Florida Accuses Pool Contractor of Violating Laws
June 28, 2013 —
CDJ STAFFOne customer said that after his pool was finished, he started having problems with the concrete and tiles. He’s still waiting for the $7,300 he was awarded at arbitration. Others have complained that Nationwide Pools dug up their back yards and didn’t finish the work. Construction defects were not repaired, despite promises. And even after the company stopped doing any work anywhere, they continued to charge their customers “progress payments.”
The State of Florida has stepped into this, seeking restitution for homeowners who were charged for partially built or defective pools, and preventing the company officials from ever working in the pool construction industry. According to the suit, customers who complained about delays were told “a series of lies and misrepresentations about ‘supply shortages’ and ‘damaged items’ in order to string them along.”
Read the court decisionRead the full story...Reprinted courtesy of
Vallagio v. Metropolitan Homes: The Colorado Court of Appeals’ Decision Protecting a Declarant’s Right to Arbitration in Construction Defect Cases
May 20, 2015 —
David M. McLain – Colorado Construction LitigationOn May 7th, the Colorado Court of Appeals issued its much anticipated ruling in Vallagio at Inverness Residential Condominium Association, Inc. v. Metropolitan Homes, Inc., et al., 2015COA65 (Colo. App. May 7, 2015). By way of background, the Vallagio at Inverness Residential Condominiums were developed by Metro Inverness, LLC, which also served as the declarant for its homeowners association. Metropolitan Homes was Metro Inverness’ manager and the general contractor on the project. Greg Krause and Peter Kudla served as declarant-appointed members of the Association’s board during the period of declarant control.
When it set up the Association, Metro Inverness included within the Association’s declaration a mandatory arbitration provision specifically for construction defect claims. This provision stated that it “shall not ever be amended without the written consent of Declarant and without regard to whether Declarant owns any portion of the Real Estate at the time of the amendment.”
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Construction Client Advisory: The Power of the Bonded Stop Notice Extends to Expended Construction Funds
February 07, 2014 —
Steven M. Cvitanovic - Haight Brown & Bonesteel LLPCFO to CEO: “I have bad news, the developer on our biggest project has run out of money.” Frightening words for sure, but contractors should not overlook the bonded stop notice in situations where the construction lender seemingly has expended all construction funds. The recent case of Brewer Corporation v. Point Center Financial, Inc. 2014 WL 346636 illustrates this point.
Contractors have two options at their disposal to secure payment on private works of improvement. The first is the mechanics lien. However, construction loan trust deeds are normally recorded prior to the commencement of construction and therefore have priority over mechanics liens. Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803, 827. Enter the bonded stop notice. The bonded stop notice requires the lender to withhold unexpended funds and, if it fails to do so, it is personally liable to the claimant for the full amount of the claim. But the stop notice also has the power of “priority” over any assignment of construction loan funds, whether before or after a stop notice is served. Civil Code § 3166, now Civil Code § 8544.
Read the court decisionRead the full story...Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLPMr. Cvitanovic may be contacted at
scvitanovic@hbblaw.com
Virginia Allows Condominium Association’s Insurer to Subrogate Against a Condominium Tenant
August 10, 2020 —
Gus Sara - The Subrogation StrategistIn Erie Insurance Exchange v. Alba, Rec. No. 190389, 2020 Va. LEXIS 53, the Supreme Court of Virginia considered whether the trial court erred in finding that a condominium association’s property insurance provider waived its right of subrogation against a tenant of an individual unit owner. The Supreme Court reversed the lower court’s decision, holding that the insurance policy only named unit owners as additional insureds, not tenants, and thus the subrogation waiver in the insurance policy did not apply to tenants. The court also found that the condominium association’s governing documents provided no protections to the unit owner’s tenant because the tenant was not a party to those documents. This case establishes that, in Virginia, a condominium association’s insurance carrier can subrogate against a unit owner’s tenant where the tenant is not identified as an additional insured on the policy.
The Alba case involved a fire at a condominium building originating in a unit occupied by Naomi Alba (Alba), who leased the condominium under a rental agreement with the unit owner, John Sailsman (Sailsman). The agreement explicitly held Alba responsible for her conduct and the conduct of her guests. An addendum to the lease stated that Sailsman’s property insurance only applied to the “dwelling itself” and that Alba was required to purchase renters insurance to protect her personal property. Along with the rental agreement, Alba received the condominium association’s Rules & Regulations, Declarations and Bylaws.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Spa High-Rise Residents Frustrated by Construction Defects
February 07, 2013 —
CDJ STAFFIs this part of the spa treatment? A couple has sued over problems at Miraval Living, a luxury high-rise on the East Side of Manhattan. There was supposed to be ballroom dancing, culinary classes, and yoga. Anthony Argyrides's lawsuit notes that those didn't materialize. What they did get, he claims, was faulty plumbing, crumbling fixtures, and defective floor tiles. Mr. Argyrides claims that his front door "spontaneously fell of its hinges and nearly hit FiOS installation workers."
Meanwhile, building management has ended their agreement with Miraval and need to find someone else to operate the building's spa. Argyrides and his fellow building residents might need something more than a few deep calming breaths. He's suing for $5.5 million.
Read the court decisionRead the full story...Reprinted courtesy of
One Way Arbitration Provisions are Enforceable in Virginia
October 07, 2019 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, I’ve discussed arbitration clauses (pros and cons) as well as the fact that in our fair Commonwealth, contracts are enforced as written (for better or worse). A case out of the Eastern District of Virginia takes both of these observations and uses them to make it’s decision.
In United States ex rel. Harbor Constr. Co. v. T.H.R. Enters., the Newport News Division of the Eastern District of Virginia federal court considered the following provision and it’s enforceability:
At CONTRACTOR’s sole election, any and all disputes arising in any way or related in any way or manner to this Agreement may be decided by mediation, arbitration or other alternative dispute resolution proceedings as chosen by CONTRACTOR…. The remedy shall be SUBCONTRACTOR’s sole and exclusive remedy in lieu of any claim against CONTRACTOR’s bonding company pursuant to the terms of any bond or any other procedure or law, regardless of the outcome of the claim. The parties further agree that all disputes under this Subcontract shall be determined and interpreted pursuant to the laws of the Commonwealth of Virginia….
This provision was the crux of the argument made by T. H. R., the Defendant, in making a motion to dismiss or stay the lawsuit for payment filed by Harbor Construction. As background, Harbor Construction contracted with T. H. R. to perform work at Langley Air Force Base. Alleging non-payment of approximately $250,000.00, Harbor filed a complaint with three counts, one under the Federal Miller Act, one for breach of contract, and a third for unjust enrichment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Narrow Promissory Estoppel Exception to Create Insurance Coverage
August 07, 2022 —
David Adelstein - Florida Construction Legal UpdatesThere is an affirmative claim known as promissory estoppel. (Whereas equitable estoppel is used an affirmative defense, promissory estoppel is used as an affirmative claim.)
To prove promissory estoppel, a plaintiff must plead and prove the following three elements: “(1) a representation as to a material fact that is contrary to a later-asserted position; (2) a reasonable reliance on that representation; and (3) a change in position detrimental to the party claiming estoppel caused by the representation and reliance thereon.” Romo v. Amedex Ins. Co., 930 So.2d 643, 650 (Fla. 3d DCA 2006) (citation and quotation omitted). Stated differently: “A party will be estopped from denying liability under the principle of promissory estoppel when the party makes ‘[a] promise which the promisor should reasonably expect to induce action or forbearance of a definite and substantial character on the part of the promisee and which does induce such action or forbearance…[and] injustice can be avoided only by enforcement of the promise.’” Criterion Leasing Group v. Gulf Coast Plastering & Drywall, 582 So.2d 799, 800 (Fla. 1st DCA 1991).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
County Sovereign Immunity Invokes Change-Order Ordinance
December 20, 2017 —
Lizbeth Dison - AHC Contruction Law BlogThe recent case of Fulton County v. Soco Contracting Company, Inc. addresses two very interesting questions for local government attorneys. First, can a county ordinance bolster a defense of sovereign immunity against a contractor’s claims? Second, can a county waive sovereign immunity by failing to respond to Requests for Admission?
Facts:
County hired Contractor to construct a facility near the airport. The contract provided that change orders must satisfy a county ordinance, which required approval by the Board of Commissioners. But in emergency situations, the County Manager could approve change orders, as long as the contractor executes a proposed modification and the purchasing agent approves it.
The project suffered substantial delays, which Contractor attributed to weather, design delays, delays by the County in providing decisions on changes, and delays in obtaining permits during the federal government’s shutdown. As a result of these issues, Contractor comes County changed the scope of the contract. Contractor asserted claims against County for the delays and the changes to the work. The appellate opinion addresses the change order claims.
Read the court decisionRead the full story...Reprinted courtesy of
Lizbeth Dison, Autry Hall & Cook, LLP