COVID-19 Business Interruption Lawsuits Begin: Iconic Oceana Grill in New Orleans Files Insurance Coverage Lawsuit
April 20, 2020 —
Jeffrey J. Vita & William S. Bennett - Saxe Doernberger & Vita, P.C.On Monday, the iconic New Orleans restaurant, Oceana Grill, filed the first Coronavirus-related business interruption insurance coverage lawsuit in a US jurisdiction. The declaratory judgment action styled Cajun Conti, LLC, et. al. d/b/a Oceana Grill v. Certain Underwriters at Lloyd’s, London was filed in Louisiana state court for the Parish of Orleans. As a direct result of the government-mandated closures and restrictions on public gatherings implemented by the City of New Orleans and State of Louisiana, Oceana Grill’s petition anticipates a significant loss of business income.
Based on allegations in the petition, there are several aspects of Oceana Grill’s policy that make this a good test case for business interruption coverage stemming from the Coronavirus. Although the specific policy language is not quoted in the petition, coverage provisions are categorically identified throughout.
As a preliminary matter, the policy at issue appears to be written on an “all risks” basis, meaning the insuring agreement of the policy would likely be triggered generally by all risks of “physical loss or damage” unless specifically excluded. This basis for coverage, which is common in property policies, is advantageous to policyholders, as it limits the insured’s burden of proof to establishing that there was physical loss or damage while leaving the burden of applying any more specific exclusion to the insurance company.
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
William S. Bennett, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at jjv@sdvlaw.com
Mr. Bennett may be contacted at wsb@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Empire State Building Owners Sue Photographer for Topless Photo Shoot
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFUSA Today reports that the owners of New York’s Empire State Building are suing photographer Allen Henson for taking pictures of a topless woman on the sky scraper’s observation deck. “The owners claim Henson damaged the building's reputation as a safe, family-friendly attraction when he took photos of the model in August,” according to USA Today. Henson allegedly did not ask the owners for permission prior to the shoot.
Henson retorted that he took the photos when children were not present, and the pictures do not have any “commercial value; he just posted them on social media.”
Read the court decisionRead the full story...Reprinted courtesy of
“Positive Limiting Barriers” Are An Open and Obvious Condition, Relieving Owner of Duty to Warn
June 13, 2018 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law Blog On June 1, the U.S. Court of Appeals for the First Circuit decided the case of Potvin v. Speedway, Inc., a personal injury case subject to the laws of Massachusetts. In Massachusetts, environmental rules require the installation of “positive limiting barriers” at gasoline service stations to contain gasoline spills of up to 5 gallons. At a self-service station now owned by Speedway, Inc., the plaintiff, a passenger in a car being serviced, exited the car but tripped on these barriers and was injured. She sued Speedway in state court, and the case was removed to federal court.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, Pillsbury Winthrop Shaw Pittman LLPMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
How Long does a Florida Condo Association Have to File a Construction Defect Claim?
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to a post on Orlando Sentinel’s HOA & Condo Blog, sponsored by the firm Becker & Poliakoff, generally a Condominium Association has “4 years from turnover of control of the Condominium Association from the developer” to file a lawsuit for construction defects. However, the association may have additional time to file.
If defects from the original construction were discovered after the 4 years have lapsed, “[a] condominium association may still pursue a claim for latent defects,” which is one that “is hidden, and not discovered despite the exercise of due diligence, for the period of 4 years from turnover.” The Statute of Repose in Florida is “10 years from the date the building received its original Certificate of Occupancy.”
Read the court decisionRead the full story...Reprinted courtesy of
DC Circuit Issues Two Important Clean Air Act and Administrative Law Decisions
December 16, 2019 —
Anthony B. Cavender - Gravel2GavelThe U.S. Court of Appeals or the District of Columbia has recently issued two important rulings on the Clean Air Act in particular and administrative law in general: California Communities Against Toxics, et al., v. EPA and Murray Energy Corporation v. EPA.
The Battle of the Memos: Seitz Makes Way for Wehrum
In the California Communities case, decided on August 20, 2019, the court held, in a 2 to 1 decision, that a petition to review a change in EPA policy announced in an agency memorandum which reversed an agency policy announced nearly 25 years ago in another agency memo must be rejected because the memo at issue was not a “final agency action” subject to the Administrative Procedure Act (APA). In 1995, the “Seitz Memo,” which interpreted Section 112 of the Clean Air Act and addresses the regulation and control of hazardous air pollutants from stationary sources, stated that once a source of toxic emissions is classified as “major,” the facility remains subject to regulation as a major source even if the facility makes changes to the facility to limit its potential to emit such toxics below the major source threshold. Then, in 2018 under a new administration, the “Wehrum Memorandum” was issued which reversed this policy and its interpretation of the law. (Both memos were issued without any kind of advance notice or opportunity to comment.) If a source takes steps to limit its potential to emit, then it may be regulated as an area source, and subject to less rigid regulation. The court majority held that the Wehrum Memo was not a final agency action and was not subject to judicial review when it was measured against both prongs of the “finality test” devised by the Supreme Court in the cases of Bennet v. Spear, 520 US 154 (1997) and US Army Corps of Engineers v. Hawkes, 136 S. Ct. 1807 (2016). While the memo undoubtedly represented the consummation of the agency’s decision-making process, the memo had no direct and appreciable legal consequences, and not therefore being a final action, the case must be dismissed. Judge Rogers filed a strong dissenting opinion.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
The Pandemic of Litigation Sure to Follow the Coronavirus
March 30, 2020 —
Aaron Lovaas - Newmeyer DillionAs the Coronavirus crisis persists, America’s richly diverse private business sector finds itself increasingly subject to unprecedented governmental orders and restrictions that were unheard of only a few weeks ago. While the various “shutdown,” “shelter in place,” and “non-essential business” orders all aim to protect the public health, there is no doubt that the wave of litigation to follow is already swelling.
Business interruption, civil authority, and cyber insurance coverages have already been widely discussed as issues certain to be litigated over the coming months and beyond. Additionally, breach of contract litigation is likely to spike as parties attempt to recoup their losses from canceled events, unfulfilled purchase commitments and other unmet obligations.
Moreover, regional and national businesses are now in the difficult position of managing their respective affairs to comply with a patchwork of executive orders that are inconsistent from state to state. And, as the pandemic wears on, many are questioning the authority under which some of these executive orders and emergency regulations are being issued in the first place. Indeed, constitutional challenges are almost certain to follow as the business community reframes the characterization of their losses into notions of unconstitutional takings of private property and governmental impairment of private contract rights.
Read the court decisionRead the full story...Reprinted courtesy of
Aaron Lovaas, Newmeyer DillionMr. Lovaas may be contacted at
aaron.lovaas@ndlf.com
BIM Meets Reality on the Construction Site
September 25, 2018 —
Aarni Heiskanen - AEC BusinessBIM models are mostly used by foremen on construction sites. But what if they could be made available for workers at the press of a button? This question was what the Finnish government-funded KIRA pilot project set out to answer. As a by-product, the project also produced augmented reality (AR) solutions for construction sites.
The research project was called ”Digitalization of a construction project based on role and location information” (RoPa). It was conducted by construction company Fira and engineering consultancy Sweco.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
1st District Joins 2nd District Court of Appeals and Holds that One-Year SOL Applies to Disgorgement Claims
June 14, 2021 —
Garret Murai - California Construction Law BlogWe’re beginning to see a trend.
This past year, the 2nd District Court of Appeals, in Eisenberg Village of the Los Angeles Jewish Home for the Aging v. Suffolk Construction Company, 53 Cal.App.5th 1201 (2020), held for the first time that a one (1) year statute of limitations period beginning upon substantial completion of a project applies to disgorgement claims under Business and Professions Code section 7031. In San Francisco CDC LLC v. Webcor Construction L.P., the 1st District Court of Appeals became the second Court of Appeals in the state to hold that a one (1) year statute of limitations beginning upon completion or cessation of work on a project applies to disgorgement claims under Business and Professions Code section 7031.
The San Francisco CDC LLC Case
The Defect Action
In September 2005, San Francisco CDC LLC entered into a $144 million construction contract with Webcor Construction, Inc. doing business as Webcor Builders to build the InterContinental Hotel in San Francisco, California.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at