The Small Stuff: Small Claims Court and Limited Civil Court Jurisdictional Limits
June 10, 2024 —
Garret Murai - California Construction Law BlogSometimes the small stuff matters.
And when it comes to legal disputes this can pose a problem for clients as well as their attorneys because litigation and arbitration, the two most frequently utilized venues to resolve legal disputes in the United States, can be and usually are expensive.
Data on the cost of civil litigation is sparse. According to a 2013 survey of trial lawyers conducted by the National Center of State Courts, the median cost of litigating a contract dispute – which is the category that most construction disputes would fall under – is $90,575. And this is in 2013 dollars. With inflation, that number rises to nearly $120,000 in 2023, and based upon our experience litigating and arbitrating complex (and even not so complex) construction disputes, it can be many multiples over that.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Attorney’s Fees Entitlement And Application Under Subcontract Default Provision
May 06, 2019 —
David Adelstein - Florida Construction Legal UpdatesMany subcontracts contain a provision in the default section that reads something to the effect:
“Upon any default, Subcontractor shall pay to Contractor its attorney’s fees and court costs incurred in enforcing this Subcontract or seeking any remedies hereunder.”
Oftentimes, a party may wonder as to the enforceability of the provision and how it is applied in the context of a dispute between a contractor and its subcontractor where both parties have asserted claims against the other.
In an opinion out of the Middle District of Georgia, U.S. f/u/b/o Cleveland Construction, Inc. v. Stellar Group, Inc., 2019 WL 338887 (M.D.Ga. 2019), a subcontractor and prime contractor on a federal construction project each asserted claims against the other in the approximate amount of $4 Million, meaning there was a potential $8 Million swing in the dispute.
The subcontract contained a provision entitling the contractor to recover attorney’s fees incurred in enforcing the subcontract or seeking remedies under the subcontract upon any default, identical to the provision above.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Chinese Drywall Manufacturer Claims Product Was Not for American Market
October 22, 2013 —
CDJ STAFFTaishan Gypsum Co. Ltd. Claimed in a hearing at the Fifth Circuit Court of Appeals that when they sold about $8.5 million of contaminated drywall to Venture Supply Inc. of Virginia, that they had no awareness that the drywall would be sold in the United States. Joe Cyr, an attorney for Taisan told the court that “Venture Supply never said it was going to distribute the goods in Virginia.”
One of the judges on the three-judge panel, Judge Jennifer Walker Elrod, was skeptical of Taishan’s claim, asking, “it was packed and labeled for the Virginia market, isn’t that correct?” When asked by a judge if Taishan was trying to avoid accountability, Cyr said that Tiashan “has not said that it doesn’t want to be accountable for its drywall.” Taishan holds the position that claims against it should be arbitrated in the People’s Republic of China.
Read the court decisionRead the full story...Reprinted courtesy of
Assignment of Construction Defect Claims Not Covered
April 20, 2017 —
Tred R. Eyerly - Insurance Law HawaiiAssignment of insurance proceeds as part of a settlement against the subcontractor for faulty workmanship was not covered under the CGL policy in accordance with Illinois law. Allied Prop. & Cas. Ins Co v. Metro North Condominium Assoc., 2017 U.S. App. LEXIS 4107 (7th Cir. March 8, 2017).
Metro North Condominium Association hired a developer to build a condominium. The developer used CSC Glass to install the building's windows. CSC installed the windows defectively, causing the building to sustain significant water damage following a rain storm.
Metro North sued the developer, who turned out to be insolvent. Metro North amended its complaint to add a claim against CSC for breach of the implied warranty of habitability. Metro North eventually dismissed its lawsuit in exchange for an assignment of CSC's policy with Allied and payment of any right to $700,000 worth of insurance coverage. The settlement specified that it was not intended to compensate Metro North for the cost of repairing or replacing CSC's defectively installed windows, but rather for the damage to the remaining parts of Metro North's condominium.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Breach of Fiduciary Duty Claim Against Insurer Survives Motion to Dismiss
June 10, 2015 —
Tred R. Eyerly – Insurance Law HawaiiWhile some of their claims were dismissed, plaintiffs' breach of fiduciary duty survived the insurer's motion to dismiss. Senft v. Fireman's Fund Ins. Co., 2015 U.S. Dist. LEXIS 61870 (D. N.J. May 12, 2015).
Plaintiffs' waterfront home was insured by Fireman's Fund. Plaintiffs alleged that the broker represented that the policy would provide (1) coverage in the event of a hurricane,(2) the "highest level of protection" offered by Fireman's Fund, and (3) "exceptional" services in the event of a catastrophe. The policy included a 2% hurricane deductible because of the home's proximity to the ocean.
Hurricane Sandy badly damaged plaintiffs' home. Plaintiffs alleged that the winds from Sandy battered their home long before the storm surge reached the structure.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Neighbors Fight to Halt Construction after Asbestos found on Property
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFSI Live reported that residents spoke out at the Staten Island, New York community board meeting to try to halt “construction taking place at former Mount Manresa Jesuit Retreat House property in Fort Wadsworth.” Barbara Sanchez, secretary of the Committee to Save Mount Manresa, stated that halting the construction is urgent now that asbestos has been discovered on the property.
"We want a full stop-work order ... Everything being done around those buildings is being blown into our homes,” Sanchez said in the meeting, according to SI Live. “So I want testing for ... everything touched by the asbestos -- and our homes, before the work continues at Mount Manresa!"
Jeanna Massimi, a resident of Fort Wadsworth, stated that people in the community are already dealing with health problems due to the construction work: “A lot of people where I live [are having] X-rays and are being tested for asbestos exposure. They can't have their bedroom windows open anymore. The dust is like soot -- it's thick. It's everywhere in the home. People are coughing, wheezing and hoarse. You end up feeling lethargic.”
Mike Gilsenan, assistant deputy commissioner at the Department of Environmental Protection, said it was “highly unlikely any dust or fibers migrated off that site. That is the best I can tell you.” But SI Live reported that he added “that the process is ‘not foolproof.’”
Read the court decisionRead the full story...Reprinted courtesy of
The Investors Profiting Off Water Scarcity
June 10, 2024 —
Linda Poon - BloombergWe’re excited to share that the Bloomberg Green series Water Grab was named a Pulitzer Prize finalist. The series, which includes contributions from several CityLab writers and alums, explores how private investors are commandeering public water for profit at the expense of both the environment and less powerful communities.
Below is a sample of stories looking at how investors, private equity firms and Wall Street are taking advantage of the world’s scarce water supply. Read the full series here, which is now in front of the paywall.
Reprinted courtesy of
Linda Poon, Bloomberg
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts Federal Court Holds No Coverage for Mold and Water Damage Claim
February 11, 2019 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Clarendon National Ins. Co. v. Philadelphia Indemnity Ins. Co., 2019 WL 134614 (D. Mass. Jan. 8, 2019), the United States District Court for the District of Massachusetts had occasion to consider the application of a prior knowledge provision in the context of a claim for mold and water-related bodily injury and property damage.
Philadelphia insured a condominium property management company under a general liability insurance policy for the period September 1, 2007 through September 1, 2008. In 2009, the insured was sued by a unit owner alleging bodily injury and property damage resulting from toxic mold conditions resulting from leaks that had been identified in her unit as early as 2004. Notably, the complaint alleged that mold was identified in 2006 and that repair efforts were undertaken, but that these efforts all proved unsuccessful. Plaintiff alleged that she was forced to vacate her apartment in 2008 as a result of the conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub LiebermanMr. Margolies may be contacted at
bmargolies@tlsslaw.com