Statutory Time Limits for Construction Defects in Massachusetts
November 27, 2013 —
CDJ STAFFConstruction defect claims are governed by a section of the Massachusetts laws and allow for three years after the work was completed, unless the defect is “inherently unknowable,” according to a post by John Shaffer on the web site of his firm, Marcus, Errico, Emmer & Brooks, a New England law firm that specializes in condominium law. Those “inherently unknowable” defects fall into the six-year statute of repose.
If, for example, a roof doesn’t show “significant water leakage” until after the end of the statutory period, “the association is out of luck and the responsible parties are off the hook,” writes Mr. Shaffer. “Even if the association could prove conclusively that the roof was improperly constructed and caused significant damage, the association’s claim will be barred.”
One problem condominium associations can face is that defects in the earliest phases of building can sometimes become apparent while the developer still controls the board. “While a developer in control of a board has the same fiduciary obligation as owner-elected trustees to protect the association’s interests, it is probably safe to assume that few developers will be inclined to sue themselves.” Here, Mr. Shaffer notes that owners can join together and either “hasten the transition to owner control of the association” or “convince them to correct the identified deficiencies.”
Mr. Shaffer notes that some questions concerning the statute of repose haven’t been answered by the Massachusetts courts. He does assure readers that “developers will no doubt argue that the statute of limitations has expired on defects because the association discovered or ‘should have discovered’ their existence more than three years before the lawsuit was started.” He advises condominium associations to calculate “their filing deadlines as conservatively as possible.”
Read the court decisionRead the full story...Reprinted courtesy of
Noncumulation Clause Limits Coverage to One Occurrence
January 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiInjury suffered by children of different families living at different times in the same apartment was limited to one occurrence under the policy's noncumulation clause. Nesmith v. Allstate Ins. Co., 2014 N.Y. LEXIS 3350 (N.Y. Nov. 25, 2014).
The landlord had a liability policy issued by Allstate. The declarations page stated there was a $500,000 limit for "each occurrence." The policy contained the following noncumulation clause:
Regardless of the number of insured persons, injured persons, claims, claimants or policies involved, our total liability . . . for damages resulting from one accidental loss will not exceed the limit shown on the declarations page. All bodily injury . . . resulting from one accidental loss or from continuous or repeated exposure to the same general conditions is considered the result of one accidental loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
In Search of Cement Replacements
October 19, 2017 —
Aarni Heiskanen - AEC BusinessCould we replace cement as the vital element in concrete some day? We look at two alternative answers to this question.
The Problems with Cement
Portland cement dominates in the construction and road building industries. From an environmental point of view, cement is not the perfect solution. The cement industry accounts up to 7% of the world’s carbon dioxide emissions. For every 600 kg of cement, approximately 400 kg of CO2 is released into the atmosphere.
It is possible to recycle concrete by crushing it and using the gravel e.g. in road construction. However, the demand for new concrete is huge and increasing. According to The Washington Post, China used more cement between 2011 and 2013 than the U.S. used in the entire 20th Century. The worldwide production of cement has increased from 3.3 billion tons in 2010 to 4.2 in 2016. Even that is not enough; shortage of cement is a real problem in some countries.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Don’t Let Construction Problems Become Construction Disputes (guest post)
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaTo start our week off right, today we have another important article from guest blogger Christopher G. Hill, LEED AP. Chris is a Virginia Supreme Court certified mediator, construction lawyer and owner of the Richmond, VA firm, The Law Office of Christopher G. Hill, PC. He authors the Construction Law Musings blog where he discusses legal and policy issues relevant to construction professionals. His practice concentrates on mechanic’s liens, contract review and consulting, occupational safety issues (VOSH and OSHA), and risk management for construction professionals. [His blog was also one of the first construction law blogs I found and followed, even if he is a Duke alum!] Take it away, Chris!
First and foremost, thanks to Melissa for inviting me back to post here at her great blog. She continues to invite me back despite my being a Blue Devil (and I try not to hold her Tar Heel status against her).
So much of discussion relating to construction law and construction lawyers centers on the litigation of disputes. This discussion comes in many forms from avoidance of such litigation through the early intervention of good counsel prior to getting into a project to what sort of resolution mechanism to use. Another branch of this discussion is essentially the right way to pursue your claim (or as some may read it start the dispute ball rolling). Sometimes a payment bond claim is the best method while others a straight up contractual suit is the best way to go.
Of course, all of this discussion presumes that there will be disputes. While I agree to some degree that in the Murphy’s Law riddled world of commercial construction, problems will arise. These problems need not rise to the level of a dispute that requires outside (read court or arbitrator) intervention. A few tips that are easy to write, but admittedly hard to practice at times can hopefully keep problems from blossoming into disputes. I’ve listed three big ones here:
1.Use “in house counsel.” Yes, I know that most of you engineers, architects, commercial general contractors and subcontractors out there aren’t big enough to either want or need a full time attorney on the payroll. What I mean by this is that when problems occur (or preferably before doing so), give your friendly local construction lawyer a call. As I learned from my dad, an ounce of prevention and all that. That 10 minute phone call may help avoid many hours of time and bills from your attorney later down the road.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Cape Town Seeks World Cup Stadium Construction Collusion Damages
March 19, 2015 —
Janice Kew – Bloomberg(Bloomberg) -- The City of Cape Town filed a civil damages claim against builders Aveng Ltd., Wilson Bayly Holmes-Ovcon Ltd. and Stefanutti Stocks Holdings Ltd. for colluding on a tender for a stadium built for the 2010 FIFA Soccer World Cup.
The claim for at least 428 million rand ($35 million) will be heard in the North Gauteng High Court, Ian Neilson, Cape Town’s executive deputy mayor, said by phone on Monday. The amount claimed is subject to change, he said.
Antitrust authorities fined 15 builders, including the trio facing the Cape Town claim, a total of 1.5 billion rand in June 2013 for rigging contracts for projects including the construction of stadiums for the 2010 World Cup hosted by South Africa. Aveng was fined 307 million rand, WBHO 311 million rand and Stefanutti 307 million rand.
Read the court decisionRead the full story...Reprinted courtesy of
Janice Kew, BloombergMs. Kew may be contacted at
jkew4@bloomberg.net
Engineer Probing Champlain Towers Debacle Eyes Possibility of Three Successive Collapses
July 05, 2021 —
Nadine M. Post - Engineering News-RecordThough the trigger may remain a mystery for some time, by the end of the week, the structural engineer probing the partial progressive collapse of a 40-year-old Surfside, Fla., residential condominium expects to complete a computer model of the unstable, 12-story remains of the building. The computer model of the still-standing wing of Champlain Towers South will initially be used to alert the search and rescue team to suspend operations if a hurricane is coming.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Related’s $1 Billion Los Angeles Project Opens After 15-Year Wait
August 22, 2022 —
John Gittelsohn - BloombergIt’s taken 15 years — longer than the time to finish Manhattan’s Hudson Yards — for Related Cos. to complete the Grand LA, a $1 billion hotel, residential and retail complex designed by star architect Frank Gehry.
The Los Angeles hilltop development’s 28-floor Conrad hotel opens July 6, and the first tenants move into a neighboring 45-story apartment tower on July 15. The retail section — a mall-like space between the two towers for restaurants and boutiques — debuts in 2023.
Grand LA rises across Grand Avenue from Gehry’s aluminum-clad Walt Disney Concert Hall, home of the Los Angeles Philharmonic. Nearby palaces of culture include the Dorothy Chandler Pavilion, the Ahmanson Theatre, the Broad art museum, Los Angeles Museum of Contemporary Art and the Colburn School, a music and dance academy.
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, Bloomberg
Wildfire Risk Scores and Insurance Placement: What You Should Know
July 15, 2024 —
Louis "Dutch" Schotemeyer & Molly L. Okamura - Newmeyer DillionWhat Are Wildfire Risk Scores and How Are They Calculated?
Wildfire risk scores are scores assigned to properties by third-party vendors based on the likelihood of direct or indirect exposure to a wildfire. Wildfire risk scores can be a factor used by insurance companies when making coverage decisions. Additionally, wildfire risk scores can be a helpful metric for real estate developers to consider when determining whether to buy a piece of property.
There are a variety of vendors that use unique methods to calculate wildfire risk scores. For example, CoreLogic, FireLine, and RedZone are vendors used by insurance companies in California. Some vendors' scoring scales are from 1-10, and some are from 1-100, but generally the higher the score, the higher the likelihood of a wildfire impacting the property. There is no national, standardized scoring scale.
Reprinted courtesy of
Louis "Dutch" Schotemeyer, Newmeyer Dillion and
Molly L. Okamura, Newmeyer Dillion
Mr. Schotemeyer may be contacted at dutch.schotemeyer@ndlf.com
Ms. Okamura may be contacted at molly.okamura@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of