Construction Law Alert: Unlicensed Contractors On Federal Projects Entitled To Payment Under The Miller Act
May 07, 2014 —
Steven M. Cvitanovic and Jessica M. Lassere Ryland - Haight Brown & Bonesteel, LLPAs a matter of first impression, the Ninth Circuit Court of Appeals in Technica LLC ex rel. U.S. v. Carolina Cas. Ins. Co., 12-56539, 2014 WL 1674108 (9th Cir. Apr. 29, 2014), allowed an unlicensed subcontractor to recover from a prime contractor for unpaid services relating to a federal construction project under a federal Miller Act claim. California law otherwise prevents unlicensed contractors from recovering for unpaid work on non-federal projects as a penal measure intended to encourage contractors to maintain a valid license at all times.
Technica LLC (“Technica”) worked as a sub-subcontractor on a large federal fence replacement project (the “Project”). Over the course of a year, Technica supplied nearly a million dollars worth of labor, materials, and services for the Project. However, Technica received only $287,861.81 in partial payments for its work. Technica proceeded to file suit in district court against the prime contractor Candelaria Corporation (“Candelaria”) and its payment surety Carolina Casualty Insurance Company (“CCIC”) under the Miller Act to recover amounts owed to it on the subcontract against the payment bond.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel, LLP and
Jessica M. Lassere Ryland, Haight Brown & Bonesteel, LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Lassere Ryland may be contacted at jlassere@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Hydrogen—A Key Element in the EU’s Green Planning
December 07, 2020 —
Matthew Oresman & Henrietta Worthington - Gravel2Gavel Construction & Real Estate Law BlogGettyImages-1150744671-300x225Hydrogen is gaining global recognition for its potential as a key player in the energy transition. Investors and businesses are exploring opportunities across multiple sectors, including energy, manufacturing, transport and finance. According to a report by Bloomberg, the current pipeline for global hydrogen projects is worth an estimated $90 billion. The EU is not going to be left behind, with a focal point of its Green Deal being on hydrogen.
The EU’s executive branch (the European Commission or EC) has confirmed its commitment to increasing hydrogen projects across the bloc, with a priority on green hydrogen. Its Hydrogen Strategy, released in March, states that hydrogen is “essential to support the EU’s commitment to reach carbon neutrality by 2050 and for the global effort to implement the Paris Agreement while working towards zero pollution.”
The EU’s executive branch (the European Commission or EC) has confirmed its commitment to increasing hydrogen projects across the bloc, with a priority on green hydrogen. Its Hydrogen Strategy, released in March, states that hydrogen is “essential to support the EU’s commitment to reach carbon neutrality by 2050 and for the global effort to implement the Paris Agreement while working towards zero pollution.”
Reprinted courtesy of
Matthew Oresman, Pillsbury and
Henrietta Worthington, Pillsbury
Mr. Oresman may be contacted at matthew.oresman@pillsburylaw.com
Ms. Worthington may be contacted at henrietta.worthington@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Appellate Court Expands Policyholders’ Ability to Plead and Seek Consequential Damages
February 27, 2019 —
Michael S. Levine & Joshua S. Paster - Hunton Andrews KurthIn a huge win for policyholders, a New York appellate court, in D.K. Property, Inc. v National Union Fire Insurance Company of Pittsburgh, Pa., held that an insured need not provide a detailed factual description or explanation for why consequential damages are recoverable at the pleading stage. Rather, an insured’s complaint must only (i) specify the types of consequential damages claimed; and (ii) allege that those damages reasonably were contemplated by the parties prior to contracting.
Here, D.K. Property’s building was damaged as a result of construction on an adjoining building, and it timely filed a claim with National Union under a policy that covers “direct physical loss or damage to” the building. National Union neither paid the claim nor disclaimed coverage. Instead, according to D.K. Property, National Union made unreasonable and increasingly burdensome information demands over a three-year period, which it alleges was a “tactic” to make pursuing the claim so expensive that D.K. Property would abandon the claim. As a result of the delay, D.K. Property alleges the structural damage to its building has worsened.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Joshua S. Paster, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Paster may be contacted at jpaster@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 —
Douglas Reiser, Builders Council BlogEver had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
New Jersey Supreme Court Rules that Subcontractor Work with Resultant Damage is both an “Occurrence” and “Property Damage” under a Standard Form CGL Policy
September 01, 2016 —
Beverley BevenFlorez-CDJ STAFFAccording to a client alert by the firm Peckar & Abramson, P.C. (P&A), “In a recent significant decision, the Supreme Court of New Jersey held that defective work of a subcontractor that causes consequential property damage is both an ‘occurrence’ and ‘property damage’ under the terms of a standard form commercial general liability (“CGL”) insurance policy.”
Patrick J. Greene, Jr., and Frank A. Hess of P&A wrote that the Cypress Point Condominium Assoc., Inc. v Adria Towers, LLC, 2016 N.J. Lexis 847 (Aug.4,2016) “decision is important in New Jersey and in other jurisdictions that had relied upon the influential New Jersey case, Weedo v. Stone–E–Brick, Inc., 81 N.J. 233 (1979), that had determined that such claims involved non-insured ‘business risks.’”
Read the court decisionRead the full story...Reprinted courtesy of
Insurer’s Discovery Requests Ruled to be Overbroad in Construction Defect Suit
October 28, 2011 —
CDJ STAFFThe US District Court has ruled in the case of D.R. Horton Los Angeles Holding Co. Inc. v. American Safety Indemnity, Co. D.R. Horton was involved in a real estate development project. Its subcontractor, Ebensteiner Co., was insured by ASIC and named D.R. Horton as an additional insured and third-party beneficiary. D.R. Horton, in response to legal complaints and cross-complaints, filed for coverage from ASIC under the Ebensteiner policy. This was refused by ASIC. ASIC claimed that “there is no potential coverage for Ebensteiner as a Named Insurer and/or D.R. Horton as an Additional Insured.” They stated that “the requirements for coverage are not satisfied.”
The case same to trial with the deadline for discovery set at March 1, 2011. ASIC stated they were seeking the developer’s “job file” for the Canyon Gate project. D.R. Horton claimed that ASIC’s discovery request was overbroad and that it would be “unduly burdensome for it to produce all documents responsive to the overbroad requests.”
D.R. Horton did agree to produce several categories of documents, which included:
“(1) final building inspection sign-offs for the homes that are the subject of the underlying litigation;(2) an updated homeowner matrix for the underlying actions; (3) the concrete subcontractor files; (4) the daily field logs for D.R. Horton’s on-site employee during Ebensteiner’s work; (5) documents relating to concrete work, including documents for concrete suppliers; (6) documents relating to compacting testing; (7) documents relating to grading; and (8) D.R. Horton’s request for proposal for grading”
The court found that the requests from ASIC were overbroad, noting that the language of the ASIC Request for Production of Documents (RFP) 3-5 would include “subcontractor files for plumbing, electric, flooring, etc. - none of these being at issue in the case.” The court denied the ASIC’s motion to compel further documents.
The court also found fault with ASIC’s RFPs 6 and 7. Here, D.R. Horton claimed the language was written so broadly it would require the production of sales information and, again, subcontractors not relevant to the case.
Further, the court found that RFPs 8, 10, 11, and 13 were also overbroad. RFP 8 covered all subcontractors. D.R. Horton replied that they had earlier complied with the documents covered in RFPs 10 and 11. The court concurred. RFP 13 was denied as it went beyond the scope of admissible evidence, even including attorney-client communication.
The court denied all of ASIC’s attempts to compel further discovery.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
North Carolina Should Protect Undocumented Witnesses to Charlotte Scaffolding Deaths, Unions Say
April 03, 2023 —
Engineering News-RecordCharlotte Observer
More than two months after a scaffolding collapse in Charlotte killed three men, labor unions are urging state leaders to protect undocumented construction workers who witnessed the collapse so they can safely talk to investigators.
Reprinted courtesy of
Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Lot of Cheap Housing Is About to Get Very Expensive
October 21, 2015 —
Patrick Clark – BloombergUrban Institute fellow Erika Poethig has a poster in her office showing 22 apartment buildings along Chicago's Lake Shore Drive. They were all built with U.S. government dollars to provide affordable housing to thousands of low-income households—and have since been converted to market-rate apartments and condominiums.
For Poethig, a former official at the Department of Housing and Urban Development, those apartments are a warning.
There are currently about 1.34 million units of affordable housing created by a HUD program known as Section 8 project-based rental assistance, according to a blog post published on Wednesday by Poethig and her Urban Institute colleague Reed Jordan. More than 30 percent of those units are kept affordable by contracts that are set to expire by the end of 2017.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg