Amid the Chaos, Trump Signs Executive Order Streamlining Environmental Permitting and Disbands Infrastructure Council
August 24, 2017 —
Garret Murai - California Construction Law BlogWe’ve been trying to stay focused here at the California Construction Law Blog. But it’s been hard.
This past week, a couple of new developments took place at the federal level on infrastructure, although if you blinked, you may have missed it.
Executive Order on Environmental Permitting
This past Tuesday, at a press conference quickly overshadowed by the President’s comments about the tragic events that took place in Charlottesville, President Trump announced that he had signed a new executive order aimed at streamlining the environmental permitting process for federally-funded projects.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Licensing Reciprocity Comes to Virginia
May 15, 2023 —
Christopher G. Hill - Construction Law MusingsRemember my admonishment to get your
Virginia contractor’s license? Well, that will get easier for experienced construction professionals that hold a license from a state or territory outside of Virginia beginning on July 1, 2023. In this past session of the General Assembly, the Youngkin administration pushed and the legislature passed a universal licensure statute that (with some exceptions for professional services as defined in
Va. Code 2.2-4301) will allow those (including contractors) who are licensed in other states to use that license to obtain a Virginia license.
The
new legislation will require DPOR to recognize another state’s license where the contractor meets the following requirements:
- The individual holds a current and valid professional or occupational license or government certification in another state in a profession or occupation with a similar scope of practice, as determined by the board in the Commonwealth
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Dealing with Hazardous Substances on the Construction Site
July 10, 2018 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Construction Law Musings, we welcome Vickie Lane. Vickie is the primary point of contact for Business Development with HAZMAT Plans & Programs, a consulting and training firm that also works under the name of HP&P Safety. Vickie’s functions with HP&P include extensive pre-project research and support though estimating, planning and cost administration. Vickie attended Ohio State University and now enjoys her role as a first time grandmother and spending free time up in the Colorado Rocky Mountains. Vickie can be reached at vlane@hppsafety.com or on Twitter @HAZMATPlans and @hpandpsafety.
Most of us perceive hazards on a construction site to be those that can be readily visualized or perhaps easily imagined, like trench cave-ins or falls from heights. These are the obvious, but what about the nocuous, microscopic hazards that can’t be seen by the human eye, but can destroy the health of your workers? Welcome to the world of hazardous materials.
The inherent danger associated with hazardous substances is workers might not be not aware of exposure. Think of a snake in the dark scenario. If it is a rattlesnake, you have warning before the bite. A cobra on the other hand gives no such warning and the bite can be fatal. So it can be with hazardous and toxic substances.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Napa Quake, Flooding Cost $4 Billion in U.S. in August
September 10, 2014 —
Noah Buhayar - BloombergAn earthquake that struck the California wine country north of San Francisco and flooding in the U.S. last month caused more than $4 billion in economic losses, according insurance broker Aon Plc. (AON)
A 6.0-magnitude temblor shook the city of Napa on Aug. 24, damaging more than 1,100 buildings, injuring at least 258 people and causing about $2 billion in economic damages, the London-based broker said today in a report. Insured losses are expected to be in the hundreds of millions of dollars, because of the below-average extent of coverage, Aon said.
“Residential earthquake insurance penetration rates have gradually lowered in California during the past two decades from 33 percent in 1996 to roughly 10 percent today,” Steve Bowen, associate director and meteorologist for Aon Benfield Impact Forecasting, said in a statement. The Napa quake “serves as a reminder of the unpredictability and costly impacts.”
Read the court decisionRead the full story...Reprinted courtesy of
Noah Buhayar, BloombergMr. Buhayar may be contacted at
nbuhayar@bloomberg.net
Traub Lieberman Attorneys Lisa M. Rolle and Vito John Marzano Secure Dismissal of Indemnification and Breach of Contract Claims Asserted against Subcontractor
November 24, 2019 —
Lisa M. Rolle & Vito John Marzano - Traub Lieberman PerspectivesOn August 7, 2019, TLSS Partner Lisa M. Rolle and associate Vito John Marzano obtained a dismissal of all claims on behalf of their client, the subfloor subcontractor at the worksite, in a severed action filed in the Supreme Court of the State of New York, County of Kings.
In April 2014, plaintiff commenced suit against several defendants, including the general contractor, after he sustained an injury when he fell through temporary plywood while installing a staircase at a worksite in Brooklyn. In May 2018, plaintiff filed a note of issue and certified the matter as ready for trial. Immediately thereafter, the general contractor initiated a second third-party action against the subcontractor seeking common-law and contractual indemnification and breach of contract. The Court subsequently granted Traub Lieberman’s motion to sever the second third-party action and instructed the general contractor to file a new action.
After the general contractor recommenced suit, Traub Lieberman, on behalf of its client, the subcontractor, immediately moved to dismiss for failure to state a cause of action. In relevant part, Traub Lieberman pointed to the deposition testimony of the general contractor’s principal to establish that the subcontractor had finished its work on the permanent subfloor no less ten months to over a year prior to plaintiff’s accident, and that the subfloor required no alteration, repair or maintenance prior to or as a result of plaintiff’s accident. Further, the general contractor’s testimony pointed to work performed by another subcontractor that directly resulted in plaintiff’s injuries. It was also brought to the Court’s attention that plaintiff had testified that he fell through a temporary plywood floor, and that the subcontractor had only installed a permanent subfloor.
Reprinted courtesy of
Lisa Rolle, Traub Lieberman and
Vito John Marzano, Traub Lieberman
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Mr. Marzano may be contacted at vmarzano@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractual “Pay if Paid” and “Pay when Paid” Clauses? What is a California Construction Subcontractor to Do?
November 29, 2021 —
William L. Porter - Porter Law GroupThe Situation California Construction Subcontractors Face in Obtaining Payment:
California construction subcontractors find themselves faced with a significant payment issue every time they are asked to sign a subcontract on a major project. Invariably, the subcontract the prime contractor presents to the subcontractor for signature will contain a clause by which the prime contractor imposes a condition on payment from the prime contractor to the subcontractor. The condition will be either one or the other of two general types. Either the prime contractor will specify that it never has to pay the subcontractor if the prime contractor itself is not paid by the owner (a “pay-if-paid” clause), or the prime contractor will pay the subcontractor only after the prime contractor has first exhausted all its efforts to obtain payment from the owner through litigation, arbitration or otherwise, possibly delaying payment to subcontractors by months or even years (a “pay-when-paid” clause).
Goal of the Article:
The goal of this article is to draw a distinction between the pay-if-paid and pay-when-paid clauses, discuss the legality of these clauses in California, the problems these clauses create for subcontractors, advise the reader of helpful recent legal developments in this area of law, address the possibility of a further legislative remedy to address the issue, and discuss what the subcontractor might do to protect itself while awaiting a legislative remedy that may or may not ever arrive.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
New OSHA Vaccination Requirements For Employers With 100 Or More Employees (And Additional Advice for California Employers)
November 19, 2021 —
Laura Fleming & Rana Ayazi - Payne & FearsUpdate 11.8.21: On Nov. 6, 2021, the United States Court of Appeals for the Fifth Circuit granted a stay of the OSHA ETS, stating that the OSHA ETS may have “grave statutory and constitutional issues.” The stay is not a final ruling on the validity of the ETS but temporarily halts its implementation nationwide. OSHA has until Nov. 8, 2021 at 5:00 PM to respond and the petitioners have until Nov. 9, 2021 at 5:00 PM to reply to OSHA’s response. The Fifth Circuit will then issue its ruling likely late this week or early next week.
On Sept. 9, 2021, President Joe Biden announced his COVID-19 Action Plan. The Action Plan called on the Department of Labor’s Occupational Safety and Health Administration (“OSHA”) to develop a rule requiring all employers with 100 or more employees to ensure their workforce is fully vaccinated or require any workers who remain unvaccinated to produce a negative test result on at least a weekly basis before coming to work.
On Nov. 4, 2021, OSHA released the rule in the form of an Emergency Temporary Standards (“OSHA ETS”). Here are ten things you need to know about the OSHA ETS:
- How To Count To 100: (1) The applicable number is the total number of employees employed on November 5, 2021—this is the headcount that will be used for the duration of the OSHA ETS. (2) The count must be done at the employer level not the individual location level. (3) Part-time employees do count towards the total number of employees. (4) Employees who work from home do count towards the total number of employees. (5) Independent contractors do not count towards the total number of employee.
Reprinted courtesy of
Laura Fleming, Payne & Fears and
Rana Ayazi, Payne & Fears
Ms. Fleming may be contacted at lf@paynefears.com
Ms. Ayazi may be contacted at ra@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
A Behind-the-Scenes Look at Substitution Hearings Under California’s Listing Law
March 04, 2019 —
Garret Murai - California Construction Law BlogThe next case, JMS Air Conditioning and Appliance Service, Inc. v. Santa Monica Community College District, 2nd District Court of Appeal, Case No. B284068 (December 17, 2018), provides an interesting behind-the-scenes look at substitution hearings under the Subletting and Subcontracting Fair Practices Act.
The Subletting and Subcontracting Fair Practices Act
- The Subletting and Subcontracting Fair Practices Act (Public Contract Code Section 4100 et seq.), also commonly referred to as the “Listing Law,” requires that prime contractors on state and local public works projects “list” the following subcontractors in their bids:
- Subcontractors who are anticipated to perform work with a value in excess of 0.5% of the prime contractor’s total bid; and
Subcontractors, on street, highway and bridge projects, who are anticipated to perform work with a value in excess of the greater of: (a) 0.5% of the prime contractor’s total bid; or (b) in excess of $10,000.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at