Court Concludes That COVID-19 Losses Can Qualify as “Direct Physical Loss”
September 28, 2020 —
Lorelie S. Masters & Jorge R. Aviles - Hunton Andrews KurthIn a victory for policyholders, a federal district court found that COVID-19 can cause physical loss under business-interruption policies. In Studio 417, Inc., et al. v. The Cincinnati Insurance Co., No. 20-cv-03127-SRB (W.D. Mo. Aug. 12, 2020), the court rejected the argument often advanced by insurers that “all-risks” property insurance policies require a physical, structural alteration to trigger coverage. This decision shows that, with correct application of policy-interpretation principles and strategic use of pleading and evidence, policyholders can defeat the insurance industry’s “party line” arguments that business-interruption insurance somehow cannot apply to pay for the unprecedented losses businesses are experiencing from COVID-19, public-safety orders, loss of use of business assets, and other governmental edicts.
The policyholders in Studio 417 operate hair salons and restaurants asserting claims for business interruption. In suing to enforce their coverage, the policyholders allege that, over the last several months, it is likely that customers, employees, and/or other visitors to the insured properties were infected with COVID-19 and thereby infected the insured properties with the virus. Their complaint asserts that the presence of COVID-19 “renders physical property in their vicinity unsafe and unusable.” Unlike some other complaints seeking to enforce such coverage, it also alleges that the presence of COVID-19 and government “Closure Orders” “caused a direct physical loss or direct physical damage” to their premises “by denying use of and damaging the covered property, and by causing a necessary suspension of operations during a period of restoration.”
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Jorge R. Aviles, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Aviles may be contacted at javiles@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Orchestrating Bias: Arbitrator’s Undisclosed Membership in Philharmonic Group with Pauly Shore’s Attorney Not Grounds to Reverse Award in Real Estate Dispute
June 21, 2017 —
Lyndsey Torp - Snell & Wilmer Real Estate Litigation BlogThe California court of appeal recently issued an unpublished decision in Knispel v. Shore, 2017 WL 2492535, affirming a judgment confirming an arbitration award in a real estate dispute involving Pauly Shore. The court of appeal held that the arbitrator’s failure to disclose her membership in the Los Angeles Lawyers Philharmonic Group with the attorney representing Pauly was not grounds to overturn the judgment.
The underlying arbitration involved a dispute between Michael Scott Shore, on the one hand, and his brother, Pauly, among others, on the other hand, regarding certain residential property located on Sunset Boulevard near The Comedy Store in West Hollywood (owned and operated by their mother, Mitzi Shore). The parties agreed to arbitrate their dispute before Judge Aviva K. Bobb (Ret.) of the Alternative Resolution Center. Judge Bobb issued an award in favor of Pauly, and he petitioned the trial court to affirm the award. Michael opposed, contending the arbitrator failed to disclose that she and Pauly’s attorney had both been members of the Lawyers Philharmonic, for which they had been practicing and performing together since November 2010.
Read the court decisionRead the full story...Reprinted courtesy of
Lyndsey Torp, Snell & WilmerMs. Torp may be contacted at
ltorp@swlaw.com
Recent Third Circuit OSHA Decision Sounds Alarm for Employers and Their Officers
October 14, 2019 —
John Baker - White and Williams LLPThe Third Circuit Court of Appeals recently issued an opinion that should serve as a warning not only to employers, but to their corporate officers. The case against Altor, Inc., a New Jersey-based construction company, began in 2012 when the Occupational Safety and Health Administration (OSHA) directed Altor and its sole director and officer to pay a $412,000 penalty (Payment Order) to OSHA for several violations, including the failure to comply with fall protection standards. The company refused to pay, arguing that it did not possess sufficient assets. The Secretary of Labor filed a Petition for Civil Contempt against Altor and its President, Vasilios Saites. The court acknowledged that the company and Mr. Saites could defend against a contempt finding by showing that he and the company were unable to comply with the Payment Order. Beyond merely stating that they could not pay, the court required that they must show that they made good faith efforts to comply with the Order.
After considering all of the evidence, the court ultimately relied on Altor’s bank records, which reflected that the company ended each month during a two-year period after the violations with a positive bank balance. Thus, the court determined that Altor could have made “at least relatively modest” payments and emphasized that the company never attempted to negotiate a reduced sum or a payment plan.
Read the court decisionRead the full story...Reprinted courtesy of
John Baker, White and Williams LLPMr. Baker may be contacted at
bakerj@whiteandwilliams.com
Best Lawyers Honors 43 Lewis Brisbois Attorneys, Recognizes Three Partners as 'Lawyers of The Year'
September 14, 2020 —
Lewis BrisboisBest Lawyers has selected 43 Lewis Brisbois attorneys across 25 offices for inclusion in its list of 2021 Best Lawyers in America. It has also recognized three Lewis Brisbois partners as "Lawyers of the Year": Los Angeles Partner Jon P. Kardassakis (Mass Tort Litigation / Class Actions - Defendants); Roanoke Partner Paul C. Kuhnel (Medical Malpractice Law - Defendants); and Northwest Indiana Managing Partner Renee J. Mortimer (Personal Injury Litigation - Defendants).
Please join us in congratulating these three partners and the following attorneys on their Best Lawyers recognition.
Reprinted courtesy of
Lewis Brisbois
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
No Rest for the Weary: Project Completion Is the Beginning of Litigation
June 18, 2019 —
Albert Li & Bob Fitzsimmons - Construction ExecutiveIn today’s environment, most construction projects end up in some form of litigation. Construction is full-time employment for lawyers – from contract negotiation to project management, lien and payment issues. Years after project completion, a company still can face construction defect litigation and be served with a Notice of Opportunity to Repair, which in most states is now codified into statute. This is the beginning of what most likely will become a lawsuit, involving many of the subcontractors.
Watch Out for the Construction Contract Blame Game
The first phase of post construction litigation involves the review of contract and insurance policy language in an attempt to transfer responsibility in the litigation to other parties.
Before construction began, contract negotiation focused on budget and timeline. In the post-construction phase, two less noticed provisions of the contract are critical – indemnity and insurance.
Reprinted courtesy of
Albert Li & Bob Fitzsimmons, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Fitzsimmons may be contacted at rfitzsimmons@rumberger.com
Mr. Li may be contacted at ali@rumberger.com
Read the court decisionRead the full story...Reprinted courtesy of
Mitigate Construction Risk Through Use of Contingency
April 26, 2021 —
Laurie A. Stanziale - Construction ExecutiveMitigation of risk and costs in a construction project are always priorities for owners. In some contracts, in particular, Guaranteed Maximum Price contracts, some of those monetary risks are shifted to the contractor. Contingency is important because it allows for money to be in the budget for the unexpected and to keep the project moving, which benefits everyone.
WHAT IS CONTINGENCY?
Contingency is an amount of money built into the contractor’s price to complete the project to address unforeseen (although sometimes very common) costs that arise. This sum of money is generally referred to as the contractor’s contingency. The amount of the contingency is a balance struck between having money on hand to address the unexpected while also not unnecessarily tying up money that could otherwise be used for the project. Contingency is typically 5-10% of the hard costs. However, how the money is actually allocated during the project is not always well thought out, which can be the source of problems during the project.
The contractor’s contingency is not to be confused with an owner’s contingency (or reserve) which is outside of the contractor’s budget and generally used for owner driven changes to the project, such as changes to scope, design and schedule.
Reprinted courtesy of
Laurie A. Stanziale, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Contractual Warranty Agreements May Preclude Future Tort Recovery
January 11, 2022 —
Taylor Ostrowski - Colorado Construction Litigation BlogWhen a buyer purchases a product that is later discovered to be defective, the court offers a remedy to make the buyer whole. Such remedies can arise either out of a contract, including express and/or implied warranties, or under common law through a tort theory. However, what happens when a buyer has already received the remedy specified in the contractual warranty, only to discover the product manufacturer misrepresented the quality of its product by failing to disclose a defect? Can the buyer subsequently recover for the same product under a tort theory of recovery? The Colorado Court of Appeals analyzed such questions in its December 2021 decision in Dream Finders Homes, LLC v. Weyerhaeuser NR Co., 2021 COA 143.
In Dream Finders, the court examines the rights of sophisticated buyers who purchased defective products and received a warranty from the product manufacturer with purchase. The court specifically determines whether such buyers may recover under the tort theory product misrepresentation and failure to disclose when the buyers have already received the remedy specified and the warranty expressly excludes the type of damage the buyer now seeks.
Read the court decisionRead the full story...Reprinted courtesy of
Taylor Ostrowski, Higgins, Hopkins, McLain & Roswell, LLCMs. Ostrowski may be contacted at
ostrowski@hhmrlaw.com
Want to Build Affordable Housing in the Heart of Paris? Make It Chic.
November 01, 2022 —
Marie Patino & Kriston Capps - BloombergThe project at 12 Rue Jean-Bart is a modest one, just eight units of affordable housing on a narrow lot in Paris near the Luxembourg Gardens. The social housing project nevertheless caused a stir with neighbors in the 6th arrondissement, one of the city’s more affluent areas.
When local politicians backing the project came to visit the building during its construction, neighbors shouted from windows across the street that it was a shame to build social housing here, according to Jean-Christophe Quinton, the Paris-based architect who designed the small in-fill development.
Local resistance was a persistent feature of the project throughout its three-year-long construction, Quinton says; the building regularly faced harsh scrutiny in local newspaper Le Parisien.
Reprinted courtesy of
Marie Patino, Bloomberg and
Kriston Capps, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of