Developer Africa Israel Wins a Round in New York Condominium Battle
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFIn Manhattan, New York, a “Supreme Court judge partially granted a temporary restraining order to Africa Israel,” which “means the developer does not at this time have to cede control of the Downtown Condominium board to unit owners, following a February lawsuit against the developers by state Attorney General Eric Schneiderman,” according to The Real Deal.
The condominium battle began after Schneiderman filed suit against the developers, claiming that they did not fix construction defects, which in turn caused them to fail to obtain a certificate of occupancy, reported The Real Deal. The attorney general “also alleged that the pair misappropriated more than $9 million placed in an escrow account to finance those repairs.”
However, according to The Real Deal, Africa Israel has claimed not to be a sponsor of the building. “Attorney Aaron Abraham, representing both Africa Israel and the sponsor of 15 Broad, claimed …that Africa Israel, an Israeli development firm led by billionaire Lev Leviev, never signed any documents claiming to be a sponsor of the building, noting that the sponsor principals were Boymelgreen and Pinchas Cohen.”
Steve Sladkus, attorney for the condominium unit owners, told The Real Deal, “They partnered up with Boymelgreen — they need to deal with the fallout of that.”
Read the court decisionRead the full story...Reprinted courtesy of
Homebuyers Aren't Sweating the Fed
December 17, 2015 —
Rani Molla – BloombergGadflyHome prices are escalating, but the culprit isn't the Federal Reserve.
The Fed is expected to raise its benchmark rate for the first time since 2006, meaning mortgage rate hikes are likely to follow. Small mortgage-rate increases and, by extension, incrementally higher monthly mortgage payments, usually won't undermine sales because buyers aren't sensitive to small payment changes.
Mortgage rates, still at historic lows, have already baked in an expected rate increase of 25 basis points, according to PwC Real Estate Advisory Leader Mitch Roschelle. The National Association of Home Builders Chief Economist David Crowe agrees, adding that the housing market could even digest a cumulative 50 basis point hike by the end of 2016.
The real stress in the housing market is coming from somewhere else: labor shortages.
Read the court decisionRead the full story...Reprinted courtesy of
Rani Molla, BloombergGadfly
Meet the Forum's ADR Neutrals: LISA D. LOVE
March 19, 2024 —
Marissa L. Downs - The Dispute ResolverCompany: JAMS
Office Location: New York, NY
Email: llove@jamsadr.com
Website: https://www.jamsadr.com/love/
Law School: Georgetown University Law Center (J.D. 1984)
Types of ADR services offered: Arbitration, mediation, neutral evaluation and special master services
Affiliated ADR organizations: JAMS, Chartered Institute of Arbitrators, and CPR
Geographic area served: Domestic and International
Q: Describe the path you took to becoming an ADR neutral.
A: I started my legal career practicing law as a complex commercial transactions attorney in the corporate department of a major New York law firm for eleven years. After leaving the firm, I served as chief legal counsel to several municipalities and as co-founding partner of a boutique finance, infrastructure and real estate law firm.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case
February 10, 2012 —
CDJ STAFFThe Texas Court of Appeals ruled on December 21 in the case of Helm v Kingston, a construction defect case. After purchasing what was described as “an extremely well-built” two-bedroom townhouse, Mr. Kingston made complaints of construction defects. Greenway Development did not repair the defects to Kingston’s satisfaction, and he filed notice of suit. In his suit, he claimed that GDI and its president, John Helm, had committed fraud and negligent misrepresentation. Kingston claimed that Helm “fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of workmanship was atrocious.” Helms brought a counterclaim that Kingston’s suit was frivolous.
About four years after Kingston purchased the townhome, the suit proceeded to trial. The trial court determined that Helm was not “liable in his individual capacity,” but this was reversed at appeal.
A second trial was held ten years later on the question of whether Kingston’s unit was a townhome or an apartment. A jury found that Helm “engaged in a false, misleading or deceptive act or practice that Kingston relied on to his detriment.” Kingston was awarded $75,862.29 and an additional $95,000 in attorney fees by the jury. Helms made an unsuccessful appeal to the Appeals Court, after which Kingston was awarded an additional $10,000. Helms then made an unsuccessful appeal to the Texas Supreme Court, which lead to an additional $3,000 for Kingston. There was also a verdict of $48,770.09 in pre-judgment interest and “five percent post-judgment interest accruing from the date of the judgment until the time the judgment is paid. Helm appealed.
In his appeal, Helm raised seven issues, which the court reorganized into five Kingston raised one issue on cross-appeal.
Helms’ first claim was that Kingston “failed to satisfy the requirement of” Texas’s Residential Construction Liability Act and that by not filing under the RCLA, Kingston’s fraud and misrepresentation claims were preempted. Further Helms claimed that the RCLA limited Kingston’s damages. The court rejected this, as the RCLA deals with complaints made to a contractor and not only did Helm fail to “conclusively establish” his “status as a ‘contractor’ under the statutory definition,” Helm testified that he was “not a contactor” at the pre-trial hearing.
Helms’s second claim was that Kingston’s later claim of a misconstructed firewall should be barred, claiming that Kingston “‘had knowledge of a defect in the firewall’ as early as 1997 but did not assert them until 2007.” The court rejected this because Kingston’s claim was that “Helm ‘fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of the workmanship was atrocious.’”
Helms also challenged whether his statements that the residence was of “good quality” constituted fraud and misrepresentation under Texas’s Deceptive Trade Practices-Consumer Protection Act. The court concluded that Helm was in a position to make knowledgeable statements and further that “residential housing units are not artistic works for which quality is inherently a matter of subjective judgment.” Helm also claimed that Kingston could have avoided certain repair expenses through the “exercise of reasonable care.” Helms argued that the repairs could have been made for $6,400. The court disagreed, as these claims were cited only to invoke the DTPA, and that later petitions established additional defects.
Helms’s next claim was that he was not allowed to designate responsible third parties. The court rejected this because there GDI represented matters concerning the residence only through Helm’s statements. The court noted that “Helm is correct that?third parties may be liable for fraud if they ‘participated in the fraudulent transactions and reaped the benefits,’” but they note that “Helm never specifically alleged that GDI or CREIC participated in Helm’s alleged fraudulent transactions.
The final issue in the decision was about court costs, and here the court denied claims on both sides. Helm argued that the award of legal fees were excessive, as they exceeded the actual damages. The court noted that they “may not substitute our judgment for that of the jury,” and also that “the ratio between the actual damages awarded and the attorney’s fees is not a factor that determines the reasonableness of the fees.” But the court also rejected Kingston’s claim for post-judgment interest on $10,312.30 that Helm had deposited in the trial court’s registry. The court noted that the monies were to be paid out upon final judgment, but the mandate did not include any reference to interest.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Is Construction Defect Litigation a Cause for Lack of Condos in Minneapolis?
September 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Peter Callaghan writing for the Minn Post, while multi-family residential real estate is “hot” right now, most developers are building apartments rather than condos. Four developers spoke on the topic during Minneapolis City Council Member Lisa Goodman’s monthly “Lunch with Lisa” program. The developers stated that financing is more difficult for condos than it is for apartments, and millennials and baby boomers seem to prefer renting over buying. However, some developers stated that “the 10-year liability exposure for construction defects” was another reason to avoid condo building.
However, not all developers avoid condo building in Minneapolis. Jim Stanton, owner of Shamrock Development, said that he still is building condos. Stanton declared that he “has a good relationship with his lender,” and “he hasn’t been sued a lot and has never had a suit reach court.”
Read the court decisionRead the full story...Reprinted courtesy of
Berger: FIGG Is Slow To Hand Over All Bridge Collapse Data
November 12, 2019 —
Richard Korman - Engineering News-RecordThe Florida International University Tragedy
About half an hour before the almost-completed pedestrian bridge collapsed onto a busy Miami-area road last year, killing six people, Denney Pate, the bridge’s engineer-of-record, sent a text to Linda Figg, the chief executive of FIGG Bridge Engineers.
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Builder’s Risk Indeed”
October 24, 2023 —
Daniel Lund III - LexologyA contractor for a hotel in Seattle was tasked with constructing the hotel utilizing premanufactured modular hotel rooms. The modular unit portion of the project was the subject of a $15.8 million subcontract between the general contractor and the manufacturer. The manufacturer was also responsible to the GC for shipping and installing the modular units.
Shipping was to be “DDP,” or “Delivery Duty Paid” – which, according to a New York federal court, “is an international shipping term meaning that the seller assumes all responsibilities and costs for delivering property to the named place of destination, including export and import clearance, fees, duties, and taxes.” Additionally, per the subcontract, the manufacturer was responsible for “ensur[ing] all modular units [were] covered, secured[,] and protected from damage during the shipping process….” The modular units were shipped from Poland to Seattle. In the shipping process, the units spent some time in the Port of Everett in Washington state, where the units sustained water damage while sitting in port.
A related damage claim made by the subcontractor against the general contractor’s builder’s risk policy. On the face of the policy, the policy covered subcontractors as “additional insured” parties, covered all manner of materials and the like to be used on the project, and would provide that coverage in the process of transporting the materials insofar as “inland or coastal waters” were concerned. Yet, the builder’s risk insurer refused to cover the claim for the damages to the modular units which occurred while sitting in port in Everett.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Not Our Territory: 11th Circuit Dismisses Hurricane Damage Appraisal Order for Lack of Jurisdiction
July 24, 2023 —
Veronica P. Adams & Koorosh Talieh - Hunton Insurance Recovery BlogThe hurdles policyholders have faced with the appraisal process in Florida are far from over. In the past, many Florida courts have limited the scope for appraisal, strictly construing the policy provision against the policyholder. Yet, recently, in
Positano Place at Naples I Condominium Association, Inc., et al. v. Empire Indemnity Insurance Company, the Eleventh Circuit dismissed an insurer’s appeal of the district court’s ruling compelling appraisal and a stay of a pending litigation.
In Positano Place at Naples I Condominium Association, Inc., et al. v. Empire Indemnity Insurance Company, the policyholder Positano filed a claim for property insurance benefits under the policy as a result of damage to the property from Hurricane Irma in 2017. After investigating the claim, Empire found that there was damage to only three of the five properties covered under the policy and disputed the amount of loss.
Reprinted courtesy of
Veronica P. Adams, Hunton Andrews Kurth and
Koorosh Talieh, Hunton Andrews Kurth
Ms. Adams may be contacted at vadams@HuntonAK.com
Mr. Talieh may be contacted at ktalieh@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of