Performance Bond Surety Takeover – Using Terminated Contractor To Complete The Work
January 06, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen a contractor is defaulted under a performance bond, can its surety hire the same defaulted contractor to complete the work? Stated differently, can the performance bond surety engage its defaulted bond-principal in taking over and completing the same work the contractor was defaulted under? The answer is “yes” if you are dealing with a standard form AIA A312 performance bond (and other bond forms that contain analogous language), as demonstrated by the recent decision in Seawatch at Marathon Condominium Association, Inc. v. The Guarantee Company of North America, 2019 WL 4850194 (Fla. 3d DCA 2019).
In this case, a condominium association hired a contractor in a multi-million dollar contract to renovate condominium buildings. The contractor provided the association, as the obligee, a performance bond written on an AIA A312 performance bond form. During construction, the association declared the contractor in default and terminated the contractor. In doing so, the association demanded that the performance bond surety make an election under paragraph 4 of the AIA A312 bond form that gave the surety the following options:
4.1 Arrange for the CONTRACTOR, with consent of the OWNER, to perform and complete the Contract; or
4.2 Undertake to perform and complete the Contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the OWNER for a contract for performance and completion of the Contract, arrange for a contract to be prepared for execution by the OWNER and the contractor selected with the OWNER’S concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the Bonds Issued on the Contract, and pay to the OWNER the amount of damages as described in paragraph 6 in excess of the Balance of the Contract Price incurred by the OWNER resulting from the CONTRACTOR Default; or
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Looming Housing Crisis and Limited Government Relief—An Examination of the CDC Eviction Moratorium Two Months In
December 14, 2020 —
Zachary Kessler - Gravel2GavelMonths after the Centers for Disease Control and Prevention (CDC) issued a nationwide eviction moratorium using its emergency pandemic powers under the Public Health Service Act, the efficacy of this unprecedented measure remains unclear. While the Order ostensibly protects tenants facing homelessness or housing insecurity due to the financial impacts of the COVID-19 pandemic through the end of 2020, legal challenges have been initiated in Ohio and Georgia, with additional lawsuits appearing likely. Further, even barring legal challenges, courts have not handled these cases in a uniform manner. With lawmakers unable to reach any stimulus or COVID-19 relief agreement before the election, the CDC Order appears likely to remain the only federal eviction moratorium through its expiration on December 31, 2020.
Since the Order’s enactment, the CDC has since released new guidance, answering some of the open questions not covered by the initial Order. This guidance, while non-binding, is largely more favorable to landlords and property management companies than the initial text of the Order, as it provides that landlords are not required to make tenants aware of the Order’s protections and may challenge the truthfulness of the tenants’ declarations in any state or municipal court. The guidance also clarified the potential criminal penalties for violating the Order and the criminal penalties for perjury for bad faith submissions of the requisite declaration by tenants.
Read the court decisionRead the full story...Reprinted courtesy of
Zachary Kessler, PillsburyMr. Kessler may be contacted at
zachary.kessler@pillsburylaw.com
Five-Year Peak for Available Construction Jobs
December 11, 2013 —
CDJ STAFFThere are more job openings in construction now than there have been since 2008. The October jobs report from the Bureau of Labor Statistics reported 124,000 job openings in construction. With the demand for workers, some builders have experienced labor shortages, according to the National Association of Home Builders. The NAHB expects the trend to continue into 2014, “if firms can find workers with the right skills.”
Read the court decisionRead the full story...Reprinted courtesy of
District Court Awards Summary Judgment to Insurance Firm in Framing Case
August 04, 2011 —
CDJ STAFFIn the case of Continental Western Insurance Company v. Shay Construction Inc., Judge Walker Miller has granted a summary judgment against Shay Construction and their co-defendant, Milender White Construction Company.
Shay was the framing subcontractor for Milender White on what the court described as “a major construction project in Grand County, Colorado.” Two of Shay’s subcontractors, Wood Source Inc. and Chase Lumber Company furnished materials, labor, and equipment to Shay. They subsequently sued for nonpayment and sought to enforce mechanic’s liens, naming both Shay and Milender as defendants. Milender White alleged that Shay had “breached its obligation under its subcontracts with Milender White.”
Shay’s insurance provider, Continental Western, stated that its coverage did not include “the dispute between Shay, its subcontractors, particularly the cross claims asserted by Milender White.” Shay then sued Continental Western, alleging breach of contract and statutory bad faith.
The court, however, has found with Continental Western and has granted them a summary judgment. They found “no genuine issue as to any material fact.” The judge did not side with Continental Western on their interpretation of the phrase “those sums that the insured becomes legally obligated to pay as damages.” The court found that the Colorado courts have not limited this to tort actions only. However, as Milender’s cross claim included claims of faulty workmanship on the part of Shay, Judge Miller found for Continental.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Court Grants Motion to Dismiss Negligence Claim Against Flood Insurer
December 22, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer successfully moved to dismiss the insured's negligence claim and demand for jury trial, leaving only the insured's breach of insurance contract claim under the National Flood Insurance Program (NFIP). La Mirage Homeowners Association Inc. v. Wright National Flood Ins. Co., 2019 U.S. Dist. LEXIS 147667 (S.D. Tex. Aug 29, 2019).
Hurricane Harvey damaged three of insured homeowner's association condominium's buildings. Wright National Flood Insurance Company was the insurer pursuant to the NFIP when the hurricane damaged the insured's property. The insured alleged that Wright breached the policy by underpaying on the flood loss claims and by not initiating the appraisal the insured demanded. The insured sought recovery for negligence, consequential damage, statutory penalties, attorney's fees and pre-and-post judgment interest.
Wright moved to dismiss the extra-contractual claims and to strike the jury demand.
The NFIP's regulations allowed homeowners to purchase policies either directly from FEMA or from private insurers that functioned as Write Your Own (WYO) providers and fiscal agents of the United States. The Fifth Circuit had previously held that state law tort claims arising from claims handling by a WYO were preempted under federal law. The court, therefore, was faced with the issue of whether the insured's claims of negligence, attorney's fees, statutory penalties, and interest were policy-handling claims which were preempted by federal law.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
California’s Wildfire Dilemma: Put Houses or Forests First?
November 29, 2021 —
Jim Hinch - BloombergAs record-breaking fires blacken millions of acres in California and elsewhere in the West this year, politicians are mostly sticking to a standard script in response. President Joe Biden’s proposed budget this year includes a $500 million boost to what the White House calls “forest management” and other efforts to reduce wildfire risk. In July, California lawmakers approved $1.5 billion in similar prevention spending.
The funds are in addition to the $2 billion the federal government spends each year fighting fires — a figure twice what it was 10 years ago and roughly five times more than in the 1980s and 1990s. A study last year found that in 2018, wildfires in California caused $148.5 billion in economic damage, including $46 billion outside the state.
Roughly one in three American houses is now in what forest scientists call the wildland-urban interface, where growing cities, remote workers, second-home buyers and commuters priced out of other housing markets are often pushing into fire-prone regions. A 2017 study found that 900,000 homes in the Western U.S. worth a combined $237 billion were “at high risk for fire damage.”
Read the court decisionRead the full story...Reprinted courtesy of
Jim Hinch, Bloomberg
Ready, Fire, Aim: The Importance of Targeting Your Delay Notices
November 08, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsProviding written notice of delay to subcontractors when a project is behind schedule is a regular part of good project documentation practices. A properly targeted delay notice is an important, project correspondence that is an appropriate response to a subcontractor’s specific delay or ongoing delays. However, when a project falls behind schedule and the project management team is in the fog of war, it could seem like a good idea to start firing off project delay notices to any and every subcontractor. While these delay notices may provide a short term burst of productivity, you could find that those same notices are aimed back at you in a future litigation.
This article identifies two potential unintended consequences of sending delay notices that a contractor should keep in its sights and then provides recommendations for properly calibrating future delay notices in light of these potential consequences.
Acceleration: You Might Get What You Ask For
A delay notice to a subcontractor could be interpreted as—or expressly state—direction to the subcontractor to accelerate its work. When a subcontractor is directed to accelerate its work, it may incur additional costs for premium, extended, or overtime labor, additional crews, increased supervision costs, increased overhead costs, and losses due to productivity impacts from the acceleration (e.g., stacking of trades and fatigue). A subcontractor may be entitled to recover these increased costs that are caused by a direction to accelerate.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com
Department of Transportation Revises Its Rules Affecting Environmental Review of Transportation Projects
December 04, 2018 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law BlogOn October 29, the U.S. Department of Transportation (DOT) published a final rule in the Federal Register which amends and revises the environmental National Environmental Policy Act (NEPA) procedures rules employed by the Federal Highway Administration (FHWA), the Federal Railroad Administration (FRA), and the Federal Transit Administration (FTA). There is a renewed interest in transportation infrastructure projects, and recent legislation is intended to accelerate required environmental reviews.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com