Lercher, Traub Lieberman
Ms. Fleming may be contacted at hfleming@tlsslaw.com
Mr. Lercher may be contacted at glercher@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Former NJ Army Base $2B Makeover is 'Buzzsaw' of Activity
June 14, 2021 —
Tom Stabile - Engineering News-RecordTake a developed property the size of New York City’s Central Park with 5 million sq ft of building area, program in new construction or renovation over 20 years and across three dozen parcels for 1,600 housing units, 300,000 sq ft of civic or government space, 500,000 sq ft for retail and 2 million sq ft of offices, and you have a pretty ambitious undertaking. The $2-billion effort to redevelop Fort Monmouth, a decommissioned former U.S. Army base in the thick of New Jersey’s suburban sprawl, is all kinds of ambitious.
Reprinted courtesy of
Tom Stabile, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (12/4/24) – Highest Rate of Office Conversions, Lending Caps for Fannie Mae and Freddie Mac and Affordability Challenges for Homebuyers
December 23, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, infrastructure-related ballot initiatives, U.S. Green Building Council’s success stories, support for sustainable building, and more!
- 2024 is expected to see the highest rate of office conversions since CBRE began tracking them in 2016. (Nish Amarnath, SmartCities Dive)
- The Federal Housing Finance Agency has established lending caps of $73 billion each for Fannie Mae and Freddie Mac, allowing them to purchase a total of up to $146 billion in multifamily loans in 2025. (Leslie Shaver, Multifamily Dive)
- A number of infrastructure-related initiatives with the potential to impact facilities managers were on the ballot during the 2024 U.S. presidential election. (Joe Burns, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Traub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp Obtain Summary Judgment in Favor of Residential Property Owners
December 13, 2022 —
Gregory S. Pennington & Emily A. Velcamp - Traub LiebermanTraub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp obtained summary judgment in favor of their clients, owners of a residential property [the “Owners” or “Defendants”] used as a short-term rental in Beach Haven, New Jersey. Plaintiff alleged injuries resulting from a fall into an open water meter pit, located in the public sidewalk abutting the Owners’ property during the time within which the property was rented to plaintiff and his family. According to plaintiff, defendants breached their duty owed to him, relying on a Borough of Beach Haven Ordinance, thereby allowing the water meter pit to be raised in an unsafe manner, which resulted in plaintiff’s fall and subsequent injuries.
After the Court denied defendants’ initial Motion for Summary Judgment on the grounds that issues of material fact existed regarding defendants’ duty and the alleged breach of that duty, a Motion for Reconsideration was filed. Mr. Pennington and Ms. Velcamp argued that their clients, as residential landowners, owed no duty of care to plaintiff for the raised condition of the water meter pit lid, located in the abutting sidewalk, as they did not cause or contribute to the alleged condition. Defendants further argued that even if a duty of care existed, no breach occurred given the lack of notice to defendants, either actual or constructive. Plaintiff attempted to argue that defendants had constructive notice of the lid’s raised condition, relying on his expert report and the fact that defendants had 3.5 months from the date the property was purchased, to the date of the subject accident to discover the lid’s raised condition. Mr. Pennington and Ms. Velcamp successfully argued that despite plaintiff’s allegations and the findings contained in plaintiff’s expert report, authored 2 months after the alleged accident, there was still no credible, material evidence to say how long the water meter pit lid was in that raised condition to allow defendants a reasonable time to discover it, remedy it, or report it to the Borough.
Reprinted courtesy of
Gregory S. Pennington, Traub Lieberman and
Emily A. Velcamp, Traub Lieberman
Mr. Pennington may be contacted at gpennington@tlsslaw.com
Ms. Velcamp may be contacted at evelcamp@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
4 Ways to Mitigate Construction Disputes
March 20, 2023 —
Bill Shaughnessy - ConsensusDocsResolving construction disputes in litigation (court or arbitration) can be expensive and may drag on for years. Most disputes could have been avoided, or at least mitigated, had the parties (both owners and contractors) identified contract risks during negotiations and been more proactive in communicating the risks during execution of the work. This article highlights four practical risk management approaches that help all parties focus on their mutual interest in close coordination and clear communication at the beginning of the project as well as throughout performance:
- Identifying and allocating risks;
- Accurate scheduling;
- Clear project documentation and communication; and
- Real-time dispute resolution.
The intent of these techniques is not to shift legal obligations or risks. Rather, the intent is to keep project personnel and project management for all the participants focused on communicating and working together, including responsibly confronting real problems to avoid or mitigate their impact. Allocating risks, scheduling, project documentation and communication, and real-time dispute resolution are independently relevant on a bilateral basis between the owner, designer, and the various contractors. These approaches and their diligent execution by the parties during construction contribute far more to a successful project than anything lawyers and claims consultants can contribute in after-the-fact legal proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker LLP (ConsensusDocs)Mr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com
Another Defect Found on the Bay Bridge: Water Leakage
February 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the San Francisco Chronicle, the eastern span of the Bay Bridge has dealt with alleged “defective welds” and “cracked steel rods,” and now there are reports of leakage. The Chronicle stated that rainwater “is dripping into the steel structure beneath the road deck on the suspension stretch of the span, which,” according to Caltrans “is supposed to be watertight.”
Water corrosion on a bridge could cost $6.4 billion, the San Francisco Chronicle claimed. Caltrans said that they “are going to have teams of engineers and inspectors there this weekend to assess the problem.”
Read the court decisionRead the full story...Reprinted courtesy of
Late Notice Kills Insured's Claim for Damage Due to Hurricane
December 27, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion for summary judgment was granted based upon the insured's late notice nearly two years after a hurricane caused property damage. Ramirez v. Scottsdale Ins. Co., 2021 U.S. Dist. LEXIS 209716 (S.D. Fla. Oct. 29, 2021).
Plaintiff alleged he suffered property loss due to wind and water damage from Hurricane Irma on September 10, 2017. The roof, exterior, and interior of the home were damaged.
On May 20, 2019, twenty months after the hurricane, plaintiff first notified Scottsdale of his claim for damages. An adjuster inspected and observed wind, wear and tear, and deterioration damage to the roof tile, as well as interior water damage to portions of the home. The claim was denied based upon wind, wear and tear, and deterioration exclusions in the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com