Court Says KBR Construction Costs in Iraq were Unreasonable
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFMike Bosse of Bernstein Shur, analyzed a case involving Kellogg Brown and Root Services Inc. (KBR) and the U.S. Army for services that KBR provided during Operation Iraqi Freedom, according to JDSupra Business Advisor: “The court case involved KBR’s construction of dining facility services near Mosul, Iraq under a cost-plus fee arrangement. Under this contractual arrangement, all allowable costs were reimbursed by the government plus the contractor was paid an additional fee.”
KBR first started on a prefabricated metal dining hall that would serve 2,500 people, but part way into building they were told to stop construction and to instead start on a new reinforced concrete building that would serve almost three times as many people.
“After construction was finished, a defense contract auditing agency suspended some of the payments to KBR and instead of the $12.5 million it expected to receive, KBR was paid only $6.7 million,” reported JDSupra Business Advisor. “After trial, the court concluded KBR did not meet its burden to show the costs it incurred were reasonable under the circumstances.”
Read the court decisionRead the full story...Reprinted courtesy of
China Bans Tallest Skyscrapers Following Safety Concerns
July 25, 2021 —
Bloomberg NewsChina is prohibiting construction of the tallest skyscrapers to ensure safety following mounting concerns over the quality of some projects.
The outright ban covers buildings that are taller than 500 meters (1,640 feet), the National Development and Reform Commission said in a notice Tuesday. Local authorities will also need to strictly limit building of towers that are more than 250 meters tall.
The top economic planner cited quality problems and safety hazards in some developments stemming from loose oversight. A 72-story tower in Shenzhen was closed in May for checks following reports of unexplained wobbling, feeding concern about the stability of one of the technology hub’s tallest buildings.
Construction of buildings exceeding 100 meters should strictly match the scale of the city where they will be located, along with its fire rescue capability, the commission said.
“It’s primarily for safety,” said Qiao Shitong, an associate law professor at the University of Hong Kong who studies property and urban law. Extremely tall buildings “are more like signature projects for mayors and not necessarily efficient.”
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Traub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp Obtain Summary Judgment in Favor of Residential Property Owners
December 13, 2022 —
Gregory S. Pennington & Emily A. Velcamp - Traub LiebermanTraub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp obtained summary judgment in favor of their clients, owners of a residential property [the “Owners” or “Defendants”] used as a short-term rental in Beach Haven, New Jersey. Plaintiff alleged injuries resulting from a fall into an open water meter pit, located in the public sidewalk abutting the Owners’ property during the time within which the property was rented to plaintiff and his family. According to plaintiff, defendants breached their duty owed to him, relying on a Borough of Beach Haven Ordinance, thereby allowing the water meter pit to be raised in an unsafe manner, which resulted in plaintiff’s fall and subsequent injuries.
After the Court denied defendants’ initial Motion for Summary Judgment on the grounds that issues of material fact existed regarding defendants’ duty and the alleged breach of that duty, a Motion for Reconsideration was filed. Mr. Pennington and Ms. Velcamp argued that their clients, as residential landowners, owed no duty of care to plaintiff for the raised condition of the water meter pit lid, located in the abutting sidewalk, as they did not cause or contribute to the alleged condition. Defendants further argued that even if a duty of care existed, no breach occurred given the lack of notice to defendants, either actual or constructive. Plaintiff attempted to argue that defendants had constructive notice of the lid’s raised condition, relying on his expert report and the fact that defendants had 3.5 months from the date the property was purchased, to the date of the subject accident to discover the lid’s raised condition. Mr. Pennington and Ms. Velcamp successfully argued that despite plaintiff’s allegations and the findings contained in plaintiff’s expert report, authored 2 months after the alleged accident, there was still no credible, material evidence to say how long the water meter pit lid was in that raised condition to allow defendants a reasonable time to discover it, remedy it, or report it to the Borough.
Reprinted courtesy of
Gregory S. Pennington, Traub Lieberman and
Emily A. Velcamp, Traub Lieberman
Mr. Pennington may be contacted at gpennington@tlsslaw.com
Ms. Velcamp may be contacted at evelcamp@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Planes, Trains and Prevailing Wages. Ok, No Planes, But Trains and Prevailing Wages Yes
October 25, 2021 —
Garret Murai - California Construction Law BlogThe California Supreme Court doesn’t often delve into construction-related issues, but this year we’ve got two cases, both related to the payment of prevailing wages on California public works projects.
The first, Mendoza v. Fonseca McElroy Grinding Co., Inc. (2021) 11 Cal.5th 1118 which we discussed in our last blog post, concerned whether mobilization work qualifies as a “public work” and in turn requires the payment of prevailing wages. On the same day that the Supreme Court issued its decision in Mendoza, it issued a decision in Busker v. Wabtec Corporation, et al. , Case No. S251135 (August 16, 2021). This is the equivalent of being struck by lightning twice.
In Busker, the California Supreme Court considered whether on a public transportation project “field work” (e.g., building and outfitting radio towers on land adjacent to train tracks) and “onboard work” (e.g., installing electronic components on train cars and locomotives”) requires the payment of prevailing wage.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Big Policyholder Win in Michigan
January 05, 2017 —
Jeremiah M. Welch – Saxe Doernberger & Vita, P.C.Jeremiah Welch and
Michael Barrese recently had a big win in front of the Michigan Court of Appeals.
The case (Skanska-Schweitzer v. Farm Bureau General Insurance Company of Michigan) involved Skanska’s claim for defense and indemnity from Farm Bureau Ins. Co. of Michigan for an injury to an elementary school student arising out of the removal of playground equipment by a landscaping company, Horrocks. Farm Bureau denied coverage because it claimed that the work was not part of Horrocks’ contract with the project owner and therefore Skanska, the construction manager, did not qualify as an additional insured on the policy.
SDV argued that the AI endorsement did not specify that Horrocks’ work be performed as part of its contract with the owner; it only required that the work be performed “for Skanska.”
Read the court decisionRead the full story...Reprinted courtesy of
Jeremiah M. Welch, Saxe Doernberger & Vita, P.C.Mr. Welch may be contacted at
jmw@sdvlaw.com
OSHA Extends Temporary Fall Protection Rules
March 01, 2012 —
CDJ STAFFOSHA announced that its current rules on fall protection for residential construction will remain in place until September 15, 2012. The current measures became effective in June 2011. Under the new rules, falls must be prevented by fall protection measures unless the measures can be shown to be unfeasible or even hazardous.
Under the extension of the temporary enforcement measures, contractors who ask for compliance assistance with OSHA are given top priority and penalties can be reduced. OSHA has conducted more than 1,000 outreach sessions on the new rules.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Problems May Delay Bay Bridge
May 10, 2013 —
CDJ STAFFFaulty bolts could lead to a delay in the opening of the Bay Bridge. Caltrans noticed problems with bolts and found that the bolts had cracked. Of the 98 bolts already tightened, 30 have failed. According to the San Francisco Chronicle, workers will be tightening all 288 bolts and then testing them. According to Tony Anziano, Caltrans’s toll bridge program manager, repairs could take one or two months. Mr. Anziano noted that the manufacturer might be responsible for part of the expense, but that the budget for the bridge also has funds set aside for unanticipated repairs.
The bolts were supplied by Dyson, an Ohio company, but it was clear whether Dyson manufactured the bolts or simply marketed them.
Read the court decisionRead the full story...Reprinted courtesy of
Newmeyer Dillion Attorneys Named to 2022 Southern California Rising Stars List
June 13, 2022 —
Newmeyer DillionNEWPORT BEACH, Calif. – June 8, 2022 – Prominent business and real estate law firm Newmeyer Dillion is pleased to announce that partner
Jason Moberly Caruso and associate
Jessica Garland Daley have been selected to the 2022 Southern California Rising Stars list by Super Lawyers. Each year, no more than 2.5 percent of the lawyers in the state are selected to receive this honor. The attorneys will be recognized in the June 2022 issues of Super Lawyers Magazine, Los Angeles Magazine and Orange Coast Magazine.
Jason Moberly Caruso is a partner in the Newport Beach office. Jason's practice focuses on land use, "contaminated sites" environmental legal work, complex litigation, and appellate matters. This is the fifth consecutive year Jason has been honored.
Jessica Garland Daley is an associate in the Newport Beach office. Jessica's practice focuses on litigation in the areas of employment law and construction law. This is the first year Jessica has been selected.
About Newmeyer Dillion
For over 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that achieve client objectives in diverse industries. With over 60 attorneys working as a cohesive team to represent clients in all aspects of business, employment, real estate, environmental/land use, privacy & data security and insurance law, Newmeyer Dillion delivers holistic and integrated legal services tailored to propel each client's operations, growth, and profits. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of