Language California Construction Direct Contractors Must Add to Subcontracts Beginning on January 1, 2022, Per Senate Bill 727
December 20, 2021 —
William L. Porter - Porter Law GroupSenate Bill No. 727, Imposing Liability on Contractors for Wage Claims of Subcontractor Employees:
California Senate Bill 727 was approved by the Governor on September 27, 2021. The new Act amended Labor Code Section 218.7 and added a new section 218.8 to the Labor Code. Both Labor Code sections impose on “direct contractors” in the construction industry (defined by Civil Code 8018 as “a contractor that has a direct contractual relationship with an owner”) liability for the wage violations of their subcontractors and sub-subcontractors at any tier when working on California private construction projects.
Specifically, new Section 218.8 expands the liability of direct contractors for wage claims of the employees of subordinate subcontractors on projects for contracts executed beginning on January 1, 2022. The liability of the direct contractor under Labor Code 218.8 will include “any debt owed to a wage claimant or third party on the wage claimant’s behalf, incurred by a subcontractor at any tier acting under, by, or for the direct contractor.” Specifically included as listed liabilities of the direct contractor are: “any unpaid wage, fringe or other benefit payment or contribution, penalties or liquidated damages, and interest owed by the subcontractor on account of the performance of the labor.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
DE Confirms Robust D&O Protection Despite Company Demise
February 18, 2015 —
James Yoder, Michael Onufrak and Siobhan Cole – White and Williams LLPOn Feb. 5, 2015, the United States Bankruptcy Court for the District of Delaware, per Judge Brendan L. Shannon, entered proposed findings of fact and conclusions of law in favor of the former president and CEO of Ultimate Escapes Inc., James M. Tousignant, and its chairman, Richard Keith, after determining that Tousignant’s actions in negotiating and executing a controversial asset purchase agreement were protected by the business judgment rule, despite the demise of the company a short time later. The failure of a business strategy, in and of itself, does not create liability on the part of the former directors and officers of a bankrupt company.
Background
Ultimate Escapes was a luxury destination club that provided its members with access to high-end vacation residences around the world. Unfortunately, Ultimate Escapes’ business suffered greatly from the economic downturn that began in 2008, and on Sept. 20, 2010, Ultimate Escapes filed voluntary petitions for relief pursuant to Chapter 11 of the Bankruptcy Code.
Reprinted courtesy of White and Williams LLP attorneys
James Yoder,
Michael Onufrak and
Siobhan Cole
Mr. Yoder may be contacted at yoderj@whiteandwilliams.com
Mr. Onufrak may be contacted at onufrakm@whiteandwilliams.com
Ms. Cole may be contacted at coles@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The Proposed House Green New Deal Resolution
February 27, 2019 —
Anthony B. Cavender - Gravel2GavelA Resolution has been proposed to the House for consideration that would recognize the Federal Government’s duty “to create a Green New Deal.” It sets forth a very ambitious 10-year program to mobilize and transform every aspect of American life to combat the threats of climate change by transitioning to an economy based upon 100% clean and renewable energy.
In doing so, millions of new jobs would be created, and everyone who wants a job would be guaranteed a job. The sponsors’ talking points declare that there is no time to lose, that Americans love a challenge, and “this is our moonshot.” The obvious goal is to eliminate the generation and use of fossil fuel and nuclear energy—they are simply not part of the solution.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Traub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp Obtain Summary Judgment in Favor of Residential Property Owners
December 13, 2022 —
Gregory S. Pennington & Emily A. Velcamp - Traub LiebermanTraub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp obtained summary judgment in favor of their clients, owners of a residential property [the “Owners” or “Defendants”] used as a short-term rental in Beach Haven, New Jersey. Plaintiff alleged injuries resulting from a fall into an open water meter pit, located in the public sidewalk abutting the Owners’ property during the time within which the property was rented to plaintiff and his family. According to plaintiff, defendants breached their duty owed to him, relying on a Borough of Beach Haven Ordinance, thereby allowing the water meter pit to be raised in an unsafe manner, which resulted in plaintiff’s fall and subsequent injuries.
After the Court denied defendants’ initial Motion for Summary Judgment on the grounds that issues of material fact existed regarding defendants’ duty and the alleged breach of that duty, a Motion for Reconsideration was filed. Mr. Pennington and Ms. Velcamp argued that their clients, as residential landowners, owed no duty of care to plaintiff for the raised condition of the water meter pit lid, located in the abutting sidewalk, as they did not cause or contribute to the alleged condition. Defendants further argued that even if a duty of care existed, no breach occurred given the lack of notice to defendants, either actual or constructive. Plaintiff attempted to argue that defendants had constructive notice of the lid’s raised condition, relying on his expert report and the fact that defendants had 3.5 months from the date the property was purchased, to the date of the subject accident to discover the lid’s raised condition. Mr. Pennington and Ms. Velcamp successfully argued that despite plaintiff’s allegations and the findings contained in plaintiff’s expert report, authored 2 months after the alleged accident, there was still no credible, material evidence to say how long the water meter pit lid was in that raised condition to allow defendants a reasonable time to discover it, remedy it, or report it to the Borough.
Reprinted courtesy of
Gregory S. Pennington, Traub Lieberman and
Emily A. Velcamp, Traub Lieberman
Mr. Pennington may be contacted at gpennington@tlsslaw.com
Ms. Velcamp may be contacted at evelcamp@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurance Telematics and Usage Based Insurance Products
October 29, 2014 —
Robert Ansehl – White and Williams LLPThe New York State Department of Financial Services (the "DFS") issued Insurance Circular Letter No. 4 on May 27, 2014 (the “Circular Letter”). The purpose of the Circular Letter was to alert stakeholders of the DFS’ interest in obtaining information about products that use embedded telematic devices, including usage-based insurance products (“UBI”) that provide benefits to insurers and policyholders.
As data capture and transmission technology become more advanced, and as user interfaces become increasingly sophisticated, many insurers are considering UBI and other programs that rely upon telematic devices to monitor the behavioral patterns, tendencies and habits of insureds. For example, when these devices are installed in an insured's vehicle, a telematic device can gather driving data, including miles driven, the time of day the driver used the vehicle, and his/her speed, acceleration and braking patterns. This data can be captured and transmitted on a real-time basis that allows insurers to make more effective underwriting determinations and to better align pricing with an insured’s driving tendencies and the resulting attendant risks. Other insurers have applied UBI to homeowner’s insurance where, for example, smoke and other alarms and monitoring devices can monitor and transmit details regarding the resident's risk-based activities (for example, whether and how often and how long the insured uses ovens and stoves on an attended and unattended basis). This data can be used to facilitate an insurer’s ability to correlate insurance coverage decisions with the insured’s actual behavior (as opposed to self-reported behavior) as measured by sophisticated home-based telematic devices. In addition, UBI and other programs provide the data on a real-time basis, as opposed to collecting information via traditional means, principally based upon post-claim reporting. Tempering increased UBI usage are countervailing privacy and data protection concerns and risks. Regulators, insurers and consumers have significant stakes in the availability, access and applications of this information.
Read the court decisionRead the full story...Reprinted courtesy of
Robert Ansehl, White and Williams LLPMr. Ansehl may be contacted at
ansehlr@whiteandwilliams.com
Phillips & Jordan Awarded $176M Everglades Restoration Contract
March 01, 2021 —
Thomas F. Armistead - Engineering News-RecordConstruction of the next major project for the Everglades Agricultural Area Reservoir south of Lake Okeechobee is set to begin in April following the South Florida Water Management District's award of a $175.8-million lump-sum contract to Phillips and Jordan Inc.
Reprinted courtesy of
Thomas F. Armistead, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Gordon & Rees Ranks #5 in Top 50 Construction Law Firms in the Nation
June 29, 2020 —
Gordon Rees Scully MansukhaniGordon Rees Scully Mansukhani has been ranked the #5 construction law firm in the nation by Construction Executive in the magazine’s 2020 ranking of The Top 50 Construction Law Firms. Gordon & Rees is the only California-based law firm to rank in the Top 25.
The firm was ranked in the Top 10 in more specific areas as well.
- #1 in the Top 10 Law Firms Ranked by Most Locations
- #2 in the Top 10 Law Firms Ranked by Number of Construction Attorneys
- #6 in the Top 10 Law Firms Ranked by Number of States Admitted to Practice
“With offices throughout the nation and outstanding construction attorneys in many of those offices, we are able to offer our construction clients a diverse range of legal services wherever they do business,” said
Ernie Isola partner and co-chair of the firm’s construction practice group.
Read the court decisionRead the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
“But it’s 2021!” Service of Motion to Vacate Via Email Found Insufficient by the Eleventh Circuit
June 21, 2021 —
Justin K. Fortescue - White and WilliamsWhile we are all getting used to the “new normal” of working remotely and relying on emails for almost all communications, a recent decision from the United States Court of Appeals for the Eleventh Circuit provides arbitration practitioners with a stark reminder – the “notice” requirements of the Federal Arbitration Act (FAA) will be strictly enforced and providing notice of a motion to vacate via email may not qualify as proper service.
In O'Neal Constructors, LLC v. DRT Am., LLC, 991 F.3d 1376 (11th Cir. 2021), O’Neal Constructors, LLC (O’Neal) and DRT America (DRT) entered into a contract containing an arbitration provision. Following a dispute, the parties went to arbitration and, on January 7, 2019, the panel issued an award requiring DRT to pay O’Neal a total of $1,415,193. The amount awarded to O’Neal consisted of two parts: $765,102 for the underlying contract dispute and $650,090 for reimbursement of O’Neal’s attorneys’ fees. While DRT paid O’Neal the first portion of the award, DRT refused to pay the portion that related to O’Neal’s attorneys’ fees.
On April 4, 2019, as a result of DRT’s refusal to pay O’Neal’s attorneys’ fees, O’Neal filed a motion to confirm the award in Georgia state court (which was subsequently removed to the Northern District of Georgia). The next day, in a separate action, DRT filed a motion to vacate the attorneys’ fees portion of the award and, that same night, DRT’s counsel emailed O’Neal’s counsel a “courtesy copy” of DRT’s memorandum in support of the motion to vacate. A few weeks later, on April 30, 2019 (i.e., more than three months after the award was issued), DRT served O’Neal (via U.S. Marshall) with a copy of the motion to vacate.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Fortescue, White and WilliamsMr. Fortescue may be contacted at
fortescuej@whiteandwilliams.com