Don’t Put Yourself In The Position Of Defending Against An Accord And Satisfaction Defense
October 10, 2022 —
David Adelstein - Florida Construction Legal UpdatesThe doctrine of accord and satisfaction lives and breathes in disputes including construction disputes. Unfortunately, a contractor, in the case discussed below, found out the hard way after it cashed checks that were accompanied with a letter that clearly indicated the checks were final payment. Once those payments were cashed, there was no “buyer’s remorse” that would allow it to still pursue disputed amounts. Remember this the next time you accept and cash a payment that says on the check it is full and final payment OR is accompanied by a letter that makes clear the payment is full and final payment. If you cash it, there is no second bite out of the apple, so to speak. If you are not interested in the payment being full and final payment, return the check. If you are not sure, either return the check or inquire and get that response in writing. Don’t put yourself in the position of defending against an
accord and satisfaction defense.
Even without the doctrine of accord and satisfaction, the contract between the contractor and owner discussed below made clear that contractor’s acceptance of final payment meant that contractor was unconditionally waiving other claims against the owner, further reinforcing that there would be no second bite out of the apple.
The morale:
(1) read the letter that accompanies a check and do NOT cash a check that indicates it is for final payment unless you are prepared to accept that amount; and
(2) read your contract to understand any contractual obligation that kicks-in with the acceptance of final payment.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Two Architecturally Prized Buildings May be Demolished
January 17, 2014 —
Beverley BevenFlorez-CDJ STAFFThe historic Portland Public Services Building, designed by Michael Graves, may be demolished after a report showed that “the 32-year-old building needs more than $95 million worth of repairs,” Dezeen Magazine reported. The Portland, Oregon building “is credited with being one of the first major buildings of postmodernism.” According to The Oregonian, the Portland city commissioners have differing opinions as to how to proceed. Council member Amanda Fritz commented that she “doesn’t think the problems at The Portland Building are all that bad compared to other city facilities,” while council member Nick Fish stated, “There’s got to be a better option than putting another $100 million into a white elephant.”
Dezeen Magazine also reported that the former American Folk Art Museum in New York is scheduled to be demolished to make room to extend the Museum of Modern Art (MoMA). Glenn Lowry, the MoMA director, stated that the decision came after a six-month study: “The analysis that we undertook was lengthy and rigorous, and ultimately led us to the determination that creating a new building on the site of the former American Folk Art Museum is the only way to achieve a fully integrated campus.”
The decision is being criticized by “architects, conservationists, and critics” reported Dezeen Magazine. Architects Tod Williams and Billie Tsien designed the former American Folk Art Museum. Williams and Tsien stated, “Demolishing this human-scaled, uniquely crafted building is a loss to the city of New York in terms of respecting the size, diversity and texture of buildings in a midtown neighborhood that is at risk of becoming increasingly homogenized."
Read the full story at Dezeen Magazine re The Portland Building...
Read the full story at The Oregonian re The Portland Building...
Read the full story at Dezeen Magazine re American Folk Art Museum... Read the court decisionRead the full story...Reprinted courtesy of
Does Article 2 of the Uniform Commercial Code Impact Your Construction Project?
November 07, 2022 —
Chris Cazenave - ConsensusDocsThe Uniform Commercial Code (UCC) is a set of statutes governing commercial transactions. Every state has adopted the UCC or some version of it. Understanding when and how the UCC applies to construction contracts is important because it can affect the agreement’s terms.
Article 2 of the UCC applies to the sales of goods, which the UCC defines very broadly to mean “all things (including specialty manufactured goods) which are movable . . . other than money in which the price is to be paid . . . .” UCC § 2-105. For the construction industry, UCC Article 2 governs most, if not all, purchases of materials and equipment installed or incorporated into the project. As a result, contractors and subcontractors should be familiar with the circumstances under which Article 2 may apply and how it may affect the project.
This article provides a brief overview of when Article 2 may affect your construction project and why it matters. The article also generally covers the UCC’s potential effects on the applicable statute of limitations, implied warranties, and when the obligation to make the payment arises.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Cazenave, Jones Walker LLP (ConsensusDocs)Mr. Cazenave may be contacted at
ccazenave@joneswalker.com
One World Trade Center Tallest Building in US
November 13, 2013 —
CDJ STAFFIt’s official! The tallest building in the United States is in New York. For forty years, the tallest building in the United States has been the Willis Tower in Chicago (better known by its former name, the Sears Tower). Now, the Council on Tall Buildings and Urban Habitat has decreed that One World Trade Center edges it out with its 1,776 feet of height, surpassing the Willis by 325 feet.
There is a caveat. The antennas on the top of the Willis building aren’t counted in. The mast on the top of One World Trade Center is, and it adds 441 feet to the height of the building. If the mast weren’t counted, One World Trade Center would be 116 feet shorter than the building in Chicago.
Read the court decisionRead the full story...Reprinted courtesy of
Disaster-Relief Bill Stalls in Senate
April 22, 2019 —
Tom Ichniowski - Engineering News-RecordA partisan squabble over funds to help Puerto Rico continue its long recovery and rebuilding from two hurricanes in 2017 has tied up a wide-ranging spending package on Capitol Hill. At stake in the fight are hundreds of millions of dollars for reconstruction and related work around the U.S.
Mr. Ichniowski may be contacted at kormanr@enr.com
Reprinted courtesy of
Tom Ichniowski, ENR
Read the court decisionRead the full story...Reprinted courtesy of
A Relatively Small Exception to Fraud and Contract Don’t Mix
April 01, 2015 —
Christopher G. Hill – Construction Law MusingsRemember all of my posts about how fraud and contract claims don’t usually play well in litigation? Well, as always with the law, there are exceptions. For instance, a well plead Virginia Consumer Protection Act claim will survive a dismissal challenge.
A recent opinion out of the Alexandria division of the U. S. District Court for the Eastern District of Virginia sets out another exception, namely so called fraudulent inducement. In XL Specialty Ins. Co. v. Truland et al, the Court considered the question of whether both a tort and contract claim can coexist in the same lawsuit when the tort claim is based upon the information provided to the plaintiff when that information proves false.
As the courts of Virginia have held for years, only certain information and statements made pre-contract can be the basis for a fraud claim in the face of a contractual duty to perform. One type of statement that is not properly the subject of a fraud in the inducement type claim is sales talk or opinion. Such sales talk (for example claiming that your company is the best for the job) is not the subject of a fraud claim because it is not meant to be relied upon and that such talk is an opinion about future performance, not a false statement of present fact or intent.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
From Both Sides Now: Looking at Contracts Through a Post-Pandemic Lens
August 03, 2020 —
Lori S. Smith - White and WilliamsA little over a year ago, I wrote a blog post about the danger of relying on precedent. Now, more than ever, clients and their advisors need to revisit contract forms on which they may have been relying for years. While many of us have lived through times that required certain adjustments in how we viewed contractual obligations — recessions, wars, oil embargoes, natural disasters, 9/11 — none of these events had the widespread and long-lasting impact that the current COVID-19 pandemic is having. None of these events shut down the U.S. economy and impacted global supply chains across every industry in the manner we are now experiencing.
With this in mind, there is a need to figure out what the “new normal” will look like for contract negotiations in a post-pandemic world. Business professionals need to now anticipate more widespread disruption than we could have ever before imagined. It isn’t just force majeure clauses or material adverse effect provisions, as these will likely add pandemics and government shutdowns to their ever-growing list of contemplated risks, if they were not already expressly covered. And it is not clear, at least in the near-term, whether a resurgence or mutation of COVID-19 or the emergence of another virus can truly be seen as unforeseeable in a post-COVID world. The issues are much more fundamental to the approach that parties may take in negotiating contracts. Commercial contracts between purchasers, vendors, distributors, licensors and licensees will need to evaluate allocation of risk from both sides and come to a new happy medium that all can live with in an ever-evolving world. While parties should review their standard contracts in their entirety, some key provisions to think about include:
- Length of the contract and exclusivity. Depending on which side you are on, you may want to reconsider a long-term arrangement that ties your company to a particular vendor or distributor. Supply chain disruption can have a seriously detrimental impact on your business. Are requirements contracts where a particular supplier is required to make available all of your needs for a certain good or service really the best arrangement for your business? What about take or pay arrangements where you are obligated to which are common in certain industries pay a minimum amount or a penalty to a supplier whether or not you actually purchase the contemplated volume of goods ? Do you really want to be tied up in an exclusive arrangement, or do you need flexibility to maintain secondary or tertiary sources of supply? Do you want to provide a licensee with an exclusive right to your technology (even within a limited field of use or industry sector)?
Read the court decisionRead the full story...Reprinted courtesy of
Lori S. Smith, White and WilliamsMs. Smith may be contacted at
smithl@whiteandwilliams.com
Business Solutions Alert: Homeowners' Complaint for Breach of Loan Modification Agreement Can Proceed Past Pleading Stage
October 08, 2014 —
Krsto Mijanovic, Annette Mijanovic, Blythe Golay - Haight Brown & Bonesteel LLPIn Fleet v. Bank of America, N.A. (No. G050049, published 9/23/14, filed 8/25/14), a California Court of Appeal held that the trial court erred in sustaining the demurrer of a lender, where the homeowners had adequately alleged causes of action for breach of contract, fraud, and promissory estoppel. The homeowners alleged that they made timely payments during the trial period plan under the modification program, but before the last payment was due, the lender foreclosed and their house was sold.
The homeowners had applied for a loan modification and were approved for a trial period plan under the modification program. They were required to make three monthly payments and verify financial hardship to permanently modify their loan. The homeowners made two payments and were told that foreclosure proceedings had been suspended. But before the third payment was due, the lender foreclosed. The trial court found that the trial period plan was not a binding loan modification agreement, so the homeowners had no right to any guaranteed loan modification.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Krsto Mijanovic,
Annette Mijanovic and
Blythe Golay
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Ms. Mijanovic may be contacted at amijanovic@hbblaw.com
Ms. Golay may be contacted at bgolay@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of