Review your Additional Insured Endorsement
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFIn his blog, Construction Contractor Advisor, Craig Martin explained the importance of reviewing your additional insured endorsement. Martin pointed out that in Mississippi, the “Fifth Circuit Court of Appeals recently ruled in Woodward, LLC v. Acceptance Indemnity Insurance Company, that a general contractor, named as an additional insured, did not have coverage for claims that a subcontractor performed faulty work.” The problem “was the language in the additional insured endorsement, which provided coverage for ongoing operations, not completed operations.”
While Martin admitted that the case applies to Mississippi, he concluded that “the issue Midwestern readers should consider is the court’s conclusion that non-conformance with the plans, in essence a construction defect claim, arises from completed operations.”
Read the court decisionRead the full story...Reprinted courtesy of
Providing “Labor” Under the Miller Act
January 28, 2019 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion out of the Northern District of California discusses the “labor” required to support a Miller Act payment bond claim on a federal construction project. It is a good case that discusses the type of labor required to support a Miller Act payment bond claim.
In Prime Mechanical Service, Inc. v. Federal Solutions Group, Inc., 2018 WL 619930 (N.D.Cal. 2018), a prime contractor was awarded a contract to design and install a new HVAC system. The prime contractor subcontracted the work to a mechanical contractor. The mechanical contractor with its sub-designer prepared and submitted a new HVAC design to the prime contractor and provided 4-5 onsite services to determine the location and layout for the new HVAC equipment, perform field measurements, obtain security passes, and plan site access and crane locations. The mechanical contractor submitted an invoice to the prime contractor and the invoice remained unpaid for more than 90 days, which the prime contractor refused to pay. The mechanical contractor than filed a Miller Act payment bond lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
White and Williams Defeats Policyholder’s Attempt to Invalidate Asbestos Exclusions
January 28, 2014 —
White and Williams LLPWhite and Williams attorneys scored a significant victory for the insurance industry on January 15, 2014, when a federal jury of four men and four women rejected a policyholder’s novel efforts to invalidate asbestos exclusions contained in insurance policies issued between February 1, 1979 and August 1, 1985.
In General Refractories Co. v. First State Ins. Co., Civil Action No. 04-CV-3509 (E.D. Pa.), General Refractories Company contended that asbestos exclusions in insurance policies issued by various insurance companies in the late 1970s and 1980s had not been submitted to the Pennsylvania Department of Insurance for approval prior to use and, therefore, were unenforceable. Holding a failure to obtain approval, by itself, would not be sufficient to render the exclusions unenforceable, the Honorable Edmund Ludwig sent the matter to trial to determine whether the Pennsylvania Insurance Commissioner implemented a policy that was uniformly executed by the Insurance Department to disapprove all asbestos exclusions between February 1, 1979 and August 1, 1985, such that the exclusions violated a “dominant public policy.”
Reprinted courtesy of Gregory LoCasale, White and Williams LLP
and
Patricia Santelle , White and Williams LLP
Ms. Santelle may be contacted at santellep@whiteandwilliams.com and Mr. LoCasale may be contacted at locasaleg@whiteandwilliams.com.
Read the court decisionRead the full story...Reprinted courtesy of
Contractors Sued for Slip
June 28, 2013 —
CDJ STAFFA man on his way to a safety meeting slipped fell on a gangway. He’s saying that the roofing paper on the gangway was improperly secured and is now suing the contractor for negligence. Donald Methvien claims that his damages exceed $50,000.
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Butterflies, Salt Marshes and Methane All Around
November 16, 2020 —
Anthony B. Cavender - Gravel2GavelOur latest summary of some recent developments in the courts and the federal agencies includes a unique case involving salt marshes adjacent to San Francisco Bay.
THE FEDERAL COURTS
A Wolf Among the Butterflies
On October 13, 2020, the U.S. Court of Appeals for the District of Columbia Circuit decided the case of North American Butterfly Association v. Chad Wolf, Acting Secretary of the Department of Homeland Security. The National Butterfly Center is a 100-acre wildlife sanctuary located in Texas along the border between the United States and Mexico, and in 2017, the DHS exerted control over a segment of the sanctuary to construct facilities to impede unauthorized entry into the United States. It was alleged that the government failed to provide advance notice to the sanctuary before it entered the sanctuary to build its facilities. The Association filed a lawsuit to halt these actions for several reasons, including constitutional claims and two federal environmental laws (NEPA and the Endangered Species Act), but the lower court dismissed the lawsuit because of the provisions of the Illegal Immigration Reform and Immigrant Responsibility Act of 1996 (IIRIRA). That law forecloses the applicability of these laws if the Secretary of DHS issues appropriate declaration. On appeal, the DC Circuit held, in a 2 to 1 decision, that the lawsuit should not have been dismissed. The plaintiffs had standing to file this lawsuit, but the jurisdiction stripping provisions of the IIRIRA, when invoked, required that the statutory claims be dismissed as well as a constitutional Fourth Amendment search and seizure claim. However, the plaintiff’s Fifth Amendment claim that the government’s actions violated their right to procedural due process must be reviewed. The Center was given no notice of the government’s claims and no opportunity to be heard before these actions were taken. The dissenting judge argued that the court was being asked to review a non-final decision, which it should not do.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
The Requirement to Post Collateral Under General Agreement of Indemnity Is Real
May 16, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn prior postings, I have discussed the all-powerful General Agreement of Indemnity (click
here and
here). This is the document a bond-principal executes to obtain bonds (e.g., performance and payment bonds). Not only does the bond-principal execute this General Agreement of Indemnity, but typically, so do other indemnitors such as the company’s principals and their spouses, other related companies, etc. The objective is that the surety has financial comfort that if a claim is made against the bond, there are avenues where it will get reimbursed and indemnified for any cost it incurs, or payment it makes, relative to that claim against the bond. When a surety issues bonds, the objective is that all losses it incurs gets reimbursed because the bonds are NOT insurance policies.
One of the powerful tools the surety can exercise in the General Agreement of Indemnity is to demand the bond-principal and other indemnitors to post collateral in an amount the surety deems sufficient to cover any losses it may incur. This is a right in any General Agreement of Indemnity I have seen and is a right the surety can rightfully exercise.
A recent example is shown from the opinion in Philadelphia Indemnity Ins. Co. v. Quinco Electrical, Inc., 2022 WL 1230110 (M.D.Fla. 2022), which pertains to the surety’s motion for preliminary injunction.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
So You Want to Arbitrate? Better Make Sure Your Contract Covers All Bases
August 16, 2021 —
Stephanie Nolan Deviney - ConsensusDocsAs a General Contractor, you may prefer to arbitrate any contractual disputes rather than engage in protracted litigation. Many Courts favor arbitration clauses and will enforce them if there is a sufficient reason to do so. However, there are several issues that a General Contractor should consider when including an arbitration clause in its construction agreement with its client. When an arbitration clause is not properly crafted, questions can arise as to who must arbitrate? Who decides whether to arbitrate? Who selects the arbitrator? What will the subject matter of the arbitration be? A look at a recent case in Pennsylvania highlights the need for properly crafted arbitration clauses.
A Recent Case Highlights The Importance Of Arbitration Clauses
In TEC Construction, LLC v. Greg Rich and Lora Rich filed in the Court of Common Pleas, Allegheny County, Pennsylvania, TEC Construction, LLC (“TEC”) and Greg and Lora Rich (the “Riches”), entered into a Construction Agreement with an arbitration clause. Specifically, the parties to the Construction Agreement, TEC and the Riches, agreed to arbitrate any disputes with the American Arbitration Association. Five subcontractors completed the work under the Construction Agreement but none of the subcontractors agreed to arbitrate.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Nolan Deviney, Fox Rothschild LLP (ConsensusDocs)Ms. Deviney may be contacted at
sdeviney@foxrothschild.com
Illinois Favors Finding Construction Defects as an Occurrence
September 23, 2019 —
Ashley L. Cooper - SDV InsightsA recent Illinois Appellate Court’s decision in, Acuity Ins. Co. v. 950 West Huron Condominium Owners Association, 2019 IL App (1st) 180743 (2019), strengthens Illinois’ precedent favoring construction defects as an occurrence under a Commercial General Liability (“CGL”) insurance policy. Acuity also broadens an insurance carrier’s obligation to defend its insured against construction defect allegations.
In Acuity, the court determined whether claims for construction defect filed against a subcontractor, triggered a duty to defend under a CGL policy. To make its determination, the court focused on the subcontractor’s scope of work. The court notes that a subcontractor normally contracts for a discrete scope of work on a project. Unlike a general contractor, who has control over or contractual obligations for all aspects of the project, a subcontractor does not have those board responsibilities. The court explained that “[f]rom the eyes of the subcontractor, the ‘project’ is limited to the scope of its own work, and the precise nature of any damage that might occur to something outside of that scope is as unknown or unforeseeable as damage to something entirely outside of the construction project.”
Accordingly, the court in Acuity held that when a complaint alleges that a subcontractor’s negligence caused damage to a part of the construction project outside of the subcontractor’s scope of work, the allegations are enough to trigger the insurer’s duty to defend the subcontractor under a CGL policy. The court’s decision in Acuity relied on a similar Illinois Appellate Court decision, Milwaukee Mut. Ins. Co. v. J.P. Larsen, Inc., 956 N.E.2d 524 (Ill. App. 2011). In Larsen, the court reached a similar conclusion where a third-party complaint by a general contractor against a subcontractor alleged that the subcontractor’s improper window caulking caused water intrusion and property damage to other parts of the building. The court in Larsen held that because the complaint alleged not only construction defects, but also damage to other property outside the subcontractor’s scope of work, the insurer had a duty to defend the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Ashley L. Cooper, Saxe Doernberger & Vita, P.C.Ms. Cooper may be contacted at