Diggin’ Ain’t Easy: Remember to Give Notice Before You Excavate in California
February 15, 2018 —
Matthew Peng – Construction Law Blog If you are reading this blog, my guess is that you know what excavation is and why it is important to the construction process. However, what you may not know is the complicated California law that governs this process. The statute for an excavation contractor to be familiar with is California Government Code section 4216,
et seq. However, like most things worth pursuing, that is easier said than done. Section 4216 contains several layers of prerequisites and requirements. This article will explore the notice requirement.
Section 4216.1 requires “every operator of a subsurface installation” to share costs of a regional notification center. This is necessary because Section 4216.2(b) requires “an excavator planning to conduct an excavation shall notify the appropriate regional notification center of the excavator’s intent to excavate” before beginning that excavation. The statute lists two regional notification centers: the Underground Service Alert—Northern California and the Under Ground Service Alert—Southern California.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Peng, Gordon & ReesMr. Peng may be contacted at
mpeng@grsm.com
Bar to Raise on Green Standard
November 07, 2012 —
CDJ STAFFNext June, members of the U.S. Green Building Council will be voting on changes to the LEED green building standard. “The bar is getting raised,” said Navad Malin of BuildingGreen, a consulting and publishing firm, in an article in USA Today. Under the proposed guidelines, builders would have to project energy and water use for five years as part of the certification process. However, if the occupants aren’t as green as the builders anticipated, the buildings will not lose their certification.
The new rules will include higher energy standards, award points for avoiding potentially hazardous materials, and even determine what kind of plumbing items can be used.
Read the court decisionRead the full story...Reprinted courtesy of
August Home Prices in 20 U.S. Cities Appreciate at Faster Pace
October 28, 2015 —
Victoria Stilwell – BloombergHome prices in 20 U.S. cities rose at a faster pace in the year ended August, a sign the industry continues to strengthen on improving demand.
The S&P/Case-Shiller index of property values climbed 5.1 percent from August 2014 after rising 4.9 percent in the year ended in July, the group said Tuesday in New York. The gain was the biggest in a year and matched the median forecast of economists surveyed by Bloomberg. Nationally, prices increased 4.7 percent after a 4.6 percent advance in the 12 months through July.
A tight supply has supported price appreciation, which may in turn entice more owners to put their properties on the market as the payoff grows. More homes that are affordable for first-time or young buyers will be needed to keep the housing recovery on track, providing a boost to consumer spending in the process.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, Bloomberg
Summarizing Changes to NEPA in the Fiscal Responsibility Act (P.L. 118-5)
September 05, 2023 —
Anthony B. Cavender & Marcus Manca - Gravel2Gavel Construction & Real Estate Law BlogThe National Environmental Policy Act (NEPA) was signed into law on January 1, 1970, and it has rarely been amended or revised since then. NEPA is basically a procedural statute which requires Federal permitting authorities, before a major federal project is approved, to carefully consider the significant environmental consequences of the proposed federal action. NEPA has been employed to conduct a probing review of wide variety of federal projects and actions, and the President’s Council on Environmental Quality (CEQ) has promulgated a comprehensive set of rules and guidance documents that must be followed or consulted. (See 40 CFR Section 1500 et seq.) The first set of NEPA rules was issued in 1978, and very little was done to bring the rules up to date until 2020. The first phase of this review has been completed, and a second and final phase will soon be underway. The NEPA review process includes the use of “categorical exclusions,” environmental assessments and environmental impact statements to measure the environmental impact of a proposed project. Over time, the rules and their implementation and judicial interpretation have become ever more complex, and an enormous body of NEPA case law has resulted.
The recent Congressional debt limit deliberations provided an opportunity to revise some of these procedures, and the Fiscal Responsibility Act, signed into law on June 3, 2023, included at Title III, a section devoted to “Permitting Reform.”
Reprinted courtesy of
Anthony B. Cavender, Pillsbury and
Marcus Manca, Pillsbury Read the court decisionRead the full story...Reprinted courtesy of
Mr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Thinking About a Daubert Motion to Challenge an Expert Opinion?
February 06, 2023 —
David Adelstein - Florida Construction Legal UpdatesWhen you receive an expert opinion, one of the first things you are considering is whether it is worth filing a Daubert motion / challenge. A Daubert motion is a generally a pretrial motion you are using to challenge the admissibility of the expert opinion. Keep in mind this deals with the admissibility, not the credibility, of the expert opinion. A Daubert motion is based on three prongs that must be answered: 1) is the witness qualified to render the expert opinion?; 2) is the expert’s opinion reliable?; and 3) is the expert’s opinion relevant?.
A Daubert motion is premised after Federal Rule of Evidence 702 that provides:
A witness who is qualified as an expert by knowledge, skill, experience, training, or education may testify in the form of an opinion or otherwise if:
- the expert’s scientific, technical, or other specialized knowledge will help the trier of fact to understand the evidence or to determine a fact in issue;
- the testimony is based on sufficient facts or data;
- the testimony is the product of reliable principles and methods; and
- the expert has reliably applied the principles and methods to the facts of the case.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Insurance Alert: Insurer Delay Extends Time to Repair or Replace Damaged Property
November 26, 2014 —
Valerie A. Moore & Christopher Kendrick – Haight Brown & Bonesteel LLPIn Stephens & Stephens XII v. Fireman's Fund Ins. (No. A135938, filed November 24, 2014), the plaintiffs obtained property insurance on a warehouse. Within a month, it was discovered to be stripped of all wiring and metal. Fireman's Fund paid for emergency repairs but nothing more, concerned that the damage had occurred outside the policy period.
The policy provided for valuation of either "replacement cost," meaning the expenditure required to replace the damaged property with "new property of comparable material and quality," or "actual cash value," defined as the actual, depreciated value of the damaged property. For replacement cost, Fireman’s Fund was not required to pay "until the lost or damaged property is actually repaired ... as soon as reasonably possible after the loss or damage," and only "[t]he amount [the insured] actually spend[s]...."
In the subsequent bad faith lawsuit, the jury awarded the full cost of repair, despite there being no repairs. The appeals court reversed, holding that there was no right to an immediate award for the costs of repairing the damage; however, the court nonetheless held that the insured was entitled to a "conditional judgment," awarding those costs if repairs were actually made.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Christopher Kendrick, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com; Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Environmental Justice Update: The Justice40 Initiative
April 29, 2024 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law BlogSoon after taking office, President Biden issued Executive Order 14008, entitled, “Tackling the Climate Crisis at Home and Abroad.” This is an unusually long and complex executive order and includes many provisions relating to environmental justice and the plight of “disadvantaged communities” that are overwhelmed by many environmental threats. Section 223 of the Order describes the President’s “Justice40 Initiative,” which is designed to ensure that 40% of Federal benefits flow to disadvantaged communities through an “all of government approach.” There is a recognition that some disadvantaged communities lack the personnel and resources to take advantage of this Initiative, so technical training funds will be made available. The Order establishes new offices throughout the Federal bureaucracy to handle and expedite environmental justice matters.
The Office of Management and Budget (OMB) and the Council on Environmental Quality (CEQ) play a large role in implementing the Initiative by issuing appropriate guidance and assisting the Federal agencies to locate, among the thousands of programs they supervise, suitable programs that will assist disadvantaged communities. At last count, 518 Federal programs administered by 19 distinct Federal agencies could be a good source for the resources needed by disadvantaged communities to cope with air and water pollution and solid waste issues. Direct grants will be made in many cases, and other programs require the community to apply for the funds promised by the Executive Order. In addition, the Order requires participating Federal agencies to assess the value and effectiveness of the benefits bestowed. OMB and the CEQ have issued guidance documents and conducted many meetings with key personnel and members of the disadvantaged communities.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Senator Ray Scott Introduced a Bill to Reduce Colorado’s Statute of Repose for Construction Defect Actions to Four Years
January 21, 2015 —
David M. McLain – Colorado Construction LitigationFor those of you reading this blog who are familiar with Colorado’s law as it pertains to construction defect actions, which I assume to be anyone reading this blog as it does not seem to get much random traffic, you are probably aware that the statute of repose applicable to construction defect actions in Colorado is generally thought of as being six plus two years. Specifically, C.R.S. § 13-80-104 states, in pertinent part:
(1)(a) Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com