Policy Sublimit Does Not Apply to Business Interruption Loss
December 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiRefusing to give the sublimit in a flood policy an expansive reading, the court found that the sublimit did not apply to business interruption loss. Federal-Mogul Corp. v. Ins. Co. of Pa., 2015 U.S. Dist. LEXIS 137394 (E.D. Mich. Oct. 8, 2015).
The insured's facility in Thailand was damaged by flood. The parties stipulated that the insured suffered a loss of $64,500,000, which included $39,406,467 in property damage and $25,093,533 in time element loss (i.e., economic loss due to an inability to operate normally). The insurer paid $30 million, stating that the High Hazard flood zone provision in the policy limited the amount owed under the policy.
The insured argued the High Hazard sublimit applied only to physical loss or damage caused by the flood, and not to time element loss. Therefore, the insured was entitled to judgment on its time element loss claim for $29,093,533. The insurer argued it was entitled to judgment as a matter of law because the High Hazard sublimit applied to all loss caused by flood, including time element loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Injured Construction Worker Settles for Five Hundred Thousand
October 28, 2011 —
CDJ STAFFAn upstate New York man who was injured when an unsecured truss fell off the railings of a scissor lift has settled for $500,000. As the accident happened at the building site for a casino for the Seneca Nation, attorneys for the construction firm had argued that New York labor laws were inapplicable as the injury happened on Seneca Nation land. The state appeals court ruled that as none of the parties involved were Native Americans, it was not internal to the affairs of the Seneca Nation.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Wins in Arbitration Only to Lose Before the Superior Court on Section 7031 Claim
June 19, 2023 —
Garret Murai - California Construction Law BlogIf you’re a regularly reader of the California Construction Law Blog you’re aware of Business and Professions Code section 7031 which courts have variously described as “harsh[ ],” “draconian” and “unjust,” but, importantly, nevertheless valid. We haven’t seen many cases applying Section 7031 in an arbitration setting, however, until now.
In Vascos Excavation Group LLC v. Gold, 87 Cal.App.5th 842 (2022), a contractor who prevailed on a payment claim in arbitration, had its victory snatched from its fingertips by the Superior Court which found that the arbitrator had exceeded her authority because the contractor was subject to Section 7031.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Bert L. Howe & Associates Returns as a Sponsor at the 30th Annual Construction Law Conference in San Antonio
January 13, 2017 —
Don MacGregor - Bert L. Howe & Associates, Inc.Bert L. Howe & Associates, Inc. is proud to join with the Texas Institute of CLE, and return for the third year as a sponsor and exhibitor at the 30th Annual Construction Law Conference to be held March 2nd & 3rd, 2017 at the La Cantera Resort and Spa in San Antonio.
With offices in San Antonio and Houston serving all of Texas, Bert L. Howe & Associates, Inc. (BHA) offers the experience of over 20 years of service to carriers, defense counsel, and insurance professionals as designated experts in nearly 6,500 cases. BHA’s staff encompasses a broad range of licensed and credentialed experts in the areas of general contracting and specialty trades, as well as architects, and both civil and structural engineers, and has provided services on behalf of developers, general contractors and sub-contractors.
BHA’s experience covers the full range of construction and construction defect litigation, including single and multi-family residential (including high-rise), institutional (schools, hospitals and government buildings), commercial, and industrial claims. BHA specializes in coverage, exposure, premises liability, and delay claim analysis as well.
As the litigation climate in Texas continues to change, and as the number of construction defect and other construction related cases continues to rise, it is becoming more important for contractors and builders to be aggressive in preparing for claims before they are made, and in defending against those claims once they are filed. Since 1993, Bert L. Howe & Associates has been an industry leader in providing construction consulting services, and has been a trusted partner with builders and insurance carriers, both large and small, across the Western and Southern United States. Here in Texas, we have been providing construction defect and construction-claims related forensic expert services for the past decade with a proven track record of successful results. To-date, we have participated in the successful defense of claims involving thousands homes here in Texas alone.
For those of you planning on attending the conference, or those who may know someone who will be, we encourage you to stop by the BHA booth and we welcome the opportunity to discuss further the broad range of services provided by BHA.
For your convenience, here is a link to the information page for the 30th Annual Construction Law Conference: https://www.clesolutions.com/store.aspx?categoryid=2
Read the court decisionRead the full story...Reprinted courtesy of
Don MacGregor, Bert L. Howe & Associates, Inc.Mr. MacGregor may be contacted at
dmac@berthowe.com
ISO Proposes New Designated Premises Endorsement in Response to Hawaii Decision
October 27, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Insurance Services Office (ISO) has issued a Circular advising it will submit to Insurance Departments in various states proposed changes to the Designated Premises Endorsement. The changes are due in part to the Hawaii Supreme Court's decision in C. Brewer & Co. v. Marine Indem. Ins., 135 Haw. 190, 347 P. 3d 163 (Haw. 2015). (Full Disclosure - our office represented C. Brewer before the Hawaii Supreme Court).
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
HOA Foreclosure Excess Sale Proceeds Go to Owner
August 15, 2022 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogOver the last few years, the Arizona Court of Appeals wrestled with the question of who should receive the excess proceeds from a foreclosure sale. We’ve blogged about some these past unreported decisions
here and
here. Those decisions, somewhat inexplicably, required excess sale proceeds to be paid to senior creditors. As we noted at the time, these unreported (and non-precedential) decisions did not seem to make much sense in the context of debtor/creditor rights. Thankfully, a reported opinion finally sets the record straight. Excess sale proceeds should be paid downstream.
In
Tortosa Homeowners Assoc. v. Garcia, et al., No. 2 CA-CV 2021-0114 (Ct. App. Aug. 1, 2022), the Court of Appeals held that after the foreclosing lienholder is paid in full, then the excess sale proceeds should be paid to claimants in the order of their priority after the foreclosing lienholder. In other words, if a junior lienholder forecloses, then any creditors behind (i.e., junior to) the foreclosing creditor should be paid, and if all such creditors are paid, then the rest should be given to the owner. Creditors senior to the foreclosing creditor should not be paid anything from the foreclosure sale. This makes sense from a policy perspective, because the senior creditor retains its lien against the property and the bidder presumably took the presence of the senior lien into account when it made its bid for the foreclosed property.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Drafting or Negotiating A Subcontract–Questions To Consider
June 21, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to drafting and negotiating a subcontract, there are provisions that should be important to you from a risk assessment standpoint. From the subcontractor’s standpoint, below are questions you should ask, or issues you should consider, as you go through the subcontract. These are the same questions and issues that are also important to a contractor as the contractor will want to ensure these issues are included in the subcontract. By asking yourself these questions, you can check to see how the subcontract addresses these issues, and how the risk should be negotiated. Hopefully, you are working with counsel to make sure you understand what risk you are assuming and those provisions you want to try to push back on. Asking yourself these questions, or considering these questions, will help you go through the subcontract with a purpose based on the risk profile of the project and certain risk you don’t want to assume.
- Prime Contract –> Does the subcontract incorporate the prime contract? Make sure to request the prime contract since the subcontract will identify the prime contract as part of the Subcontract Documents and will require you to assume towards the contractor the same obligations the contractor is required to assume towards the owner.
- Scope of Work –> What is the scope of work? Is it clear. Make sure the scope is clear and you understand the scope.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Wait! Don’t Sign Yet: Reviewing Contract Protections During the COVID Pandemic
April 13, 2020 —
Danielle S. Ward - Balestreri Potocki & HolmesAs the circumstances of the COVID pandemic change day by day, and we all rush to keep business moving where and when we can, companies should consider hitting the “pause button” before renewing or executing any new contracts. Developing contracts often takes considerable time and expense, and companies are not in the habit of reworking them often. A change in law may prompt a company to revisit their contract terms, but otherwise business is often carried out with a standard form contract for a period of years. With the COVID pandemic affecting nearly every business and industry, life is not business as usual, and companies should make sure their contracts consider what previously seemed like an unforeseeable event.
Force Majeure clauses are included in many contracts to excuse contract performance when made impossible by some unforeseen circumstance. These clauses typically fall under two categories: general and specific. General force majeure clauses excuse performance if performance is prevented by circumstances outside the parties’ control. By contrast, specific force majeure clauses detail the exhaustive list of circumstances (acts of god, extreme weather, war, riot, terrorism, embargoes) which would excuse contract performance. Force majeure clauses are typically interpreted narrowly. If your contract has a specific clause and pandemic or virus is not one of the listed circumstances it may not apply. Whether a particular existing contract covers the ongoing COVID pandemic will vary depending on the language of the contract.
Force majeure clauses previously made headlines when the great economic recession hit in 2008. A number of courts held that simple economic hardship was not enough to invoke force majeure. The inability to pay or lack of desire to pay for the contracted goods or services did not qualify as force majeure. In California, impossibility turns on the nature of the contractual performance, and not in the inability of the obligor to do it. (Kennedy v. Reece (1964) 225 Cal. App. 2d 717, 725.) In other words, the task is objectively impossible not merely impossible or more burdensome to the specific contracting party.
California has codified “force majeure” protection where the parties haven’t included any language or the circumstances in the clause don’t apply to the situation at hand. Civil Code section 1511 excuses performance when “prevented or delayed by an irresistible, superhuman cause, or by the act of public enemies of this state or of the United States, unless the parties have expressly agreed to the contrary.” (Civ. Code § 1511.) What qualifies as a “superhuman cause”? In California, the test is whether under the particular circumstances there was such an insuperable interference occurring without the party's intervention as could not have been prevented by the exercise of prudence, diligence and care. (Pacific Vegetable Oil Corp. v. C. S. T., Ltd. (1946) 29 Cal.2d 228, 238.)
If you find yourself in an existing contract without a force majeure clause, or the statute does not apply, you may consider the doctrine of frustration of purpose. This doctrine is applied narrowly where performance remains possible, but the fundamental reason the parties entered into the contract has been severely or substantially frustrated by an unanticipated supervening circumstance, thus destroying substantially the value of the contract. (Cutter Laboratories, Inc. v. Twining (1963) 221 Cal. App. 2d 302, 314-15.) In other words, performance is still possible but valueless. Note this defense is not likely to apply where the contract has simply become less profitable for one party.
Now that COVID is no longer an unforeseeable event, but rather a current and grave reality, a party executing a contract today without adequate protections may have a difficult time proving unforeseeability. Scientists are not sure whether warm weather will suppress the spread of the virus, as it does with the seasonal flu, but to the extent we get a reprieve during the summer we may see a resurgence of cases this Fall or Winter. Companies should take care in reviewing force majeure clauses, and other clauses tied to timely performance such as delay and liquidated damages before renewing or executing new contracts.
Your contract scenario may vary from the summary provided above. Please contact legal counsel before making any decisions. During this critical time, BPH’s attorneys can be reached via email to answer your questions.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle S. Ward, Balestreri Potocki & HolmesMs. Ward may be contacted at
dward@bph-law.com