Construction Costs Must Be Reasonable
May 17, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to proving a construction cost, particularly a cost in dispute, the cost must be REASONABLE. Costs subject to claims must be reasonably incurred and the party incurring the costs must show the costs are reasonable.
An example of the burden falling on the contractor to prove the reasonableness of costs is found in government contracting.
“[T]here is no presumption that a [government] contractor is entitled to reimbursement ‘simply because it incurred…costs.’” Kellogg Brown & Root Services, Inc. v. Secretary of Army, 973 F.3d 1366, 1371 (Fed. Cir. 2020) (citation omitted). Stated differently, a federal contractor is not entitled to a presumption of reasonableness just because it incurs costs. Id.
In government contracting, the Federal Acquisition Regulations (known as “FAR”) puts the burden of reasonableness on the contractor that incurred the costs. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Charles Carter v. Pulte Home Corporation
October 12, 2020 —
Michael Velladao - Lewis BrisboisIn Carter v. Pulte Home Corp., __Cal.App.5th__(July 23, 2020), the California Court of Appeal affirmed the entry of judgment in favor of subcontractors in connection with a Complaint for Intervention based on equitable subrogation filed by Travelers Property Casualty Company of America (“Travelers”) seeking to recover defense costs incurred in defending Pulte Home Corporation (“Pulte”) in an underlying construction defect lawsuit. The parties’ dispute arose out of Travelers’ defense of Pulte as an additional insured under policies issued to four subcontractors involved in the underlying construction defect lawsuit. Several subcontractors involved in the underlying construction defect lawsuit refused to defend Pulte based on the indemnity clauses in their subcontracts. Such clauses promised to indemnify Pulte as follows:
“all liability, claims, judgments, suits, or demands for damages to persons or property arising out of, resulting from, or relating to Contractor’s performance of work under the Agreement (“Claims”) unless such Claims have been specifically determined by the trier of fact to be the sole negligence of Pulte. . . .”
Pulte eventually settled the construction defect lawsuit and its claims against all of the subcontractors. Travelers ultimately paid $320,491.82 for Pulte’s defense and recovered $164,400 from some of the subcontractors. Travelers’ intervention in the underlying lawsuit was intended to recover the remaining $156,091.82 from the subcontractors that refused to indemnify Pulte for the defense of the construction defect lawsuit. In the underlying trial, Travelers argued that the subcontractors were obligated to pay defense costs on a joint and several basis (minus what Travelers had already recovered). The trial court did not agree and held that Travelers was not entitled to equitable subrogation for the remaining defense costs.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
Contractors: Revisit your Force Majeure Provisions to Account for Hurricanes
September 14, 2017 —
David Adelstein - Florida Construction Legal UpdatesWe now know and can appreciate the threat of hurricanes. Not that we did not appreciate the reality of hurricanes–of course we did–but Hurricane Harvey and Hurricane Irma created the type of actual devastation we fear because they hit close to home. The fear came to life, creating panic, anxiety, and uncertainty. It is hard to plan for a force majeure event such as a hurricane because of the capriciousness of Mother Nature. But, we need to do so from this point forward. No exception! And, I mean no exception!!
A force majeure event is an uncontrollable event that cannot be anticipated with any degree of definitiveness. The force majeure event will excusably delay or hinder performance obligations under a contract. One type of force majeure event is a hurricane—an uncontrollable and unforeseen act of Mother Nature.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
West Coast Casualty’s 25th Construction Defect Seminar Has Begun
May 16, 2018 —
Beverley BevenFlorez-CDJ STAFFThe first day of this year’s West Coast Casualty Seminar has concluded, with two more days ahead to learn, network, and discuss the construction defect industry’s current trends.
Don’t forget to stop by the Bert L. Howe & Associate’s exhibit so that you can participate in their Sink a Putt for Charity Golf Challenge. As in the past, attendees can participate for free in the BHA golf challenge and win a $25 Amazon gift card, and for every successful putt made, BHA will make a $25 cash donation in the golfer’s name to be distributed equally between each worthy organization. This year, participant’s efforts on the green will help benefit three cancer fighting institutions that are dedicated to treating and eradicating children’s cancer: Hawaii’s Children’s Cancer Foundation, St. Jude Children’s Research Hospital, and Shriners Hospital for Children. BHA is also raffling Dodger’s tickets, so you won’t want to miss their exhibit. You may read more about this year’s exhibit at
BHA HAS A NICE SWING and take a look back at previous exhibits,
20 YEARS OF BHA AT WEST COAST CASUALTY'S CD SEMINAR: CHRONICLING BHA'S INNOVATIVE EXHIBITS.
Want some help maximizing your work-play schedule? Check out
CDJ’s Sample Itinerary to get the Most out of West Coast Casualty’s Construction Defect Seminar that includes the seminar schedule as well as dining and event suggestions. We also have included suggestions for exploring the Greater Anaheim area:
BEYOND THE DISNEYLAND RESORT: DINING,
BEYOND THE DISNEYLAND RESORT: SPECIAL EVENTS,
BEYOND THE DISNEYLAND RESORT: MUSEUMS, and
BEYOND THE DISNEYLAND RESORT: WORLD CLASS SHOPPING EXPERIENCES.
Last week, Don MacGregor wrote a not-to-be-missed piece on
THE EVOLUTION OF CONSTRUCTION DEFECT TRENDS AT WEST COAST CASUALTY SEMINAR.
Thursday, this year’s West Coast Casualty awards will be presented. To learn more about these coveted awards, please see
A LOOK BACK AT THE OLLIES and
AN ERA OF LEGENDS.
We hope you enjoy days two and three of the seminar!
Read the court decisionRead the full story...Reprinted courtesy of
Order for Appraisal Affirmed After Insureds Comply with Post-Loss Obligations
April 15, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Florida Court of Appeal affirmed an order compelling an appraisal because the insureds complied with their post-loss obligations under the policy. State Farm Fla. Ins. Co. v. Cardelles, 2015 Fla. App. LEXIS 2559 (Fla. Ct. App. Feb. 25, 2015).
The insureds suffered damage to their home after Hurricane Katrina on August 25, 2005, and again after Hurricane Wilma on October 24, 2005. After each hurricane, State Farm was notified. With the assistance of their public adjuster, the insureds submitted sworn proofs of loss for damages caused by each hurricane. After the deductible, State Farm paid $19,000 for the Hurricane Katrina claim and $13,000 for the Hurricane Wilma claim. The insureds repaired their roof and made minor repairs to their home with the State Farm payment, but claimed the payment was insufficient to fully repair the damage from the two hurricanes.
Four years later, the insureds hired a second public adjuster, who submitted a supplemental claim to State Farm for $127,000 in damages. State Farm requested documents and an updated sworn proof of loss. The insureds did not submit any additional documents because they had not made any additional repairs without further payment from State Farm. The insureds did, however, allow State Farm to make a further inspection of the damages.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Haight’s San Diego Office is Growing with the Addition of New Attorneys
June 21, 2024 —
Haight Brown & Bonesteel LLPThe San Diego office has recently added two attorneys to the team.
Amanda McKechnie has joined the Construction Law Practice Group. Amanda has extensive experience representing national developers, owners, general contractors, design professionals and subcontractors in complex construction litigation.
Arash Yahyai has joined the Construction Law and General Liability Practice Groups. Arash focuses on defending actions involving complex construction defect, insurance defense, premises liability, product liability, catastrophic personal injury and other general liability related cases.
Read the court decisionRead the full story...Reprinted courtesy of
Haight Brown & Bonesteel LLP
Texas Supreme Court Finds Payment of Appraisal Award Does Not Absolve Insurer of Statutory Liability
April 19, 2021 —
Allison Griswold & Sarah Smith - Lewis BrisboisThe Texas Supreme Court recently published its long-awaited decision in the Hinojos v. State Farm Lloyds. In it, the court affirmed its holding in Barbara Technologies, finding that payment of an appraisal award does not absolve an insurer of statutory liability when the insurer accepts a claim but pays only part of the amount it owes within the statutory deadline, and a policy holder can proceed with an action under the Texas Prompt Payment of Claims Act.
In 2013, Louis Hinojos made a claim for storm damage to his home. State Farm’s initial inspection resulted in an estimate below the deductible, but Hinojos disagreed and requested a second inspection. At the second inspection, the adjuster identified additional damage resulting in a payment to Hinojos of $1,995.11. Hinojos then sued State Farm – and State Farm invoked appraisal approximately 15 months after suit was filed. The appraisal resulted in State Farm tendering an additional payment of $22,974.75. State Farm moved for summary judgment, arguing that timely payment of an appraisal award precluded prompt payment (or Chapter 542) damages. The trial court granted summary judgment and Hinojos appealed (notably Barbara Technologies had not yet been decided). The Court of Appeals affirmed State Farm’s victory on the basis that “State Farm made a reasonable payment on Hinojos’s claim within the sixty-day statutory limit….” Hinojos petitioned the Texas Supreme Court for review.
Reprinted courtesy of
Allison Griswold, Lewis Brisbois and
Sarah Smith, Lewis Brisbois
Ms. Griswold may be contacted at Allison.Griswold@lewisbrisbois.com
Ms. Smith may be contacted at Sarah.Smith@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Response: Essential Business Operations: a High-Stakes Question Under Proliferating “Stay at Home” Orders
April 27, 2020 —
Karen C. Bennett, Katherine I. Funk & Jane C. Luxton - Lewis BrisboisAn ever-expanding number of states and local government authorities are issuing “shelter in place” or “stay at home” orders that restrict the movement of employees of non-essential businesses. These orders have prompted many businesses to question whether they qualify as “essential,” requiring employees to continue working. With substantial differences among the stay at home orders – and even potential conflicts between state and local directives – it is a matter of extreme urgency for businesses to determine whether they fall within the definition of “essential,” particularly as many of these orders include civil and criminal penalties.
Developments are unfolding very quickly, and clients we are advising are encountering law enforcement visits and threats of criminal prosecution as a consequence of decisions to stay open. As these designations are heavily fact-specific, and being revised, advance preparation and advice of counsel are essential.
Reprinted courtesy of Lewis Brisbois attorneys
Karen C. Bennett,
Katherine I. Funk and
Jane C. Luxton
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Funk may be contacted at Katherine.Funk@LewisBrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of