Montana Significantly Revises Its Product Liability Laws
May 22, 2023 —
William L. Doerler - The Subrogation StrategistOn May 4, 2023, Montana changed its product liability laws when the Governor signed SB 216, which was effective upon passage and applies to claims that accrue on or after May 4, 2023. Among the changes is the adoption of a sealed container defense and the application of comparative negligence principles in strict liability actions. Montana also adopted a defense based on certain actions not being brought within 10 years. In addition, Montana adopted a rebuttable presumption with respect to a product’s defective condition. A jury must be informed about this rebuttable presumption with respect to certain warnings claims, premarket licensing procedures or claims involving drugs and/or medical devices. The changes to the Montana Code are further described below.
- In situations where there are multiple defendants, a defendant in a strict liability or breach of warranty action may now assert, as a defense, that the damages of the claimant were caused in full or in part by a person with whom the claimant has settled or released from liability. See MCA § 27-1-703(6)(a) (as revised). Comparative negligence or fault defenses are also available in actions against sellers, even where there are not multiple defendants. See MCA § 27-1-719(4)(e) (discussing a seller’s defenses in situations other than multiple defendant situations) (as revised).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Be Careful with Good Faith Payments
February 24, 2020 —
Christopher G. Hill - Construction Law MusingsSometimes doing the expedient thing and what looks good at the time can come back to bite you. Just ask 3M Company.
In Faneuil, Inc. v. 3M Co., the Virginia Supreme Court considered a customer services subcontract between Faneuil and 3M relating to a toll collection contract 3M entered into with ERC. The subcontract had a “pay if paid” clause in it requiring payment to 3M from ERC before ERC was required to pay Faneuil, a written change order provision and a base monthly payment to Faneuil for the services that could be reduced in the event of less than expected toll collections. Further, the subcontract stated that if either party settled 3rd party claims, that settlement would not bind the other party to the subcontract absent consent or Court order.
Faneuil was then alleged to have been required to provide “Special Services” relating to manual identification of license plates and other information necessary for toll billing due to 3M’s alleged failure to provide adequate imaging services. Faneuil requested (without written change order) and 3M promised to pay extra for these services. When 3M was slow to pay for the special services, Faneuil did what you would expect and threatened to stop providing them. Instead of contesting the right to the work, 3m made sporadic “good faith” payments to induce continued Special Services from Faneuil. Eventually 3M’s issues caused ERC to stop payments and thus 3M stopped paying Faneuil. 3M then settled the payment claims with ERC and still failed to pay Faneuil.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Job is Substantially Complete, the Subcontract was Never Signed, the Subcontractor Wants to be Paid—Now What?
July 28, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCA recent case in North Carolina illustrates the types of problems created when a general contractor accepts a subcontractor’s bid and then allows the subcontractor to perform the work without obtaining a signed subcontract.[i] In this case, the general contractor (Choate Construction Company – “Choate”) accepted a bid from a foundation subcontractor (Southeast Caissons, LLC – “SEC”). Choate sent the subcontract to SEC. SEC provided its changes in a “Proposed Addendum” to the subcontract stating, “[SEC] hereby accepts the terms of the attached Subcontract, subject to and conditioned upon Choate[’s] acceptance of the terms set forth in this Addendum[.]” After that, Choate called SEC and exchanged emails concerning the subcontract terms, but did not reach an agreement. SEC then performed its subcontract and sought payment, and acknowledged it had not signed the subcontract. Choate agreed it owed SEC something, but refused to pay because SEC did not have a signed subcontract, asserting the subcontract was not binding on Choate.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Exception to Watercraft Exclusion Does Not Apply
September 24, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that an additional insured was not entitled to coverage despite an exception to the watercraft exclusion. Holden v. U.S. United Ocean Serv., LLC, 2014 U.S. App. LEXIS 15954 (5th Cir. Aug. 19, 2014).
United entered a contract with Buck Kreihs Company, Inc. under which Buck Kreihs would perform ship-repair work for United. Under the contract, Buck Kreihs would indemnify United for all liabilities arising out of the work or services performed by Buck Kreihs for United. The contract further provided that Buck Kreihs was to procure general liability coverage and name United as an additional insured. Buck Kreihs did so under a policy issued by St. Paul.
Holden, an employee of Buck Kreihs, was injured while preparing to remove a gangway that led from a dock at Buck Kreihs's facility to a barge owned by United. Holden sued United, which tendered to St. Paul as an additional insured. St. Paul denied coverage under the policy's watercraft exclusion. Holden and United settled. United pursued its third party suit against St. Paul. The district court granted summary judgment to St. Paul.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Work without Permits may lead to Problems Later
September 10, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the Los Angeles Register, “Southern California homeowners often have repairs or improvements done to their property without getting the required building permits,” which sometimes, may be fine, but other times it leads to disastrous problems.
The Register used an example of a San Clemente couple who had issues selling their home when a building inspector found that weep screeds were covered up by a cement deck installed by a contractor. The contractor also failed to get building permits for the work that was done. The buyer stated that repairs needed to be done prior to the sale.
According to Mac MacKenzie, an agent at Coldwell Banker in Irvine, the situation is not uncommon: “We’ve had (permit problems) kill deals before, and we’ve had them almost kill deals. If it’s serious enough, it can stop a transaction from closing.”
Permits are generally required “for any alteration, major repairs or new construction,” according to the Register, while they are not necessary “for minor repairs, such as fixing leaky pipes, painting, new carpeting or new kitchen countertops.”
Read the court decisionRead the full story...Reprinted courtesy of
Convictions Obtained in Las Vegas HOA Fraud Case
March 19, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Las Vegas Review-Journal reported that a jury “convicted four defendants charged in the massive scheme to take over and defraud homeowners associations.” Convicted defendants included former Benzer attorney Keith Gregory, Benzer’s half-sister Edith Gillespie, Salvatore Ruvolo, and David Ball.
According to the Las Vegas Review-Journal, “Prosecutors contended the multimillion-dollar scheme was carried out between 2003 and 2009 by former construction company boss Leon Benzer and the late construction defects lawyer Nancy Quon. Benzer has since pleaded guilty. Quon committed suicide in 2012 under the weight of the high-profile investigation.”
Read the court decisionRead the full story...Reprinted courtesy of
New World Cup Stadiums Failed at their First Trial
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFProblems abounded at the inaugural match at one of the new World Cup stadiums in Manaus, Brazil, reported The News Tribune. Problems also were reported at the Arena da Amazonia. Bathrooms weren’t completed, roofs leaked, and some fans were sold tickets for seats that didn’t exist. Furthermore “construction material could be seen in some places and many wheelchair fans had difficulties accessing their seats.”
"This is a critical point that needs to be reevaluated, it can't happen again," said Miguel Capobiango, one of the officials in charge of World Cup preparations in Manaus, as quoted by The News Tribune. "But this is why we have these test events."
Read the court decisionRead the full story...Reprinted courtesy of
Emerging Trends in Shortened Statutes of Limitations and Statutes of Repose
January 02, 2024 —
Ivette Kincaid & Thomas McCarrick - Kahana FeldIntroduction
A growing trend in construction defect legislation around the country has seen the shortening of statutes of limitation and statutes of repose for a plaintiff to bring claims related to construction defects. Over the past ten years, several states, notably Florida and Texas, have shortened their statutes of repose. This is generally positive news for developers and contractors; however, the specifics and ramifications of these legislative and judicial updates are still unknown.
Statute of Limitations
A statute of limitations sets forth the time that a plaintiff has to sue or allege a particular cause of action against a defendant. These time limitations are codified into law and vary depending on the State and the cause of action. A statute of limitations starts at the occurrence of an injury or damage or at the time the injury or damage is discovered. The statute of limitations may be subject to some exceptions such as tolling for reasons such as the injured party being a minor in which case depending on the particular statute, the statute does not begin to run until after the minor reaches the age of majority.
Reprinted courtesy of
Ivette Kincaid, Kahana Feld and
Thomas McCarrick, Kahana Feld
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Mr. McCarrick may be contacted at tmccarrick@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of