Texas EIFS Case May Have Future Implications for Construction Defects
October 02, 2013 —
CDJ STAFFLennar Homes addressed a problem with EIFS in homes built in Texas in the 1990s by replacing every roof they had built. Some of those homes had problems with leaks, rotting, or termites, but other roofs hadn’t suffered any problems. Lennar’s insurers initially refused coverage. Lennar managed to settle with all but one, Markel American Insurance.
Their dispute formed the case Lennar Corp. v. Markel American Insurance Co. This was first tried before a jury and eventually appealed to the Texas Supreme Court. Brian S. Martin of Thompson Coe Cousins & Irons LLP discusses this case at Insurance Journal.
Markel’s claim was that under the policy language, Lennar could not make voluntary payments without getting Markel’s consent, which they did not. But the Texas Supreme Court disagreed, determining that Lennar took, as Mr. Martin notes, “a reasonable approach to a serious problem.”
Markel also made the claim that the whole amount of the damages was not covered by the policy, as they did not view the policy as covering the cost of determining the extent of the damage. The Court disagreed, noting that “under no reasonable construction of the phrase can the cost of finding EIFS property damage in order to repair it not to be considered ‘because of the damage.’”
Mr. Martin concludes by calling the Texas Supreme Court decision “a frontal assault on several critical provisions of liability policies that will assuredly lead to further litigation.” He also notes that the decision “may indicate a shift in the Court’s approach in insurance cases to a more result-oriented jurisprudence.”
Read the court decisionRead the full story...Reprinted courtesy of
Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Get Construction Defects in Writing
December 11, 2013 —
CDJ STAFFSometimes, even if a developer is willing to make a repair, sometimes the repair doesn’t get to the actual problem, according to Nicholas D. Cowie of Cowie & Mott, writing on his blog. He notes that “getting it ‘right’ the first time is important and written documentation is key.” He gives the example of “when a developer agrees to informally repair a window or roof leak, the ‘repair,’ as far as the developer is concerned, may consist merely of sending out a worker with a caulk gun to seal gaps that should have been protected with a solid flashing material during the original installation.”
As a better course, he says that homeowner associations should “request a written description of the proposed repair” in order that it can be evaluated. This also allows follow-up to determine if the agreed-upon repair was done properly. And, although some homeowners associations would rather not have the original subcontractor repair their own work, here warranties often come into play.
Read the court decisionRead the full story...Reprinted courtesy of
Green Construction Trends Contractors Can Expect in 2019
May 01, 2019 —
Emily Folk - Construction ExecutiveThe construction industry has come a long way since it was started building homes out of logs and sticks. Modern homes and buildings are marvels of engineering filled with wood, concrete and steel—much of which could be recycled if the building were ever torn down. Green construction is a growing field that will continue to expand in the coming year. What green construction trends can we expect to see in the coming year?
Augmented and Virtual Reality
Augmented reality (AR) is growing more popular every year for games and entertainment, but it also has some applications in green construction. AR and virtual reality (VR) programs, either through a headset or on a smartphone, can be used to improve collaboration between companies, allowing each company to see a virtual overlay of their stage of the project.
For green and eco-friendly construction, it can be used to show how a finished product will look on undeveloped land, making it easier to judge the ecological impact of the project. The use of AR and VR in green construction is still in its infancy, though we will likely start to see more of it in 2019.
Reprinted courtesy of
Emily Folk, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Examination of the Product Does Not Stop a Pennsylvania Court From Applying the Malfunction Theory
June 28, 2021 —
Gus Sara - The Subrogation StrategistPennsylvania recognizes the malfunction theory in product liability cases. This theory allows a plaintiff to circumstantially prove that a product is defective by showing evidence of a malfunction and eliminating abnormal use or reasonable, secondary causes for the malfunction. The malfunction theory is available to plaintiffs as an alternative to proving a traditional strict product liability case in those circumstances where direct evidence of a product defect is not found. In Pa. Nat’l Mut. Cas. Ins. Co. v. Sam’s East, Inc., 727 MDA 2020, 2021 Pa. Super. Unpub. LEXIS 752, the Superior Court of Pennsylvania (Superior Court) considered whether the plaintiffs could avail themselves to the malfunction theory if the plaintiffs’ expert was able to examine the product.
The Sam’s East, Inc. case arose from a February 2015 fire at the residence of Gerald and Michelle Thompson (the Thompsons). The fire caused injuries to the Thompsons, as well as significant damage to their residence. Pennsylvania National Mutual Casualty Insurance Company (Insurer) provided homeowners insurance coverage for the property and made payments to the Thompsons as a result of the fire. Insurer retained a fire investigator to investigate the origin and cause of the fire. The fire investigator determined that the fire originated at an electric space heater that was purchased from defendant Sam’s East, Inc. (Sam’s East) in December 2011. Insurer and the Thompsons filed a lawsuit against Sam’s East in early 2017 for their respective damages.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Lost Productivity or Inefficiency Claim Can Be Challenging to Prove
May 02, 2022 —
David Adelstein - Florida Construction Legal UpdatesOne of the most challenging claims to prove is a lost productivity or inefficiency claim. There is an alluring appeal to these claims because there are oftentimes intriguing facts and high damages. But the allure of the presentation of the claim does not compensate for the actual burden of proof in proving the lost productivity or inefficiency claim, which will require an expert. And they really are challenging to prove.
Don’t take it from me. A recent Federal Claims Court opinion, Nova Group/Tutor-Saliba v. U.S., 2022 WL 815826, (Fed.Cl. 2022), that I also discussed in the preceding
article, exemplifies this point.
To determine lost productivity or inefficiency, the claimant’s expert tried three different methodologies.
First, the expert looked at industry standard lost productivity factors such as those promulgated by the Mechanical Contractor’s Association. However, the claimant was not a mechanical contractor and there is a bunch of subjectivity involved when using these factors. The expert decided not to use such industry standard factors correctly noting they provide value when you are looking at a potential impact prospectively, but once you incur actual damages and have real data, it is not an accurate measure.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
OSHA Again Pushes Back Record-Keeping Rule Deadline
November 30, 2017 —
Tom Ichniowski - Engineering News-RecordThe federal Occupational Safety and Health Administration is extending again—this time, by two weeks—the compliance date for its rule requiring companies to file annual electronic reports of workplace injuries and illnesses.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Ichniowski, ENRMr. Ichniowski may be contacted at
ichniowskit@enr.com
Homebuilders See Record Bearish Bets on Shaky Recovery
June 18, 2014 —
Callie Bost – BloombergSomeone thinks the housing rebound is built on shaky foundations.
A record 180,000 puts traded on the SPDR S&P Homebuilders (XHB) exchange-traded fund on June 11, according to data compiled by Bloomberg. The contract with the highest ownership pays off in the event of a 20 percent slump by December in the ETF tracking stocks from DR Horton Inc. to Williams-Sonoma Inc.
Prospects for rising interest rates and an uneven recovery in the housing market have hurt returns this year, sending the SPDR Homebuilders ETF down 3.3 percent. While economic data yesterday showed that builders broke ground on 1 million U.S. homes in May, permits, a proxy for future construction, decreased because of fewer applications for condominiums and apartment buildings.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Bost may be contacted at
cbost2@bloomberg.net