Ahead of the Storm: Preparing for Dorian
September 16, 2019 —
Adam P. Handfinger, Stephen H. Reisman & Gary M. Stein - Peckar & Abramson, P.C.While Hurricane Dorian churns in the Atlantic with its sights currently set on the east coast of Florida, storm preparations should be well underway. As you are busy organizing efforts to secure your job sites, we at Peckar & Abramson offer some quick reminders that may prove helpful:
- Review your contracts, particularly the force majeure provisions, and be sure to comply with applicable notice requirements
- Even if not expressly required at this time, consider providing written notice to project owners that their projects are being prepared for a potential hurricane or tropical storm and that the productivity and progress of the work will be affected, with the actual time and cost impact to be determined after the event.
- Consult your hurricane plan (which is often a contract exhibit) and confirm compliance with all specified safety, security and protection measures.
- Provide written notice to your subcontractors and suppliers of the actions they are required to take to secure and protect their portions of the work and the timetable for completion of their storm preparations.
Reprinted courtesy of Peckar & Abramson, PC attorneys
Adam P. Handfinger,
Stephen H. Reisman and
Gary M. Stein
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Mr. Reisman may be contacted at sreisman@pecklaw.com
Mr. Stein may be contacted at gstein@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
4 Breakthrough Panama Canal Engineering Innovations
October 11, 2017 —
Hobbes S. Sujith - Construction InformerThrough the rainforest of Central America stretches one of the seven wonders of the modern world. It’s the mother of all shortcuts – the Panama Canal. Over 300 million tons of cargo pass through its gates every year. Stretching through the heart of the Americans, this canal has changed the face of global trade. Ships traveling between the Atlantic and Pacific used to sail thousands of kilometers around Cape Horn. So in 1879 engineers planned to cut a channel through the Isthmus of Panama. And that, was going to become the history of Panama Canal engineering.
To understand how the Panama Canal can carry such a huge amount of cargo, we need to travel back in time to 17th century France. There, engineers building the Briare Canal (Canal de Briare) faced an big problem. How to make water flow up a hill?
Read the court decisionRead the full story...Reprinted courtesy of
Hobbes S. Sujith, Construction Informer
Don’t Ignore a Notice of Contest of Lien
April 29, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case, Jon M. Hall Company, LLC v. Canoe Creek Investments, LLC, 49 Fla.L.Weekly D812a (Fla. 2d DCA 2024), demonstrates four important things when it comes to liens:
- An owner can shorten the time period to foreclose on the lien, whether against the real property or a lien transfer bond, to 60 days by recording a notice of contest of lien;
- An owner can transfer a lien to a lien transfer bond during litigation;
- An owner can record a notice of contest of lien to force the lienor to amend its lawsuit to sue the lien transfer bond surety within 60 days; and
- A contractors’ failure to amend its lawsuit to sue the lien transfer bond within 60 days will extinguish its rights to pursue a claim against the lien transfer bond, and will otherwise extinguish the lien, fairly or unfairly.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Fannie Mae, Freddie Mac Shares Fall on Wind-Down Measure
March 12, 2014 —
Clea Benson and Cheyenne Hopkins – BloombergCommon shares of Fannie Mae and Freddie Mac experienced their biggest intraday drop in 10 months after leaders of the Senate Banking Committee announced plans to eliminate the companies in a new bill.
Fannie Mae shares tumbled as much as 44 percent, paring the losses to 31 percent to close in New York at $4.03, after Edwin Groshans, a managing director at Washington-based equity research firm Height Analytics LLC, described the proposal as holder-negative. Freddie Mac fell 27 percent to close at $4.04. Preferred shares also dropped, some by as much as 12 percent.
The bipartisan measure, drafted with input from President Barack Obama’s administration, would replace the U.S.-owned mortgage financiers with government bond insurance that would kick in only after private capital suffered losses of at least 10 percent, Senate Banking Committee Chairman Tim Johnson and Senator Mike Crapo said in a statement today. The bill would require most borrowers to make down payments of at least 5 percent.
Ms. Benson may be contacted at cbenson20@bloomberg.net; Ms. Hopkins may be contacted at chopkins19@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Clea Benson and Cheyenne Hopkins, Bloomberg
Contrasting Expert Opinions Result in Denial of Cross Motions for Summary Judgment
February 27, 2023 —
Tred R. Eyerly - Insurance Law HawaiiGiven the opposing experts' contradictory reports, the court denied both the insured and insurer's motions for summary judgment regarding coverage for a pipe leak. Pronti v. Hanover Ins. Co., 2022 U.S. Dist. LEXIS 222306 (W.D. N. Y. Dec. 9, 2022).
The insured had a swimming poll and spa, which functioned using a subsurface plumbing system, covered with concrete decking. A subsurface pipe began to leak, preventing the pool from properly functioning. The insureds gave notice under their homeowners' policy and contended that significant portions of the pool, spa, concrete decking and other landscaping had to be torn out to do repairs. The insurer retained an expert, Sarah G. Byer, a structural engineer, to investigate. The parties agreed that the pipe had a leak, but disputed if the location of the leak was specifically identified.
The parties also disputed the cause of the leak. Byer found that the most likely cause was deterioration incurred over the pipe's lifetime based on the age of the plumbing system and Byer's personal observation of the pipe. Byer further stated that the physical qualities of flexible PVC piping made it susceptible to damage from chlorine and water over time.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Rhode Island Examines a Property Owner’s Intended Beneficiary Status and the Economic Loss Doctrine in the Context of a Construction Contract
March 18, 2019 —
Shannon M. Warren - The Subrogation StrategistIn Hexagon Holdings Inc. v. Carlisle Syntec, Inc. No. 2017-175-Appeal, 2019 R.I. Lexis 14 (January 17, 2019), the Supreme Court of Rhode Island, discussing claims associated with allegedly defective construction, addressed issues involving intended beneficiaries to contracts and the application of the economic loss doctrine. The court held that, based on the evidence presented, the building owner, Hexagon Holdings, Inc. (Hexagon) was not an intended third-party beneficiary of the subcontract between the general contractor (A/Z Corporation) and the subcontractor, defendant McKenna Roofing and Construction, Inc. (McKenna). In addition, the court held that, in the context of this commercial construction contract, the economic loss doctrine applied and barred Hexagon’s negligence claims against McKenna.
Approximately nine years after Hexagon entered into a contract with A/Z Corporation for the construction of a building, Hexagon filed suit against A/Z Corporation’s roofing installation subcontractor, McKenna, and the manufacturer of the roofing system. Hexagon alleged that the roof began to leak shortly after McKenna installed it. Notably, Hexagon did not sue A/Z Corporation.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and WilliamsMs. Warren may be contacted at
warrens@whiteandwilliams.com
OSHA’s COVID-19 Emergency Temporary Standard Is in Flux
December 06, 2021 —
Megan E. Baroni & Jonathan H. Schaefer - Construction ExecutiveOn Friday, Nov. 5, 2021, Occupational Safety and Health Administration’s COVID-19 Vaccination and Testing Emergency Temporary Standard was issued, with most requirements set to go into effect on Dec. 5. The ETS applies to employers with a total of 100 or more employees company-wide. Employers covered by the ETS would be required to develop, implement and enforce a mandatory vaccination policy, subject to limited exemptions, or allow unvaccinated employees to test regularly and be subject to a mask policy, among other associated recordkeeping, reporting and training requirements.
Almost immediately, the ETS was hit with a number of legal challenges in various courts across the country. On November 6, just a day after the ETS was issued, the U.S. Circuit Court of Appeals for the Fifth Circuit issued an order staying the implementation of the ETS until further notice. The Court’s order was not a final ruling on the validity of the ETS but has halted implementation of the ETS, at least for the time being. Other legal challenges are already in process, further complicating the issue of if and when the ETS will become effective.
As of November 2021, the ETS is on hold, at least temporarily. That could change any day and the ETS could be back in effect, in whole or in part, or permanently halted. The legal challenges to the ETS are unlikely to end, or diminish, until the Supreme Court has weighed in, making for a few uncertain months ahead.
Reprinted courtesy of
Megan E. Baroni and Jonathan H. Schaefer, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Baroni may be contacted at mbaroni@rc.com
Mr. Schaefer may be contacted at jschaefer@rc.com
Read the court decisionRead the full story...Reprinted courtesy of
EEOC Sues Whiting-Turner Over Black Worker Treatment at Tennessee Google Project
October 18, 2021 —
James Leggate - Engineering News-RecordThe Whiting-Turner Contracting Co., which ranks as one of the industry’s largest contractors, has been accused in a federal civil rights lawsuit of creating a racially hostile work environment at a Tennessee project site and of retaliating against employees who complained.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at https://www.enr.com/leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of