Richard H. Glucksman, Esq. & Brian D. Kahn, Esq. – Chapman Glucksman Dean & Roeb BulletinINTRODUCTION
The current COVID-19 health crisis has greatly impacted nearly every aspect of our business and personal lives. The constant flow of rapidly evolving, and often contradictory information creates its own challenges for those who are responsible for ensuring compliance with relevant regulations and best practices while still moving forward with their business and family activities.
This bulletin differs from most Chapman, Glucksman, Dean & Roeb bulletins in that it does not highlight a recent case, statute or a single development, but rather acts as a resource and “links” to provide you with needed information and to simplify your search for critical information during this unusual and challenging time.
CIVIL LITIGATION: CLOSURES AND RESTRICTIONS
The State and Federal Court systems in California have drastically reduced their operations. The Governor issued Executive Order N-38-20, this suspends certain limitations on the Chief Justice’s authority, making it possible for orders to be issued adapting the Court’s operations to address the COVID-19 health crisis. As of this time, the most recent statewide order from the Chief Justice is the March 30, 2020 Order which allows Courts to utilize remote technology when possible. The March 30, 2020 Order also clarifies a prior Order suspending all trials for 60 days. As many of you are aware, civil trials in California must commence within five years of the initiation of the action, this is commonly referred to as the “five year rule”. While the five year time period was initially extended by the Chief Justice for 60 days, the Judicial Council subsequently adopted a series of Emergency Rules, including one which extends this to six months for all civil actions filed on or before April 6, 2020. The Judicial Council also adopted rules tolling the statutes of limitation for civil causes of action are tolled from April 6, 2020 to 90 days after the state of emergency has ended.
In addition to the statewide orders and rules, counties have enacted their own rules. Los Angeles Superior Court, for instance, has closed some locations while others remain open on a limited basis. On March 17, 2020 an Order was issued limiting the Court to “essential functions” through April 16, 2020. However, on April 15, 2020, a further Order extended the closure through May 12, 2020. While truly urgent Ex Partes may go forward, all regularly set hearings will be continued until after June 22, 2020. Trials will begin after June 22, 2020 with non-priority trials anticipated to start in later August or September. Notably, any deadlines imposed by current trial or hearing dates still stand until the specific dates are continued.
As with other aspects of the COVID-19 health crisis, the impact upon Civil Litigation continues to evolve, for the most up to date information we include the following links to the California Courts. The first page includes links to all the State and County Orders, the second page is for the Judicial Council Rules.
Links:
https://newsroom.courts.ca.gov/news/court-emergency-orders-6794321
https://newsroom.courts.ca.gov/news/judicial-branch-emergency-actions-criminal-civil-and-juvenile-justice
STATE AND LOCAL STAY AT HOME ORDERS
The State of California declared a state of emergency on March 4, 2020. On March 13, 2020 the President declared a national state of emergency. On March 19, 2020 Governor Newsom issued Executive Order N-33-20, also known as the “Stay at Home” order. This orders all Californian’s to stay at home, unless they are part of an essential businesses are exempt which generally includes construction and insurance. Generally, Californians are allowed to run essential errands, but they are not to congregate with those outside of their household.
In addition to the State, many cities and counties have enacted additional orders regarding whether certain types of businesses can remain open, use of parks, trails and other public amenities as well as what type of protective measures must be adhered to such as covering your face in public. As with Civil Litigation, the State and Local Government regulations continue to evolve. A link to the State’s COVID-19 page is below and we also encourage you to check your local City and County sites for additional information.
https://covid19.ca.gov/
BUSINESS AND FINANCIAL GUIDELINES
The impact of COVID-19 is unprecedented. While “essential businesses” may remain open for customers, steps must be taken to protect the health of both employees and customers. There are both State and, in many instances, Local Government regulations addressing these precautions. In addition to taking safety measures to protect the health of all involved, there are a multitude of financial concerns to be addressed. While most people have already heard about the moratorium on residential and commercial evictions, this does little to address how property owners will receive funds to pay their financial obligations, how tenants can pay their other obligations, how either can make payroll and most importantly, how employees who can no longer work due to their “non-essential” business being closed can put food on their tables.
The Coronavirus Aid, Relief, and Economic Security Act (the “CARES” act) may provide financial relief for many business by means of loans, some of which may be forgivable, and tax credits. The CARES act also modifies the Family Medical Leave Act (“FMLA”) to provide paid leave for those who cannot work due to COVID-19 as well as other benefits. The IRS has extended the deadline to file and pay taxes to July 15, 2020. Additionally, there are other Federal and State benefits which may be available for those whose jobs are impacted.
The financial impacts of COVID-19 are far reaching and continue to evolve. The Department of Insurance ordered insurance companies to return premiums for at least the months of March and April. This applies to certain lines of insurance where the risk of loss has fallen substantially. However, business interruption, environmental and pollution claims have increased exponentially. While most such policies require some physical damage in order to trigger an occurrence, there has been some discussion of legislation deeming the COVID-19 pandemic to fulfill the physical damage requirement.
If your business has been closed or impacted by COVID-19 we encourage you to review your insurance policies and key contracts to ascertain what your rights and obligations are as well as whether you may have any coverage for your losses. Just as importantly, speak with your business partners including vendors, customers and employees to ascertain their capabilities and willingness to work through this crisis.
US Department of Labor OSHA Guidelines:
https://www.osha.gov/SLTC/covid-19/
California Labor & Workforce Development Agency Resource Page:
https://www.labor.ca.gov/coronavirus2019/
California Employment Development Department:
https://www.edd.ca.gov/about_edd/coronavirus-2019.htm
CONSTRUCTION GUIDELINES
Many of our clients are involved in the construction industry. Construction has been deemed an essential activity and is exempt from many of the “stay at home” orders but certain protections and regulations still apply. In addition to the general workplace guidelines discussed above certain jurisdictions are providing guidance as to how to provide a safe construction site workplace. We have included a link the Los Angeles Department Building and Safety guidelines below.
However, in some instances work on a project may be delayed or may not be able to progress due to the project owner stopping work or the inability of subcontractors or suppliers to continue as originally intended. In this case one should review their contracts to see what justifies delay and inability to perform by either party and the impact thereof. Contracts should also be evaluated to ascertain whether the costs associated with compliance with the new COVID-19 regulations are a recoverable cost under the contract. As with the general business discussion above, contractors should review all available insurance, including builder’s risk to ascertain the existence of possible coverage.
LA DBS guidelines:
https://ladbs.org/docs/default-source/publications/misc-publications/construction-site-guidance.pdf
SUMMARY
The COVID-19 health crisis has had and, for the foreseeable future, will have a broad and severe impact on our society. The variety of evolving regulations on the Federal, State and Local Government levels make it challenging to comply, especially for businesses in operation. There are also a variety of resources available to help ensure compliance with these regulations as well as the financial and physical viability of our communities’ companies and employees. Please do not hesitate to contact us if you need any assistance in navigating these rules and resources.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean & Roeb and
Brian D. Kahn, Chapman Glucksman Dean & Roeb
Mr. Glucksman may be contacted at rglucksman@cgdrlaw.com
Mr. Kahn may be contacted at bkahn@cgdrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Lennar Profit Tops Estimates as Home Prices Increase
March 26, 2014 —
John Gittelsohn – BloombergLennar Corp. (LEN), the biggest U.S. homebuilder by market value, reported a fiscal first-quarter profit that beat analysts’ estimates as the company sold more homes at increased prices.
Net income climbed to $78.1 million, or 35 cents a share, in the three months through February, from $57.5 million, or 26 cents, a year earlier, the Miami-based company said in a statement today. Analysts expected earnings of 28 cents a share, the average of 17 estimates compiled by Bloomberg.
Publicly traded builders have been increasing prices to take advantage of a tight supply of new and existing homes while using their economies of scale to reduce costs and widen profit margins. Lennar’s profit, deliveries and orders grew even as inclement weather threatened home sales in much of the U.S. during the quarter, according to Drew Reading, a Bloomberg Industries analyst.
“Lennar followed KB Home (KBH) in reporting order trends indicating a strong start to the spring selling season,” Reading said in a note after the earnings were released.
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelson may be contacted at
johngitt@bloomberg.net
Hurdles with Triggering a Subcontractor Performance Bond
April 05, 2017 —
David Adelstein – Florida Construction Legal UpdatesThere have been a couple of decisions as of late, particularly in federal court, that have gone in favor of a performance bond surety and against a general contractor’s claim against a subcontractor’s performance bond. These decisions have been so unfavorable that they may be swaying certain internal decisions to move to subcontractor default insurance with, perhaps, subcontractors that pose less risk. From the general contractor’s perspective, if they have to stop the management of the job and progress to jump through hoops to trigger the performance bond’s obligations, rightfully or wrongfully, the bond may not provide them the value they need. Performance bonds are an appropriate product in many instances, but there should be more consistency regarding the actual trigger of a subcontractor’s performance bond obligations. Project teams need to absolutely understand what efforts they need to take, and how they need to take such efforts, in order to properly trigger a performance bond’s obligations. This is a must (and I have presented many seminars on this very issue). Or, the general contractor should move away from the traditional AIA /standard performance bond form, which is the direction I always go when I am involved in the drafting of a performance bond.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Pushing the Edge: Crews Carve Dam Out of Remote Turkish Mountains
July 04, 2023 —
Pam McFarland - Engineering News-RecordRugged Construction | Part Two of an ENR Series
On a cold, gray day in late March, the mountains on the drive to the Yusufeli hydroelectric dam project site in northeastern Turkey seem ominous.
With the highest of these rising more than 3,000 meters above sea level—some of them snow-capped—the jagged rock formations look stark and imposing, the type only a trained professional should attempt to cross.
Reprinted courtesy of
Pam McFarland, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Travelers’ 3rd Circ. Win Curbs Insurers’ Asbestos Exposure
May 03, 2017 —
Gregory D. Podolak - Saxe Doernberger & Vita, P.C.In breaking news this week, LAW360.com posted that the Third Circuit ruled Friday that “a common exclusion found in a Travelers policy bars coverage for claims arising out of asbestos in any form, limiting insurers’ potential exposure to asbestos injury claims by precluding policyholders from arguing that the exclusionary language is ambiguous and doesn’t extend to products containing the carcinogen.”
In its detailed analysis of the decision, LAW360 turned to Greg Podolak for his analysis.
Gregory D. Podolak, managing partner of Saxe Doernberger & Vita PC’s Southeast office, said the ruling is a cautionary tale that should galvanize policyholders and their insurance brokers to take a closer look at policies to delete or curtail broad “arising out of” language in exclusions. Otherwise, insureds could find themselves without any coverage for claims even remotely related to a certain product, he said.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C.Mr. Podolak may be contacted at
gdp@sdvlaw.com
Construction Worker Dies after Building Collapse
November 18, 2011 —
CDJ STAFFA Bronx construction worker died when the pillars gave way in the basement where he was working. The two-story commercial building collapsed, burying Mr. Kebbeh under about six feet of rubble. The New York Times reports that firefighters dug him out with their bare hands. Mr. Kebbeh was taken to Jacobi Medical Center where he died. Two other construction workers escaped unharmed.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Will Claims By Contractors on Big Design-Build Projects Ever End?
February 27, 2023 —
Richard Korman - Engineering News-RecordIn the annals of construction disputes, it is a blip, not a blast.
After a Flatiron Construction-Zachry Group joint venture struck out on most of its arbitrated claims against engineering firm partners on the I-85/385 design-build interchange project in Greenville, S.C., and had others dismissed in court, the contractors had one more source from which to try to cover unexpected project costs: a contractor protective professional policy. Flatiron-Zachry filed a lawsuit last October in San Antonio federal court to try to force payment from Steadfast, a subsidiary of Zurich American Insurance Co.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Spearin Doctrine as an Affirmative Defense
November 30, 2016 —
David Adelstein – Florida Construction Legal UpdatesThe Spearin doctrine, referred to as the implied warranty of constructability doctrine, is oftentimes utilized as an affirmative defense by a contractor being sued for construction defects. Under the Spearin doctrine (recognized in the government contract setting), a contractor is NOT liable for defects in the plans and specifications furnished by the owner if the contractor constructs the project pursuant to the plans and specifications. This is because the owner impliedly warrants the constructability of the plans and specifications it furnishes to the contractor. Hence, the contractor should not be liable for defective construction caused by the owner furnishing defective plans and specifications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at