Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
No Duty To Defend Additional Insured When Bodily Injury Not Caused by Insured
July 26, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe court found there was no duty to defend a suit for bodily injury against the additional insured where the injury was not caused by the insured. Consigli Constr. Co. v. Travelers Indem. Co., 2017 U.S. Dist. LEXIS 95339 (D. Mass. June 21, 2017).
Consigli was the general contractor for a renovation project at a high school. Among the subcontractors was American Environmental, Inc., who was responsible for demolishing concrete floors within the existing structures, and Costa Brothers, who did the masonry work. Wellington M. Ely was an employee of Costa Brothers and worked as a mason on the project.
Costa Brothers had a CGL policy with Travelers. As a subcontractor, Costa Brothers agreed to name Consigli as an additional insured on its policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Perrin Construction Defect Claims & Trial Conference
June 11, 2018 —
Beverley BevenFlorez-CDJ STAFFRichard Glucksman, Esquire, Partner of the Los Angeles firm Chapman Glucksman Dean Roeb & Barger, will be moderating the panel, “Green Building/LEED: An Overview and Claims Discussion” at the Perrin Construction Defect Claims & Trial Conference in Las Vegas, Nevada. The panel will be discussing the following topics:
- Risk and claims case studies including solar and SIPs (Structural Insulated Panels)
- Green Building/LEED and The Law: Review of National Claims/Lawsuits
- AIA Documents for Sustainable Projects
Thursday, June 21st, 2018
Four Seasons Hotel
3960 S Las Vegas Blvd
Las Vegas, NV 89119
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara LLP Attorneys to Speak at the 2016 National Construction Claims Conference
September 01, 2016 —
Beverley BevenFlorez-CDJ STAFFBremer Whyte Brown & O’Meara, LLP (BWBO), announced that Keith G. Bremer, Founding Partner and John H. Toohey, Partner, will be speaking at the CLM National Construction Claims Conference being held September 28-30th this year. More than 500 professionals will gather at the conference location, the Manchester Grand Hyatt in San Diego, California.
According to BWBO’s release, “the CLM will hold the most comprehensive construction claims conference ever. In addition to addressing construction defect claims, conference sessions will also address facets of construction-related claims including construction site accidents/injuries, coverage issues, subcontractor issues, and new technologies. Sessions will also address issues on the national, regional, and state levels.”
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Installation of Defective Steel Framing
June 26, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe California Court of Appeal affirmed the trial court's holding that the insurer had no duty to defend claims arising out of the insureds' installation of defective steel framing in an apartment building. Regional Steel Corp. v. Liberty Surplus Ins. Corp., No. B245961(Cal. Ct. App. May 16, 2014) [decision here].
Regional Steel was a subcontractor for providing reinforced steel to the columns, walls, and floors of an apartment building under construction. Regional used 90 degree and 135 degree seismic hooks as approved by the general contractor, JSM Construction, Inc. The City building inspector issued a correction notice, however, requiring the exclusive use of the 135 degree hooks. Levels one through three had defective tie hooks and required repair. JSM refused to pay Regional's invoices and withheld $545,000. JSM had to make repairs that required opening up numerous locations in the concrete walls, welding reinforcements to the steel placed by Regional, and otherwise strengthening the inadequate installation.
Regional sued JSM for the withheld payment. JSM cross-claimed, asserting breach of contract and breach of express and implied warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Accounting for Payments on Projects Became Even More Crucial This Year
September 21, 2020 —
Christopher G. Hill - Construction Law MusingsI discussed
several of the statutory changes affecting the construction industry here at Construction Law Musings in the run-up to July 1, 2020. One of those changes, an amendment to
Virginia Code Section 43-13, may add another arrow to the collection quiver of subcontractors and suppliers. As part of the previously-linked rundown, I highlighted one of the big additions in 2020, namely the amendment making those pesky clauses that let those up the payment chain from you hold money on “this or any other project” void as against public policy.
The other big addition to 43-13 is the change that adds a possible civil cause of action for downstream and unpaid subcontractors and suppliers in the event that funds paid to a general contractor or subcontractor are not first used to pay their downstream contractors and suppliers. Prior to July 1, 2020, this statute provided criminal penalties for such behavior but did not contain the possibility of a civil penalty. The operative language for the change is as follows:
The use by any such contractor or subcontractor or any officer, director, or employee of such contractor or subcontractor of any moneys paid under the contract before paying all amounts due or to become due for labor performed or material furnished for such building or structure for any other purpose than paying such amounts due on the project shall be prima facie evidence of intent to defraud. Any breach or violation of this section may give rise to a civil cause of action for a party in contract with the general contractor or subcontractor, as appropriate; however, this right does not affect a contractor’s or subcontractor’s right to withhold payment for failure to properly perform labor or furnish materials on the project.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Termination for Convenience Clauses: Maybe More Than Just Convenience
June 06, 2022 —
Robert C. Shaia - ConsensusDocsA contractor begins work on a project and everything is going well, until one day the owner informs the contractor that it is being terminated for convenience. Possibly, there is no discussion about alleged defects, reasons for the termination, or any damages the owner might seek against the contractor. In that moment, the contractor may be unaware of any perceived wrongdoing or problems with its work.
The industry has typically accepted that, in this scenario, the owner implicitly waives the right to any remedies against the contractor, except those expressly set forth in the contract. Reasonable minds might assume that, if the owner believed it needed to seek further remedies, it would terminate the contractor for cause instead of convenience. And often overlooked during contract negotiations are the benefits of including an express “waiver of remedies” in the termination for convenience section.
Read the court decisionRead the full story...Reprinted courtesy of
Robert C. Shaia, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Mr. Shaia may be contacted at
rshaia@watttieder.com
Issuing Judgment After Confirmation of Appraisal Award Overturned
May 01, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Court of Appeal reversed and remanded the trial court's judgment in favor of the insured because after confirming the appraisal award, judgment was issued before the insurer could offer policy defenses. State Farm Florida Ins. Co. v. Hochreiter, 2023 Fla. App. LEXIS 743 (Fla. Ct. App. Feb. 3, 2023.
After a dispute arose over the scope and amount of damage suffered by the insureds' roof, they sued State Farm. State Farm responded to the complaint by demanding an appraisal, a stay of litigation, and an extension of time to respond to the complaint.
The trial court granted the demand and retained jurisdiction regarding post-appraisal matters once the appraisal was complete. The court further ordered State Farm to respond to the complaint within twenty days of the conclusion of the appraisal "if any issues remain." The order did not specify whether the issues that remained had to relate to the initial appraisal stage of the litigation or the subsequent stage during which the trial court had jurisdiction to adjudicate disputed issues related to coverage.
Read the court decisionRead the full story...Reprinted courtesy of