What is the Effect of an Untimely Challenge to the Timeliness of a Trustee’s Sale?
April 13, 2017 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogEver wonder what happens if a person challenges the timeliness of a trustee’s sale after the sale already occurred? Waiver of the argument of course! And, in the case of Wells Fargo Bank, N.A. v. Waltner, the affirmance of an eviction judgment.
In the Waltner case, Wells Fargo Bank, N.A., as Trustee for WaMu Mortgage Pass-Through Certificates, Series 2005-PR4 Trust (the “Bank”), purchased a residential property at a trustee’s sale in September 2015. The Bank gave the occupant of the house, Sarah Waltner (“Waltner”), notice to vacate the property, but she did not do so. Accordingly, the Bank filed a summary action to evict Waltner, which the trial court ultimately granted.
After the trial court granted the Bank relief, Waltner filed a motion to dismiss and a motion to vacate the eviction judgment arguing, among other things, that the judgment was void because the Bank conducted the trustee’s sale after the statute of limitations expired. Both motions were denied, and Waltner appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Subcontract Should Flow Down Delay Caused by Subcontractors
December 21, 2020 —
David Adelstein - Florida Construction Legal UpdatesA general contractor’s subcontract with its subcontractor should include a provision that entitles it to flow down liquidated damages assessed by the owner stemming from delays caused by the subcontractor. Such a provision does not mean the general contractor does not have to prove delays caused by the subcontractor or can arbitrarily allocate the amount or days it claims the subcontractor is liable. The general contractor still will need to reasonably establish the delays the subcontractor caused the critical path of the schedule, i.e., delayed the job. In addition to the right to flow down liquidated damages, the subcontract should also entitle the general contractor to recover its actual extended general conditions caused by the subcontractor’s delays (regardless of whether the owner assesses liquidated damages). The objective is that if the subcontractor delays the job, the subcontractor is liable for liquidated damages the general contractor is liable to the owner for in addition to the general contractor’s own delay damages. This is an important subcontractual provision so that the risk of delay caused by subcontractors is clearly flowed down to them in the subcontract.
In a 1987 case, Hall Construction Co., Inc. v. Beynon, 507 So.2d 1225 (Fla. 5th DCA 1987), the subcontract at-issue contained language that stated, “The parties hereto agree that a supplier who delays performance beyond the time agreed upon in this Purchase Order shall have caused [general contractor] liquidated damages in the amount required of [general contractor] by their contract per day for each day such delay continues which sum the supplier hereby agrees to pay.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Social Distancing and the Impact on Service of Process Amid the COVID-19 Pandemic
April 13, 2020 —
Robert Devine, James Burger & Susan Zingone - White and WilliamsService of process usually requires person-to-person contact and is an essential part of civil procedure. It notifies the defendant of the legal proceedings against him/her and establishes jurisdiction. “Process” refers to the documents that must be served on a defendant. If service of process is not performed pursuant to the governing rules of civil procedure, a lawsuit cannot proceed.
Service of Process in NJ and PA
Personal service is required to be the first attempted means of service in New Jersey. If personal service is not successful, then service may be made by mailing a copy of the process via registered or certified mail with return receipt requested to the defendant’s usual place of abode or business/place of employment, or to an authorized agent. The party attempting to serve the defendant by mail can choose to mail the process by regular mail as well, and if the defendant refuses to accept or claim the registered or certified copy, and the regular mail copy is not returned, then service is considered effectuated.
Pennsylvania allows for a defendant to be served via personal service by handing a copy to the defendant or by delivering a copy to an adult family household member at the defendant’s residence. Pennsylvania also permits service of process by mail. Process can be served by mail requiring a signature of the defendant. If the mail is unclaimed, alternative service must be attempted.
Reprinted courtesy of White and Williams attorneys
Robert Devine,
James Burger and
Susan Zingone
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Burger may be contacted at burgerj@whiteandwilliams.com
Ms. Zingone may be contacted at zingones@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Kiewit Selected for Rebuild of Collapsed Baltimore Bridge
September 02, 2024 —
Jim Parsons - Engineering News-RecordKiewit Infrastructure Co. has been tapped to rebuild Baltimore’s I-695/Francis Scott Key Bridge under a progressive design-build procurement announced Aug. 29 by the Maryland Transportation Authority (MDTA). Work on the expected four-year reconstruction effort is scheduled to begin next year.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
No Retrofit without Repurposing in Los Angeles
October 21, 2013 —
CDJ STAFFThe Los Angeles Times has continued its series on the seismic safety of buildings in downtown Los Angeles. According to the article, Los Angeles only requires seismic retrofits of buildings if their purpose is being changed. One investor, Izak Shomof, bought a residential hotel and kept it as one to avoid retrofitting the building. He converted an office building to upscale residences and so the building was strengthened.
His son, Eric Shomof, keeps an office in the unreinforced building. He said if more retrofitting were required, “you’d see a lot more vacant buildings down here,” describing the process as “not cheap.”
Depending on whether or when a building has changed its use, the concrete buildings of downtown Los Angeles may or may not be protected against failure in an earthquake.
Read the court decisionRead the full story...Reprinted courtesy of
National Lobbying Firm Opens Colorado Office, Strengthening Construction Defect Efforts
January 05, 2017 —
Beverley BevenFlorez-CDJ STAFFMichael Best Strategies, a national law and lobbying firm, has recently opened an office in Colorado. According to the Denver Business Journal, the firm “has recruited several big-name associates — a move that could give business leaders even more clout with the Legislature on issues such as construction-defects reform.”
One of the firm’s recruits, Jeff Thormodsgaard, the lead lobbyist in the recent movement to make it harder to sue condominium builders, told the Denver Business Journal, “The only change [in the construction-defects reform effort] is that we’re going to be adding more feet and more boots on the ground and more gravitas.”
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Supreme Court Limits the Powers of the Nation’s Bankruptcy Courts
June 11, 2014 —
Earl Forte – White and Williams LLPOn June 9, 2014, the Supreme Court of the United States issued its much-awaited decision in Executive Benefits Insurance Agency v. Arkison, Chapter 7 Trustee of Estate of Bellingham Insurance Agency, Inc., Case No. 12-1200, in which the court confirmed that the power of the nation’s bankruptcy courts to hear and decide cases involving state-created private rights in which the bankruptcy proof of claim process has not been directly invoked, is severely limited by Article III of the Constitution of the United States.
The decision in Executive Benefits, while providing some clarity to practitioners and the public following the Court’s June 2011 decision in Stern v. Marshall, 131 S. Ct. 2594 (2011), nevertheless will make a substantial portion of bankruptcy litigation matters more cumbersome and potentially more expensive to guide through the bankruptcy system. Clients and practitioners are best advised to hire knowledgeable counsel to help navigate the more complex procedural waters created by this decision.
Although the Court in Executive Benefits did resolve a pending procedural question that had dogged practitioners since Stern was decided in 2011, the Court’s decision in Executive Benefits now makes it abundantly clear that many disputes that were previously heard and decided in the nation’s bankruptcy courts can no longer be decided there and must be submitted to the district courts for full de novo review and entry of a final judgment or order. It is difficult to see how this decision will not make bankruptcy litigation more cumbersome and expensive by adding an additional layer of judicial involvement to many matters, notably to fraudulent transfer and other avoidance “claw back” actions that historically have been decided in the bankruptcy courts and used famously in Madoff and other cases as an efficient device for creating value for creditors.
Read the court decisionRead the full story...Reprinted courtesy of
Earl Forte, White and Williams LLPMr. Forte may be contacted at
fortee@whiteandwilliams.com
Ohio Court of Appeals Affirms Judgment in Landis v. Fannin Builders
April 20, 2011 —
Beverley BevenFlorez CDJ STAFFThe Ohio Court of Appeals affirmed the judgment in Landis v. William Fannin Builders. Landis contracted Fannin Builders to build their home. The case involved staining problems on the T1-11 siding chosen by the plaintiffs.
After a year and a half of discussion on how to resolve the problem of uneven staining on the siding, Landis filed suit “against Fannin Builders, alleging claims for breach of contract, breach of the express limited warranty, and violation of the Ohio Consumer Sales Practices Act (“OCSPA”). Fannin Builders, in turn, filed a third-party complaint against 84 Lumber, alleging claims for breach of contract and indemnification. With the trial court’s leave, Fannin Builders also later amended its answer to add a counterclaim against appellees for breach of contract and unjust enrichment. In the counterclaim, Fannin Builders alleged that appellees still owed it $3,908.98 for the construction of appellees’ home.”
“In its decision, the trial court found in appellees’ favor on their breach of contract claim and against appellees on their claims for breach of the express limited warranty and violation of the OCSPA. Additionally, the trial court found in Fannin Builders’ favor on its counterclaim for breach of contract and against Fannin Builders on its third-party claims for breach of contract and indemnity. The trial court determined that appellees’ damages amounted to $66,906.24, and after setting off the $3,908.98 that appellees owed Fannin Builders under the construction contract, the trial court awarded appellees $62,997.26. The trial court reduced its decision to judgment on May 18, 2010.”
Fannin Builders appealed this judgment and assigned the following errors:
[1.] The Trial Court Erred as a Matter of Law by Concluding that Appellant Breached its Contract with Appellees when it provided a Semi-Transparent Oil-Based Stain that Simply did not Meet their Approval.
[a.] The Contract does not Contain a Satisfaction Clause.
[b.] Even if the Court Implies a Satisfaction Clause, the Court Should Apply an Objective Standard.
[2.] The Trial Court Erred as a Matter of Law by Failing to Consider Appellant’s Right to Cure.
[3.] The Trial Court committed Reversible Error by not Assessing Damages Using “Diminished Value Standard,” and by Creating a Remedy that Constitutes Economic Waste.
[4.] The Trial Court Erred as a Matter of Law by Concluding that Appellant is Barred from Seeking Indemnification When 84 [Lumber] Never Fulfilled its Obligations Pursuant to the Settlement Agreement Entered on August 2, 2005.
In response to the first assigned error, the Court of Appeals stated: “Because the failure to provide siding of a uniform color, not appellees’ displeasure, breached the contract, we reject Fannin Builders’ contention that the trial court implied a satisfaction clause into the contract and found a breach of that clause. Accordingly, we overrule Fannin Builders’ first assignment of error.”
The Court of Appeals overruled the second assignment of error and provided the following reasoning: “Although Fannin Builders depends upon a term of the limited warranty for its right to cure, the trial court concluded that no breach of the limited warranty occurred. Fannin Builders breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIA’s Quality Standards. Consequently, the limited warranty does not apply to this case, and thus, it does not prevent appellees’ recovery of damages.”
The Appeals Court found “the trial court’s award of damages” was “both reasonable and supported by competent, credible evidence,” and therefore concluded “that the trial court did not err in setting appellees’ damages at $62,997.26.” The Fannin Builders third assignment of error was overruled.
The fourth and final assignment of error was also overruled by the Court of Appeals. “While Fannin Builders correctly asserts that 84 Lumber never installed the replacement siding, it ignores the fact that it ordered 84 Lumber to remove the replacement siding from appellees’ property. Thus, Fannin Builders precluded 84 Lumber from completely performing under the August 2, 2005 letter agreement. […] Consequently, Fannin Builders cannot now claim that the letter agreement is unenforceable or that it is entitled to indemnification from 84 Lumber. Because Fannin Builders assumed all liability for the defective siding in the letter agreement, it is responsible for appellees’ damages.”
James A. Zitesman, Columbus, Ohio Business Attorney, compared the case to Jones v. Centex (Ohio App. 2010), which had a different verdict:
“The common thread is the implied warranty of good workmanship. In the Jones case, the Court found that the buyers had in fact waived all implied warranties, including the implied warranty of good workmanship. In the contract between Jones and Centex, the builder stated that it “…would not sell the property to Purchasers without this waiver.” Probably should have been a sign to the buyers.
In the Landis case, the Court stated, “Contracts for the future construction of a residence include a duty, implied by law, that the builder must perform its work in a workmanlike manner.” The Court gave significant weight to the concept of the implied warranty of good workmanship. The builder relied upon the BIA Warranty which limits builders’ liability and exposure to legal issues. The trial court concluded there was no breach of the limited warranty, rather the builder “breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIAs Quality Standards.”
The Supreme Court of Ohio has accepted the Jones v. Centex Homes case for review.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of