Huh? Action on Construction Lien “Relates Back” Despite Notice of Contest of Lien
May 01, 2023 —
David Adelstein - Florida Construction Legal UpdatesNot every case law you read makes sense. This sentiment goes to the uncertainty and grey area of certain legal issues. It is, what you call, “the nature of the beast.” You will read cases that make you say “HUH?!?” This is why you want to work with construction counsel to discuss procedures and pros / cons relative to construction liens.
An example of a case that makes you say “HUH” can be found in Woolems, Inc. v. Catalina Capstone Creations, Inc., 2023 WL 2777506 (Fla. 3d DCA 2023) dealing with a construction lien foreclosure dispute.
Here, a contractor filed a lawsuit against a subcontractor with a summons to show cause why the subcontractor’s construction lien should not be discharged. This is a specific complaint filed under
Florida Statute s. 713.21(4). This statute requires the lienor to essentially foreclose on its construction lien within 20 days after it was served with a “show cause” summons. The subcontractor filed its answer and counterclaim but did NOT assert a claim to foreclose its construction lien.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Delays and Suspension of the Work Under Fixed Price Government Contract
July 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting fact pattern and case decided by the Civilian Board of Contract Appeals dealing with (1) force majeure type events and epidemics (Covid-19); (2) suspension of the work; and (3) delays. These are three topics important to all contractors including federal contractors.
In Lusk Mechanical Contractors, Inc. v General Services Administration, 2024 WL 1953697, CBCA 7759 (CBCA 2024), a contractor entered into a fixed price contract with the government to repair, replace, and modernize site and building systems at a federal building. The contractor commenced work right before Covid-19. When Covid-19 hit, the government issued the contractor a two-week suspension of work notice on March 27, 2020. The suspension of work allowed off-site administrative work to continue but suspended on-site physical work. The government extended the suspension of work three more times. The contractor could resume work on the exterior on June 1, 2020, but was not permitted to resume work on the interior until July 20, 2020. On the same date that the contractor was able to commence interior work, it submitted a modification for delay caused by the suspension – 64 days for the time period the entire site shutdown, and 51 days for the interior work shutdown.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Quick Note: Remember to Timely Foreclose Lien Against Lien Transfer Bond
July 09, 2019 —
David Adelstein - Florida Construction Legal UpdatesWhen a construction lien is transferred to a lien transfer bond pursuant to Florida Statute s. 713.24, instead of foreclosing the lien against the real property, you are foreclosing the lien against the lien transfer bond. This is not a bad deal and, oftentimes, is probably ideal. Remember, however, just because a construction lien was transferred to a lien transfer bond (pre-lawsuit) does not mean you get more time to file your lien foreclosure lawsuit. A lawsuit must still be filed within one year (short of that period being specifically shortened under operation of the law).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Insurer Entitled to Reimbursement of Defense Costs Under Unjust Enrichment Theory
May 04, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court for the district of Hawaii determined that the insurer could recover defense costs from an additional insured consistent with its Reservation of Rights letter under an unjust enrichment theory. Giga, Inc. v. Kiewit Infrastructure W. Co., 2020 U.S. Dist. LEXIS 10151 (D. Haw. Jan. 22, 2020).
This case was related fall-out from the Arthur case. Arthur v. Dept. of Hawaiian Homelands, 185 Haw. 149 (Haw. Ct. App. 2015). A prior post on the case is here.
In Arthur, a resident, Mona Arthur, of the Kalawahine Streamside Housing Development, was killed when she apparently slipped and fell from a hillside adjacent to the project. She was on the hillside tending to her garden there. At the bottom of the hill was a two foot fence in front of a drainage ditch, where Mona allegedly hit her head.
Mona's husband, William Arthur, sued a variety of defendants including the land owner, designer, developer, civil engineer and others. William alleged the defendants were negligent in the design, construction and supervision of the construction of the hillside area.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court Holds That Self-Insured Retentions Exhaust Vertically And Awards Insured Mandatory Prejudgment Interest in Stringfellow Site Coverage Dispute
October 19, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn State of California v. Continental Ins. Co. (No. E064518; filed 9/29/17), a California appeals court ruled that after Continental was ultimately held to pay its policy limits for remediation of the Stringfellow hazardous waste site, the insured State of California was entitled to mandatory prejudgment interest on the full amount dating back to 1998, when a federal district court had issued a judgment under F.R.C.P. 54 declaring the State liable under both the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and state law. To get there, the state appeals court held that vertical exhaustion applied to the attachment of Continental’s excess policies.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Following My Own Advice
October 21, 2015 —
Craig Martin – Construction Contractor AdvisorI often advise clients on the use of E-Verify and the importance of getting policies and in place to ensure compliance. This is particularly true for clients that do federal and state work. Now it’s my turn to follow my own advice.
I was recently appointed to represent the Nebraska Board of Engineers and Architects. As such, I am a contractor for the State of Nebraska. That means I have to use E-Verify.
Here is a refresher of “our” E-Verify obligations as a contractor for the State.
Nebraska adopted an E-Verify law in 2009. Nebraska statute section 4-114 requires all contractors that are awarded a contract by a state agency or political subdivision to register with ta federal immigration verification system. Although not explicit in the statute, the Department of Labor has indicated that the obligation to E-Verify applies only to new employees that will be working on the project.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
KY Mining Accident Not a Covered Occurrence Under Commercial General Liability Policy
December 04, 2018 —
Phillip A. Perez - Saxe Doernberger & Vita, P.C.In Am. Mining Ins. Co. v. Peters Farms, LLC,1 the Kentucky Supreme Court ruled that a mining error was not a covered accident under a commercial general liability insurance policy. The central issue was whether an insured mining company’s unauthorized removal of minerals from a neighboring property was an “occurrence” that unintentionally caused “property damage” as defined by the mining company’s commercial general liability policy (“CGL Policy”).
Read the court decisionRead the full story...Reprinted courtesy of
Phillip A. Perez, Saxe Doernberger & Vita, P.C.Mr. Perez may be contacted at
pap@sdvlaw.com
Michigan Finds Coverage for Subcontractor's Faulty Work
August 24, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Michigan Supreme Court held that under a CGL policy, an "accident" may include unintentional subcontractor work that damages the insured's work product. Skanska USA Building Inc. v. M.A.P. Mechanical Contractors, Inc., et al., 2020 Mich. LEXIS 1194 (Mich. June 29, 2020).
Skanska USA Building Inc. was the construction manager on a renovation project for a medical centre. The heatng and cooling portion of the project was subcontracted to M.A.P. Mechanical Contractors, Inc. (MAP). MAP installed a steam builder and piping for the heating system. The installation included several expansion joints. After completion, Skanska learned that MAP had installed some of the expansion joints backward. This caused significant damage to concrete, steel and the heating system. The medical center sent a demand letter to Skanska, who send a demand letter to MAP. Skanska did the repairs and replacement of the damaged property. Skanska then submitted a claim of $1.4 million for its work to Amerisure Insurance Company. The claim was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com