Leftover Equipment and Materials When a Contractor Is Abruptly Terminated
November 06, 2023 —
Brian Perlberg - ConsensusDocsTermination for cause is costly and adversarial and has been covered in this
article. But can a terminating party use equipment and tools left behind on the worksite (i.e., a crane)? The answer depends on what is in your contract.
Under
ConsensusDocs, a constructor must give its permission to use any equipment or supplies left at the worksite, such as a crane.
[i] Moreover, the owner must indemnify the constructor for using their equipment. This makes sense because even if a constructor were appropriately terminated for cause, using their equipment and materials they no longer possess or control unfairly creates additional liability exposure. At a minimum, the owner should take on the risk of using the equipment and materials since they benefit from such use.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Perlberg, ConsensusDocs CoalitionMr. Perlberg may be contacted at
bperlberg@ConsensusDocs.org
Federal District Court Continues to Find Construction Defects do Not Arise From An Occurrence
May 10, 2012 —
CDJ STAFFCoverage for construction defects continues to be hotly contested in Hawaii state and federal courts. In a recent decision, Judge Mollway felt bound to follow the Ninth Circuit’s decision in Burlington Ins. Co. v. Oceanic Design & Constr., Inc., 383 F.3d 940, 944 (9th Cir. 2004), where the court found construction defect claims arise from breach of contract, not from an occurrence. Judge Mollway’s most recent decision on the issue is Illinois Nat. Ins. Co. v. Nordic PCL Constr., Inc., 2012 U.S. Dist. LEXIS 58464 (D. Haw. April 26, 2012).
Nordic constructed a grocery store for Safeway. In addition to the grocery store, Nordic built a 165-space rooftop parking deck, retail shops and related improvements. After opening for business in 2007, Safeway experienced significant leaks. Safeway demanded that Nordic repair the parking deck. Nordic sent the demand letter to the insurer, who agreed to appoint counsel subject to a reservation of rights.
Safeway filed suit against Nordic in state court alleging, among other things, breach of contract and negligence. The insurer provided Nordic with a defense, but Nordic hired independent counsel.
The insurer filed for declaratory relief in federal district court.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Ireland Said to Plan Home Loans Limits to Prevent Bubble
October 01, 2014 —
Joe Brennan – BloombergIreland’s central bank plans to impose limits for the first time on how much banks can lend home buyers as real estate values soar again in the home of western Europe’s worst property collapse, two people with knowledge of the matter said.
The regulator is preparing to publish a consultation paper on its proposals within weeks, said one of the people, who asked not to be named, as the matter is private. Banks and lobby groups will have a chance to comment on the plans, which center on introducing loan-to-value and loan-to-income restrictions. A spokesman for the central bank in Dublin declined to comment.
Irish homes prices are surging even as banks grapple with the aftermath of mortgage crisis that forced the government to bail out most of the nation’s lenders. A quarter of the country’s owner-occupier home loans are in arrears or had their terms eased. Loans granted during the boom for more than 85 percent of the property value were most likely to default in the wake of the crash, central bank economists said today.
Read the court decisionRead the full story...Reprinted courtesy of
Joe Brennan, BloombergMr. Brennan may be contacted at
jbrennan29@bloomberg.net
Subcontractors on Washington Public Projects can now get their Retainage Money Sooner
July 26, 2017 —
Brett M. Hill - Ahlers & Cressman PLLCSubcontractors on public projects in Washington State will no longer be required to wait until final acceptance of the project to get their retainage money. A new statute, which goes into effect on July 23, 2017 and applies only to Washington public projects, will allow subcontractors to get their retainage sooner.
Under prior law, a subcontractor could only get its retainage prior to final acceptance if the general contractor provided a retainage bond to the public owner to secure a release of the general contractor’s retainage and the subcontractor then provided a similar retainage bond to the general contractor in the amount of its own retainage. If the general contractor decided to not provide a retainage bond to the owner, the subcontractor would be forced to wait until final acceptance of the project before it could get paid its retainage.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers & Cressman PLLCMr. Hill may be contacted at
bhill@ac-lawyers.com
Attempt to Overrule Trial Court's Order to Produce Underwriting Manual Fails
April 25, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter being ordered by the trial court to produce its underwriting manual, the insurer's writ of certiorari to quash the order was denied by the Florida Court of Appeals. People's Trust Ins. Co. v. Foster, 2022 Fla. App. LEXIS 542 (Fla. Ct. App. Jan. 26, 2022).
The insured sued after his claim for damage caused by a water pipe in his home that leaked. In discovery, the insurer refused to produce its underwriting manual. Ruling on a motion to compel, the trial court ordered that the manual be produced. The insurer appealed.
On appeal, the insurer argued its underwriting manual was categorically prohibited in breach of contract cases until and unless bad faith litigation commenced. Although courts had quashed the premature discovery of insurers' business practices, claims files, underwriting files, underwriting manuals, and the like in breach of contract actions, there was no categorical legal rule prohibiting discovery of underwriting manuals in breach of contract cases, especially if they were relevant.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
An Interesting Look at Mechanic’s Lien Priority and Necessary Parties
May 13, 2019 —
Christopher G. Hill - Construction Law MusingsAs regular readers of Construction Law Musings are well aware, I like to discuss mechanic’s liens. Whether it is their picky nature, the way court’s treat them or the soon to take effect changes in the form, mechanic’s liens are a topic near and dear to my heart as a construction attorney.
This past month the Fairfax Circuit Court took on the intersection of mechanic’s lien priority under Virginia Code section 43-21 (the lien priority statute) and what constitute necessary parties that must be named in any enforcement suit. In Marines Plumbing, LLC v. Durbin, et al., the Court discussed an all too typical scenario. Marines Plumbing performed repair work on the defendants’ property and the defendants did not pay for the work. Marines Plumbing recorded a memorandum of lien and subsequently sued to enforce that lien. In filing its suit, Marines Plumbing failed to name the trustees and lender on a deed of trust securing the loan on the property. Needless to say, the Defendants moved to dismiss the action for failure to name necessary parties (lender and trustees).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
California Supreme Court Holds “Notice-Prejudice” Rule is “Fundamental Public Policy” of California, May Override Choice of Law Provisions in Policies
November 12, 2019 —
Anthony L. Miscioscia & Timothy A. Carroll - White and Williams LLPOn August 29, 2019, in Pitzer College v. Indian Harbor Insurance Company, 2019 Cal. LEXIS 6240, the California Supreme Court held that, in the insurance context, the common law “notice-prejudice” rule is a “fundamental public policy” of the State of California for purposes of choice of law analysis. Thus, even though the policy in Pitzer had a choice of law provision requiring application of New York law – which does not require an insurer to prove prejudice for late notice of claims under policies delivered outside of New York – that provision can be overridden by California’s public policy of requiring insurers to prove prejudice after late notice of a claim. The Supreme Court in Pitzer also held that the notice-prejudice rule “generally applies to consent provisions in the context of first party liability policy coverage,” but not to consent provisions in the third-party liability policy context.
The Pitzer case arose from a discovery of polluted soil at Pitzer College during a dormitory construction project. Facing pressure to finish the project by the start of the next school term, Pitzer officials took steps to remediate the polluted soil at a cost of $2 million. When Pitzer notified its insurer of the remediation, and made a claim for the attendant costs, the insurer “denied coverage based on Pitzer’s failure to give notice as soon as practicable and its failure to obtain [the insurer’s] consent before commencing the remediation process.” The Supreme Court observed that Pitzer did not inform its insurer of the remediation until “three months after it completed remediation and six months after it discovered the darkened soils.” In response to the denial of coverage, Pitzer sued the insurer in California state court, the insurer removed the action to federal court and the insurer moved for summary judgment “claiming that it had no obligation to indemnify Pitzer for remediation costs because Pitzer had violated the Policy’s notice and consent provisions.”
Reprinted courtesy of
Timothy Carroll, White and Williams and
Anthony Miscioscia, White and Williams
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Supreme Court Rules Matching of Materials Decided by Appraisers
March 28, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Connecticut Supreme Court determined that an appraisal panel could resolve whether the insurer must replace undamaged materials so that they match the damaged materials. Klass v. Liberty Mut. Ins. Co., 2022 Conn. LEXIS 2 (Conn. Jan. 11, 2022).
The insured reported damage to the roof of his home to Liberty Mutual. A representative from Liberty Mutual inspected and noticed a few shingles missing from the rear slope of the roof. The representative agreed that the damage was caused by wind damage, a covered loss under the policy. Liberty Mutual accepted coverage and issued an estimate to replace the rear slope of the roof. The insured's contractor inspected the roof and provided an estimate that contemplated replacement of the entire roof at nearly double the cost of Liberty Mutual's estimate.
The insured requested an appraisal. Liberty Mutual responded that the insured could not invoke the appraisal process in the absence of a "competing" estimate (i.e., one that addressed the claim for which coverage was accepted). Any dispute regarding the matching of the front and rear roof slope was a question of coverage, not an issue for appraisal.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com