Ready, Fire, Aim: The Importance of Targeting Your Delay Notices
November 08, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsProviding written notice of delay to subcontractors when a project is behind schedule is a regular part of good project documentation practices. A properly targeted delay notice is an important, project correspondence that is an appropriate response to a subcontractor’s specific delay or ongoing delays. However, when a project falls behind schedule and the project management team is in the fog of war, it could seem like a good idea to start firing off project delay notices to any and every subcontractor. While these delay notices may provide a short term burst of productivity, you could find that those same notices are aimed back at you in a future litigation.
This article identifies two potential unintended consequences of sending delay notices that a contractor should keep in its sights and then provides recommendations for properly calibrating future delay notices in light of these potential consequences.
Acceleration: You Might Get What You Ask For
A delay notice to a subcontractor could be interpreted as—or expressly state—direction to the subcontractor to accelerate its work. When a subcontractor is directed to accelerate its work, it may incur additional costs for premium, extended, or overtime labor, additional crews, increased supervision costs, increased overhead costs, and losses due to productivity impacts from the acceleration (e.g., stacking of trades and fatigue). A subcontractor may be entitled to recover these increased costs that are caused by a direction to accelerate.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com
Barratt Said to Suspend Staff as Contract Probe Continues
January 26, 2017 —
Jack Sidders - BloombergBarratt Developments Plc suspended at least three more employees within its London business as part of an ongoing probe into potential misconduct in the awarding of contracts, according to two people familiar with the decision.
The people asked not to be named because a police investigation is ongoing. The suspensions follow that of London regional managing director Alastair Baird, who was arrested in October. He was released on bail until April, along with a 47-year-old woman, according to a Metropolitan Police spokesman, who was unable to immediately respond to a request for comment.
Read the court decisionRead the full story...Reprinted courtesy of
Jack Sidders, BloombergMr. Sidders may be followed on Twitter @JackSidders
Maryland Finally set to Diagnose an Allocation Method for Progressive Injuries
February 18, 2020 —
William S. Bennett - Saxe Doernberger & Vita, P.C.Maryland’s highest court recently heard arguments regarding the proper method of allocation of the covered damages from a slowly progressing asbestos injury amongst insurance policies in place over a period of years. Rossello v. Zurich American Insurance Company, Case No. 2436 (Md. 2019). The court may also be forced to determine what the proper trigger of coverage is for latent bodily injury claims, although the plaintiff has not framed the issue in that manner.
In Rossello, the plaintiff, Patrick Rossello, worked for a period of years for the now-defunct Lloyd E. Mitchell, Inc. (“Mitchell”), a construction company operating until 1976. In 1974 he was exposed to and inhaled asbestos fibers. He was ultimately diagnosed in 2013 with malignant mesothelioma as a result of that exposure. Rossello obtained a judgment for approximately $2,700,000 against Mitchell and secured the right to pursue its insurance. As relevant to this dispute, Mitchell carried liability insurance policies, which provide coverage for asbestos related claims, from 1974 to 1977.
Rossello seeks to hold Zurich, as successor to Maryland Casualty Company, accountable for the full value of his award, based on the 1974 policy. Although this contention actually implicates two separate issues, plaintiff’s counsel passed over the initial trigger of coverage issue and focused instead on the issue of allocation of coverage.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
America’s Infrastructure Gets a D+
March 16, 2017 —
Garret Murai – California Construction Law BlogThe American Society of Civil Engineers (ASCE) has issued their 2017 Infrastructure Report Card, which assigns a letter grade to the nation’s infrastructure.
Our country’s grade in 2017? A disappointing D+.
Although, if you’re a glass half full kind of person (bless your soul) at least our grade didn’t fall since the last report card was issued in 2013, when our grade was a D+ as well.
In short, we suck. Although, apparently, we don’t suck evenly across the board.
ASCE has divided its cumulative GPA into grades for specific courses, if you will. Our transit systems received a grade of D-; our airports, dams, drinking water and waste water plants, inland waterways, levees and roads received a grade of D; our power plants, hazardous waste plants, public parks and schools received a grade of D+; our bridges, ports and solid waste plants a grade of C+, and our rail systems received a grade of B.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
DC District Court Follows Ninth Circuit’s Lead Dismissing NABA’s Border Wall Case
April 10, 2019 —
Anthony B. Cavender - Gravel2GavelOn February 14, the U.S. District Court for the District of Columbia dismissed the complaint of the National American Butterfly Association (NABA) alleging that the U.S. Government’s border wall preparation and law enforcement activities at NABA’s National Butterfly Center, located in South Texas along the Rio Grande River, violated federal environmental laws (National Environmental Policy Act (NEPA)) and the Endangered Species Act (ESA)) as well as NABA’s constitutional rights. The case is National American Butterfly Association v. Nielsen, et al.
On January 25, 2017, the President issued an Executive Order to the Secretary of the Department of Homeland Security (Secretary) to “take all appropriate steps to immediately plan, design, and construct a physical wall along the southern border” with Mexico. A few weeks later, the Secretary issued a memorandum to the U.S. Customs and Border Enforcement to implement the Executive Order. The land occupied by the NABA has been affected by these actions, as well as other actions taken by the Secretary pursuant to her authority under the Illegal Immigration Reform and Immigrant Responsibility Act (IIRIRA), located at 8 U.S.C. § 1103.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Protect Against Design Errors With Owners Protective Professional Indemnity Coverage
March 14, 2018 —
Joseph Nawa – New Day Underwriting Managers, LLCPrior to the devastation caused by Hurricanes Harvey, Irma and Maria, the AIA Consensus Construction Forecast had predicted “slower growth for the construction industry for the remainder of 2017 and through 2018.” But, given the hundreds of billions of dollars in damages caused by these horrific events, Mark Zandi, chief economist at Moody's Analytics, estimates a lift to the economy through the rebuilding of these areas. This, of course, is dependent on insurer funds and the amount of aid offered through government sources.
Nonetheless, the process will be costly, timely and exhaustive. Under such circumstances, speed is a necessity. In addition to being drawn into the earliest stages of the project development cycle, the services of construction professionals have merged so intensely that even their “consultative advice” have produced exposures in “collaborative” environments rife with liability.
A challenge for contractors in today’s design/build marketplace is securing professional liability insurance policies that will not only manage the risks associated with their own errors and omissions, but also the problems caused by designers and others contracted to work on the project. However, this too is not very easy. Such policies when purchased by contractors can be exceedingly cost prohibitive.
Read the court decisionRead the full story...Reprinted courtesy of
Joseph Nawa, Construction Executive, a Publication of Associated Builders and Contractors. All Rights ReservedMr. Nawa may be contacted at
joseph.nawa@newdayunderwriting.com
Not If, But When: Newly Enacted Virginia Legislation Bans “Pay-If-Paid” Clauses In Construction Contracts
August 22, 2022 —
Joseph A. Figueroa & Thomas E. Minnis - ConsensusDocsRecently passed legislation in Virginia is likely to dramatically change contractual relationships between prime contractors and subcontractors in the Commonwealth. Abrogating well-established common-law principles set forth by the Supreme Court of Virginia, on April 27, 2022, the Virginia General Assembly, after receiving input from Virginia Governor Glenn Youngkin, passed Senate Bill 550 banning “pay-if-paid” clauses in public and private construction contracts. Contractors performing work in Virginia should take note of the new law, which goes into effect next year and will apply to any contracts executed after January 1, 2023.
The History Of Pay-if-Paid Clauses In Virginia
Broadly speaking, “pay-if-paid” clauses are a commonly used tool by prime contractors on construction projects to shift the risk to subcontractors in the event that the owner does not pay the prime contractor for work. Such clauses usually include language creating an express condition precedent to the subcontractor’s right to be paid for work under a subcontract, stating that the prime contractor shall be under no obligation to pay the subcontractor for work unless and until the prime contractor first receives payment for that work by the project owner. The “pay-if-paid” clause also has a less extreme cousin, the “pay-when-paid” clause, which merely delays the time in which the prime contractor is obligated to pay the subcontractor to the time in which the prime contractor is paid by the owner. It does not, however, extinguish the prime contractor’s ultimate obligation to pay the subcontractor.
Reprinted courtesy of
Joseph A. Figueroa, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs) and
Thomas E. Minnis, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)
Mr. Figueroa may be contacted at jfigueroa@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Certain Private Projects Now Fall Under Prevailing Wage Laws. Is Yours One of Them?
November 21, 2022 —
Nancy Cox - Construction ExecutiveFor the last few years, New York State Labor Law has required that all contractors overseeing public development projects pay their workers the prevailing wage rate, which includes a regulated hourly rate for wage and benefits. Fast forward to 2022, the requirements of Section 224-A are extending to private projects costing more than $5 million where 30% or more of the financing for the construction costs was obtained from public sources like state or local funding.
There are a number of forms of financing that qualify as public funding, and its important for developers to understand exactly how these are defined under the new law. Public funding includes any indirect or direct payment from government authorities, savings from fees, tax credits or payments in lieu of taxes, loans from public entities and more.
In order to provide further clarity, the law also clearly defined certain project exemptions to the new rule. First, affordable housing projects will not be affected, along with historic rehabilitation projects or small renewable energy projects. Also, projects for established non-profit companies receive an exemption as long as the company reports gross annual revenues less than $5 million. Other exemptions include projects for schools under 60,000 square feet and those funded by the Urban Development Corporation’s Restore New York's Communities Initiative.
Reprinted courtesy of
Nancy Cox, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of