Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Modernist Houses Galore! [visual candy for architects]
February 25, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaDo you like modern architecture? Is Frank Lloyd Wright someone you wish you could have met?
If so, then you’ll want to check out the new “Masters Gallery” of the North Carolina Modernist Houses (NCMH) group. With changes and additions announced this week, it’s Gallery is America’s largest open digital archive of Modernist houses, as well as the internationally known Modernist architects who designed them.
Currently, the Gallery showcases over 30 architects with extensive house histories and over 10,000 photos. The Gallery is extensive and searchable and includes, among many other notables, Frank Gehry and, of course, Frank Lloyd Wright.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback can be contacted at
mbrumback@rl-law.com
New Nafta Could Settle Canada-U.S. Lumber War, Resolute CEO Says
February 02, 2017 —
Jen Skerritt - BloombergA renegotiation of Nafta could be used to settle a lumber dispute that’s been simmering between Canada and the U.S. for decades and threatens to make housing unaffordable for thousands of Americans, according to the world’s largest newsprint maker.
Read the court decisionRead the full story...Reprinted courtesy of
Jen Skerritt, BloombergMs. Skerritt may be followed on Twitter @jenskerritt
Insurance and Your Roof
November 13, 2013 —
CDJ STAFFThose seeking home insurance should look up. Bankrate points out that the type of roof a home has can affect how much it costs to insure it. “The roof is the first layer that wind, hail, wildfire and other hazards really begin to act on,” Tim Reinhold, the chief engineer at the Insurance Institute for Business and Home Safety, told the site.
For insurers, the most problematic roof type is probably wood shakes. “Some companies won’t even insure certain roof types, such as wood shakes, in high fire-risk areas,” said Robert Hunter, the director of insurance for the Consumer Federation of America.
Not that other roof types are problem-free. Metal roofs can corrode, particularly when two different metals touch. Shingles age more quickly than other roof types, becoming brittle, and they can blow off in high winds. Tile roofs are expensive, something insurers are guaranteed to factor into the insurance rates.
Read the court decisionRead the full story...Reprinted courtesy of
General Contractor/Developer May Not Rely on the Homeowner Protection Act to Avoid a Waiver of Consequential Damages in an AIA Contract
August 04, 2011 —
Higgins, Hopkins, McLain & Roswell, LLCRecently, in Caribou Ridge Homes, LLC v. Zero Energy, LLC, et al., Case No. 10CV1094, Boulder County District Court Judge Ingrid S. Bakke entered a ruling and order on the Plaintiff’s Motion for Determination of Question of Law Pursuant to C.R.C.P. 56(h) on Issue of Damages. The Order found that the Plaintiff was not a homeowner intended to be protected by the Homeowner Protection Act (the “HPA”) and thus could not pursue its claims for consequential damages against Defendant.
By way of background, on June 18, 2008, Plaintiff Caribou Ridge Homes, LLC (“Caribou”) entered into a Standard Form Agreement Between Owner and Contractor AIA Document A114-2001 (the “Contract”) with Defendant Zero Energy, LLC (“Zero Energy”). Plaintiff hired Zero Energy to serve as a general contractor for the construction of a single-family home in the Caribou Ridge subdivision in Nederland, Colorado. A provision in the contract contained a mutual waiver of consequential damages (“Waiver”).
Read the full story…
Reprinted courtesy Higgins, Hopkins, McLain & Roswell, LLC
Read the court decisionRead the full story...Reprinted courtesy of
Florida Enacts Property Insurance Overhaul for Benefit of Policyholders
July 05, 2023 —
Laura Farrant & Bradley S. Fischer - Lewis BrisboisFort Lauderdale, Fla. (June 13, 2023) – On June 1, 2023, Governor Ron DeSantis signed into law CS/SB 7052 (the Act), increasing consumer protection and insurer accountability in Florida. The newly enacted and amended statutes under CS/SB 7052 bolster policyholder protections and impose greater insurer oversight, including heightened penalties for insurer misdeeds in the state under a new law that will take effect on July 1, 2023 (this legal alert does not address all of the statutory revisions associated with the Act). As House Speaker Paul Renner noted, “The insurance legislation signed by Governor DeSantis today . . . not only empowers homeowners, but also cultivates market-driven competition, ultimately leading to lower costs.”
Statutory Revisions Regarding Insurance Coverage
The Act prohibits authorized insurers from cancelling or nonrenewing a property insurance policy for a residential property or dwelling that was damaged by any covered peril until the earlier of: (a) when the property has been repaired; or (b) one year after the insurer issues the final claim payment. The Act also expands current law prohibiting authorized insurers from cancelling or nonrenewing a residential property insurance policy until 90 days after repairs are completed for damages resulting from a hurricane or wind loss that is the subject of a state of emergency declared by the Governor and for which the Office of Insurance Regulation (OIR) has issued an emergency order. See Fla. Stat. §627.4133(2)(d)(1)(a) and (b) (Notice of cancellation, nonrenewal, or renewal premium).
Reprinted courtesy of
Laura Farrant, Lewis Brisbois and
Bradley S. Fischer, Lewis Brisbois
Ms. Farrant may be contacted at Laura.Farrant@lewisbrisbois.com
Mr. Fischer may be contacted at Bradley.Fischer@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Happenings in and around the 2015 West Coast Casualty Seminar
May 07, 2015 —
Beverley BevenFlorez-CDJ STAFFWest Coast Casualty Construction Defect Seminar returns to the Disneyland Hotel next week (May 14th and 15th), and the Construction Defect Journal has compiled a list of concerts, sporting events, and museum exhibitions taking place in and around Anaheim. Whether you like to spend your personal time checking out a new band, or watching your favorite Angel slide into home, or perusing the local art museum, there is something to spark your interest.
CONCERT VENUES
THE HOUSE OF BLUES IN ANAHEIM
Located in Downtown Disney, The House of Blues in Anaheim is a short walk from the convention hall.
Live Band Karaoke
Wednesday, May 13th Starting at 10pm
No Cover
For More Information...
Rockin’ The Blues with Griff Hamlin
Thursday, May 14th at 10pm
For More Information...
Tyrone Wells
Saturday, May 16th at 7pm
For More Information and to Purchase Tickets...
THE GROVE OF ANAHEIM
Near Angel Stadium, the Grove of Anaheim is just a few miles away from the seminar location.
Ministry
Monday, May 11th Doors Open at 7pm / Show Begins at 8pm
For More Information and to Purchase Tickets...
Kamelot plus Special Guest Dragonforce
Friday, May 15th Doors Open at 7pm / Show Begins at 8pm
For More Information and to Purchase Tickets...
CHAIN REACTION
Attendees can escape to this all-ages club that’s just a ten minute drive from the Disneyland Hotel.
Ice Nine Kills
Wednesday, May 13th at 7pm
For More Information and to Purchase Tickets...
Warped Tour Battle of the Bands
Thursday, May 14th at 7pm
For More Information and to Purchase Tickets...
Manifest Presents
Saturday, May 16th at 7pm
For More Information and to Purchase Tickets...
SPORTING EVENTS
ANGEL’S STADIUM – BASEBALL
Take care of your popcorn-and-peanuts-and-cracker-jacks fix while cheering for the Angel’s—conveniently just a few miles from the Disneyland Hotel.
Angels v. Colorado Rockies
Tuesday, May 12th at 7:05pm
Wednesday, May 13th at 7:05pm
For More Information and to Purchase Tickets...
MUSEUM EXHIBITIONS
MUZEO
This local museum and cultural center is a short drive from the convention hall.
Cougars and Grizzlies: Sharing their Path
April 18, 2015-September 13th, 2015
Museum Days/Hours: Tuesday – Sunday (Closed Mondays) / 10 am to 5 pm
For More Information and to Purchase Tickets...
BOWERS MUSEUM (Santa Ana)
Voted “The Best Museum in Orange County” by OC Register Readers for 16 consecutive years, this arts and cultural center is worth the fifteen minute drive.
Qi Baishi: China’s Modern Master
April 11th, 2015-July 11th, 2015
Museum Days/Hours: Tuesday – Sunday (Closed Mondays) / 10 am to 4 pm
For More Information and to Purchase Tickets...
Where Ends Meet: A Retrospective of Works by Nancy Ravenhall Johnson
March 13th, 2015-August 16th, 2015
Museum Days/Hours: Tuesday – Sunday (Closed Mondays) / 10 am to 4 pm
For More Information and to Purchase Tickets...
Exhibition: Adams, Curtis, and Weston: Photographers of the American West
May 16th, 2015-November 29th, 2015
Museum Days/Hours: Tuesday – Sunday (Closed Mondays) / 10 am to 4 pm
For More Information and to Purchase Tickets...
Lecture: Adams, Curtis, and Weston: Photographers of the American West
Saturday, May 16th from 1:30pm to 2:30pm
For More Information and to Purchase Tickets...
Read the court decisionRead the full story...Reprinted courtesy of
Limiting Plaintiffs’ Claims to a Cause of Action for Violation of SB-800
November 18, 2011 —
Samir R. Patel, Esq., Lorber, Greenfield, & Polito, LLPThere has been a fair share of publicity about the SB-800 amendments to the Civil Code (Civil Code section 896, et seq.) that codified construction defect litigation in 2002. Most of the publicity is geared toward the pre-litigation standards allowing a builder the right to repair before litigation is commenced by a homeowner. Less focus and attention has been given to the fact that violation of the SB-800 performance standards is being used by plaintiff’s counsel as an additional tool in the plaintiff’s pleading tool box against builders. Closer scrutiny to SB-800 reveals that those provisions should in fact act as a limitation to the pleading tools available to plaintiffs and an additional tool for builders in the defense of cases governed by SB-800.
The typical construction defect complaint contains the boiler plate versions of numerous causes of action. These causes of action include Strict Liability, Negligence, Negligence Per Se, Breach of Contract, Breach of Contract – Third-Party Beneficiary, Breach of Express Warranties, Breach of Implied Warranties, among others. The wide array of causes of action leave a defendant “pinned to the wall” because they require a complex defense on a multitude of contract and tort related causes of action. Furthermore, the statutes of limitations as to these claims widely differ depending upon if the particular defect is considered latent or patent. The truth of the matter remains, no matter what the circumstances, if a construction defect matter ultimately goes to trial, it is inevitable that plaintiffs will obtain a judgment on at least one of these causes of action.
On its own, the Strict Liability cause of action can be a thorn in a defendant’s side. A builder is obviously placing a product into the stream of commerce and strict liability is a tough standard to defend against, particularly when it concerns intricate homes comprised of multiple components that originally sold for hundreds of thousands of dollars. A Negligence cause of action can also be difficult to defend because the duty of care for a builder is what a “reasonable” builder would have done under the circumstances. An interpretation of this duty of care can easily sway a jury that will almost always consist of sympathetic homeowners. A Negligence Per Se cause of action can also leave a defendant vulnerable to accusations that a builder violated the Uniform Building Code or a multitude of other obscure municipal construction-related code provisions during the construction of the home. Lastly, the Breach of Contract cause of action leaves a builder relying on dense and intricate purchase and sale agreements with dozens of addenda which leave the skeptical jurors turned off by what they view as one-side, boilerplate provisions. Ultimately, when a matter is about to go to trial, the complexity of these complaints can benefit a plaintiff and increase a plaintiff’s bargaining power against a defendant who is attempting to avoid a potentially large judgment.
Enter the SB-800 statutes. The SB-800 statutes apply to all homes sold after January 1, 2003. Civil Code section 938 specifically states that “[t]his title applies only to new residential units where the purchase agreements with the buyer was signed by the seller on or after January 1, 2003.” (Civil Code §, 938.) As time progresses, more residential construction defect cases will exclusively fall under the purview of SB-800. Slowly but surely more SB-800 governed litigation is being filed, and its exclusive application is looming on the horizon.
On its surface, this “right to repair” regime has left builders with a lot to be desired despite the fact that it is supposed to allow the builder the opportunity to cure any deficiencies in their product before litigation can be filed by potential plaintiffs. However, the application of the time line for repair has shown to be impractical for anything but the most minor problems involving only small numbers of residential units. Moreover, the fact that the fruits of the builder’s investigation into the claimed defects in the pre-litigation context can freely be used as evidence against it in litigation makes builders proceed with trepidation in responding with a repair. For these reasons, more SB-800 litigation can be expected to result due to the shortcomings of the pre-litigation procedures, and savvy defense counsel should anticipate the issues to be dealt with in presenting the defense of such cases at trial.
This fact should not necessarily be met with fear or disdain. Within the SB-800 statutes, the legislature made it clear that they were creating a new cause of action for construction defect claims, but it further made it clear that this cause of action is a plaintiff’s exclusive remedy. The legislature giveth, but at the same time, the legislature taketh away. Throughout numerous provisions within the SB-800 statutes, the Civil Code states that claims for construction defects as to residential construction are exclusively governed by the Civil Code, and that the Civil Code governs any and all litigation arising under breaches of these provisions. Civil Code section 896 specifically states:
In any action seeking recovery of damages arising out of, or related to deficiencies in, the residential construction … the claimant’s claims or causes of action shall be limited to violation of, the following standards, except as specifically set forth in this title. (Civil Code §, 896.)
Civil Code section 896 then provides approximately fifty-plus standards by which a construction defect claim is assessed under that provision. Civil Code section 896 covers everything from plumbing to windows, and from foundations to decks, and in several instances expressly dictates statutes of limitations as to specific areas of construction that severely truncate the 10-year latent damage limitations period. As for any construction deficiencies that are not enumerated within Civil Code section 896, Civil Code section 897 explicitly defines the intent of the standards and provides a method to assess deficiencies that are not addressed in Civil Code section 896. Civil Code section 897 states:
Intent of Standards
The standards set forth in this chapter are intended to address every function or component of a structure. To the extent that a function or component of a structure is not addressed by these standards, it shall be actionable if it causes damage. (Civil Code §, 897.)
Therefore, Civil Code section 897 acts as a catch-all by which defects that are not covered within Civil Code section 896 can be evaluated on a damage standard mirroring the Aas case (damages must be present and actual). The result of sections 896 and 897 being read in combination is a comprehensive, all-inclusive set of performance standards by which any defect raised by Plaintiffs can be evaluated and resolved under a single SB-800 based cause of action.
Civil Code section 943 makes clear that a cause of action for violation of SB-800 performance standards is a plaintiff’s sole remedy for a residential construction defect action. Specifically, Civil Code section 943 states:
Except as provided in this title, no other cause of action for a claim covered by this title or for damages recoverable under 944 is allowed. In addition to the rights under this title, this title does not apply to any action by a claimant to enforce a contract or express contractual provision, or any action for fraud, personal injury, or violation of a statute. (Civil Code §, 943.)
Civil Code section 944 provides the method for computing damages within a construction defect action, as follows:
If a claim for damages is made under this title, the homeowner is only entitled to damages for the reasonable value of repairing any violation of the standards set forth in this title, [and] the reasonable cost of repairing any damages caused by the repair efforts… . (Civil Code §, 944.)
A cursory review of these statutes yields the conclusion that the legislature was attempting to create an exclusive cause of action that trumps all other causes of action where SB-800 applies. The remedy available to plaintiffs is limited to that allowed by the Civil Code. As noted above, “[n]o other cause of action for a claim covered by this title…is allowed.” (Civil Code §, 943.) Therefore, Civil Code sections 896, 897, 943, and 944 specifically prohibit the contract-based and tort-based causes of action typically pled by plaintiffs.
Plaintiff’s counsel has seized upon the language of section 943 to advance the argument that SB-800 still allows a plaintiff to advance typical contract and tort based causes of action. On the surface, this argument may seem compelling, but a minimum of scrutiny of the express language of section 943 dispels this notion. Section 943 says that it provides rights “[i]n addition” to those under the SB-800 Civil Code provisions. Clearly, the language in section 943 is intended to expressly underscore the fact that a plaintiff is not precluded from seeking relief in addition to that allowed under SB-800 for damages not arising from a breach of the SB-800 standards or for damages in addition to those recoverable under Section 944. This language does not provide an unfettered license to bring a Strict Liability, Negligence or other cause of action against a builder where SB-800 applies.
In fact, this language only keeps the door open for plaintiffs to pursue such causes of action not arising from a breach of the SB-800 standards should there be such supporting allegations. For example, if a plaintiff alleges that a builder breached an “express contractual provision” related to the timing of the completion of the home and close of escrow, and the contract specifies damages in this regard, a plaintiff may have a viable separate cause of action for Breach of Contract for recovery of those damages precisely because that is not an issue expressly dealt with in SB-800 in the performance standards under sections 896 and 897, or in the damage recovery terms under 944. As it stands, the vast majority of complaints are seeking redress for violation of the same primary right; that is, defects specifically outlined in Section 896 and 897 or which result in damages as stated in Section 944.
So, how does a builder defend against a complaint that contains multiple causes of action regarding construction defects for a home sold after January 1, 2003? There are numerous ways to approach this. First and foremost, these superfluous and improper causes of action can be attacked by demurrer seeking dismissal of all causes of action other than the cause of action alleging violation of SB-800. If the the time period within which to file a demurrer has passed already, a motion for judgment on the pleadings can be utilized to attack the improper causes of action in the same way as a demurrer can be used for this purpose.
The limitation to a demurrer or motion for judgment on the pleadings is that the judge is restricted to viewing only the four corners of the pleading when making a ruling. It is typical for plaintiffs’ counsel to cleverly (or one might even say, disingenuously) leave the complaint purposely vague to avoid a successful defense attack on the pleadings by not including the original date the residence was sold. In that instance, a motion for summary adjudication can be used to attack a plaintiff’s complaint. By simply providing evidence that the homes were originally sold after January 1, 2003, the improper causes of action should be subject to dismissal by summary adjudication. If the plaintiff is a subsequent purchaser, the builder still has recourse to enforce the pleading limitations under SB-800. Civil Code section 945 states that “[t]he provisions, standards, rights, and obligations set forth in this title are binding upon all original purchasers and their successors-in-interest.” (Civil Code §, 945.)
Attacking a plaintiff’s complaint to eliminate multiple causes of action can have numerous benefits. The practical result is that a plaintiff will only have one viable cause of action. The advantage is that the SB-800 performance standards include the defined performance standards and shortened statutes of limitations periods with regard to specific issues. Furthermore, as to defects which are not specifically provided for in Civil Code section 896, Civil Code section 897 requires a proof of actual damages. Therefore, a plaintiff must provide evidence of current damages and not simply conditions that may potentially cause damage in the future.
The Appellate Courts have yet to directly address and interpret these SB-800 provisions. The time for that is undoubtedly drawing near. For now, however, plaintiffs will have to find ways to accurately plead construction defect claims within the confines of one cause of action for breach of the performance standards enumerated within the Civil Code.
Printed courtesy of Lorber, Greenfield & Polito, LLP. Mr. Patel can be contacted at spatel@lorberlaw.com and Mr. Verbick at tverbick@lorberlaw.com.
Read the court decisionRead the full story...Reprinted courtesy of