Guessing as to your Construction Damages is Not the Best Approach
November 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesArbitrarily guessing as to your construction damages is NOT the best approach. Sure, experts can be costly. No doubt about it. Having an expert versus guessing as to your construction damages caused by another party’s breach of contract is a no brainer. Engage an expert or, at a minimum, be in a position to competently testify as to your damages caused by another party’s breach of contract. Otherwise, the guessing is not going to get you very far as a concrete subcontractor found out in Patrick Concrete Constructors, Inc. v. Layne Christensen Co., 2018 WL 6528485 (W.D. New York 2018) where the subcontractor could not competently support its delay-related damages or change orders and, equally important, could not support that the damages were proximately caused by the general contractor’s breach of the subcontract.
In this case, the concrete subcontractor entered into a subcontract to perform concrete work for a public project. The project was delayed and the general contractor was required to pay liquidated damages to the owner. Not surprisingly, the subcontractor disputed liability for delays and sued the general contractor for all of its delay-related damages “in the form of labor and materials escalation, loss of productivity, procurement and impact costs, field and home office overhead, idle equipment, inability to take on other work, lost profits, and interest.” Patrick Concrete Constructors, 2018 WL at *1.
The general contractor moved for summary judgment as to the plaintiff’s delay-related damages – the subcontractor’s damages were nothing but guesses and the subcontractor could not prove the general contractor was the cause of the subcontractor’s damages.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Risk Spotter Searches Internal Data Lakes For Loaded Words
October 11, 2017 —
Tom Sawyer - Engineering News-RecordA tech start-up recently announced that it has been granted seven U.S. patents for a system that applies a “deep learning” algorithm to examine corporate e-mail databases and flag those with message fields or attachments containing language that might increase risk for a company involved in a federal discrimination lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Sawyer, ENRMr. Sawyer may be contacted at
sawyert@enr.com
Newmeyer Dillion Named 2023 Best Law Firm in Multiple Practice Areas By U.S. News-Best Lawyers
November 07, 2022 —
Newmeyer DillionNEWPORT BEACH, Calif. – November 3, 2022 – Prominent business and real estate law firm Newmeyer Dillion is pleased to announce that U.S. News-Best Lawyers® has recognized the firm in its 2023 "Best Law Firms" rankings, in seven practice areas earning the highest ranking possible - Tier 1 in the Orange County Metro area. The practices recognized include:
Commercial Litigation
Construction Law
Insurance Law
Litigation - Construction
Litigation - Insurance
Litigation - Real Estate
Real Estate Law
Additionally, the firm has been recognized as Tier 2 in Employment Law - Management and Tier 3 in Litigation - Labor & Employment.
"Newmeyer Dillion prides itself on genuinely partnering with our clients to offer business-oriented solutions for their legal issues," said Managing Partner Paul Tetzloff. "Receiving this honor shows that our clients appreciate the quality of our work and our team's dedication to their organization's success."
Firms included in the 2023 "Best Law Firms" list have been recognized by their clients and peers for their professional excellence. Firms achieving a Tier 1 ranking have consistently demonstrated a unique combination of quality law practice and breadth of legal expertise.
To be eligible for the "Best Law Firms" ranking, a firm must have at least one attorney recognized in the current edition of The Best Lawyers in America for a specific practice area. Best Lawyers recognizes the top 4 percent of practicing attorneys in the U.S., selected through exhaustive peer-review surveys in which leading lawyers confidentially evaluate their professional peers.
About Newmeyer Dillion
For over 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that achieve client objectives in diverse industries. With over 60 attorneys working as a cohesive team to represent clients in all aspects of business, employment, real estate, environmental/land use, privacy & data security and insurance law, Newmeyer Dillion delivers holistic and integrated legal services tailored to propel each client's operations, growth, and profits. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
Lost Productivity or Inefficiency Claim Can Be Challenging to Prove
May 02, 2022 —
David Adelstein - Florida Construction Legal UpdatesOne of the most challenging claims to prove is a lost productivity or inefficiency claim. There is an alluring appeal to these claims because there are oftentimes intriguing facts and high damages. But the allure of the presentation of the claim does not compensate for the actual burden of proof in proving the lost productivity or inefficiency claim, which will require an expert. And they really are challenging to prove.
Don’t take it from me. A recent Federal Claims Court opinion, Nova Group/Tutor-Saliba v. U.S., 2022 WL 815826, (Fed.Cl. 2022), that I also discussed in the preceding
article, exemplifies this point.
To determine lost productivity or inefficiency, the claimant’s expert tried three different methodologies.
First, the expert looked at industry standard lost productivity factors such as those promulgated by the Mechanical Contractor’s Association. However, the claimant was not a mechanical contractor and there is a bunch of subjectivity involved when using these factors. The expert decided not to use such industry standard factors correctly noting they provide value when you are looking at a potential impact prospectively, but once you incur actual damages and have real data, it is not an accurate measure.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New York Regulator Issues Cyber Insurance Guidelines
March 29, 2021 —
Anne Kelley - Newmeyer DillionFrom the rise of ransomware attacks to the recent SolarWinds-based cyber espionage campaign that struck at the very heart of the U.S. Government, it is apparent that cybersecurity is more critical than ever. COVID-19 and the remote workplace has only served to embolden cyber criminals, and cyber risk now permeates nearly every aspect of modern life from health care data to national security.
Cyber insurance plays a critical role in managing cyber risk, and businesses increasingly rely on such coverage to minimize cyber losses. Because of surging cybercrime, it is estimated that the cyber insurance market will increase from $3.15 billion in 2019 to $20 billion by 2025. Having a robust cyber insurance market and ample available coverage is vital to U.S. businesses.
In recognition of this reality, the New York Department of Financial Services recently issued the first guidance by a U.S. regulator on cyber insurance—a Cyber Insurance Risk Framework. A key premise of the Framework is to drive improved cybersecurity and cyber risk management, thereby reducing cyberattacks and ensuring that cyber insurance premiums do not spiral out of control. The Framework recognizes the importance of ensuring a healthy cyber insurance market, and applies to all property/casualty insurers that write cyber insurance.
Read the court decisionRead the full story...Reprinted courtesy of
Anne Kelley, Newmeyer DillionMs. Kelley may be contacted at
anne.kelley@ndlf.com
New York Appeals Court Rekindles the Spark
March 16, 2017 —
Lian Skaf - White and Williams LLPIn John Trimble, et al. v. City of Albany, et al., 2016, 144 A.D.3d 1484; 42 N.Y.S. 3d 432 (N.Y. App. Div.), the Supreme Court of New York, Appellate Division, addressed the issue of governmental immunity for municipal fire companies. The court held that the plaintiff, John Trimble (Trimble), had sufficient evidence related to the four-pronged test for establishing a “special relationship” between a municipality and a citizen for liability to attach. In addition, the court held that the defendants were not entitled to summary judgment on the issue of governmental immunity. Specifically, regarding the latter holding, the court stated that, when there is no actual choice made on the part of the government, the government’s actions cannot be considered discretionary and immunity will not apply.
In the case at hand, a fire occurred at Trimble’s home on the evening of February 2, 2013. Trimble called 911 and the Department of Fire and Emergency Services for the City of Albany (the Department) responded. After extinguishing the fire, the Department conducted an investigation and cleared the home. The Department’s investigators then told Trimble that the fire was extinguished and it was safe to enter the home. Trimble did so, removing some items so that he could stay with relatives that night. Several hours later, there was a rekindle and the rekindled fire destroyed the home.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Arkansas Federal Court Fans the Product Liability Flames Utilizing the Malfunction Theory
September 14, 2020 —
Michael J. Ciamaichelo - The Subrogation StrategistTo establish a product liability claim in Arkansas, the plaintiff must prove that the product was supplied in a defective condition, which rendered it unreasonably dangerous and that the defective condition was the proximate cause of the claimed damage or injury. Ordinarily, a plaintiff relies upon direct evidence of a product defect to establish its product liability claim. However, in some cases, the product sustains so much damage that it is impossible for a plaintiff to obtain direct evidence of a defect.
The malfunction theory allows a plaintiff in a product liability action to establish a defect through circumstantial evidence, when direct evidence of a defect no longer exists. In order to utilize the malfunction theory, a plaintiff must present evidence that an unspecified product defect was the most likely cause of the damage/accident and rule out all other possible causes of the damage/accident. In Am. Nat’l Prop. & Cas. Co. v. Broan-Nutone, No. 5:18-CV-5250, 2020 U.S. Dist. LEXIS 117116, the United States District Court for the Western District of Arkansas ruled that the plaintiff offered sufficient evidence under “the malfunction theory” to defeat a summary judgment motion in a product liability action involving a bathroom fan that was destroyed in a fire.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com
COVID-19 and Mutual Responsibility Clauses
June 01, 2020 —
Joseph M. Leone - ConsensusDocsAs everyone knows, there is a tremendous amount of uncertainty in the construction industry due to the COVID-19 pandemic. Schedules, productivity, safety processes, and seemingly everything else are being affected. In these difficult times, most contractors are making every effort to work together to solve the problems caused by COVID-19. But what happens when differences arise between project owners, contractors, and subcontractors as to the effect of COVID-19 on a project? One party may want to continue pushing the schedule, others may want to slow down, or, more likely, not be able to keep up with the original schedule because of some reason related to COVID-19. As between a prime contractor and a subcontractor, a mutual responsibility clause can provide some clarity or, unfortunately, depending on how the subcontract is written, confusion.
Almost all subcontracts have a clause which flows down the prime contractor’s obligations on a project to the subcontractor as applicable to the subcontractor’s work. Known as “flow-down” clauses, this clause works in one direction; obligations of the prime contractor “flow-down” to the Subcontractor. A mutual responsibility clause, in essence, works in both directions. The subcontractor is required to perform its obligations consistent with the prime contractor’s obligations to the owner and the subcontractor is granted the same rights against the prime contractor which the prime contractor has against the owner. Obligations flow down and rights flow up. The rights and obligations flowing through the prime contractor include, the obligation to perform the work in accordance with the plans and specifications, the obligation to meet the schedule constraints in the prime agreement, and the right to extensions of time and change orders to the extent the prime contractor obtains the same.
Read the court decisionRead the full story...Reprinted courtesy of
Joseph M. Leone, Drewry Simmons Vornehm, LLP Mr. Leone may be contacted at