One Way Arbitration Provisions are Enforceable in Virginia
October 07, 2019 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, I’ve discussed arbitration clauses (pros and cons) as well as the fact that in our fair Commonwealth, contracts are enforced as written (for better or worse). A case out of the Eastern District of Virginia takes both of these observations and uses them to make it’s decision.
In United States ex rel. Harbor Constr. Co. v. T.H.R. Enters., the Newport News Division of the Eastern District of Virginia federal court considered the following provision and it’s enforceability:
At CONTRACTOR’s sole election, any and all disputes arising in any way or related in any way or manner to this Agreement may be decided by mediation, arbitration or other alternative dispute resolution proceedings as chosen by CONTRACTOR…. The remedy shall be SUBCONTRACTOR’s sole and exclusive remedy in lieu of any claim against CONTRACTOR’s bonding company pursuant to the terms of any bond or any other procedure or law, regardless of the outcome of the claim. The parties further agree that all disputes under this Subcontract shall be determined and interpreted pursuant to the laws of the Commonwealth of Virginia….
This provision was the crux of the argument made by T. H. R., the Defendant, in making a motion to dismiss or stay the lawsuit for payment filed by Harbor Construction. As background, Harbor Construction contracted with T. H. R. to perform work at Langley Air Force Base. Alleging non-payment of approximately $250,000.00, Harbor filed a complaint with three counts, one under the Federal Miller Act, one for breach of contract, and a third for unjust enrichment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Denver Parking Garage Roof Collapses Crushing Vehicles
February 12, 2014 —
Beverley BevenFlorez-CDJ STAFFOn Monday night, a parking garage ceiling collapsed at the Park Mayfair Condos in Denver, Colorado, according to KKTV News. Residents claim that “between five and ten vehicles were completely destroyed after the ceiling of the underground garage caved in.” No one was injured from the incident. Structural engineers have not commented “yet on how the collapse occurred, but residents told sister station KCNC that the ceiling fell after a cement beam holding up one side of the roof collapsed.”
According to KWGN News, FOX31 interviewed a “passerby” who alleged that he lived in the condominium five years ago, but moved out “because inspectors repeatedly sent notices to fix problems with the garage, but, to his knowledge, no action was taken by the condo complex.”
Read the full story at KKTV News...
Read the full story at KWGN News... Read the court decisionRead the full story...Reprinted courtesy of
New York Court Holds That the “Lesser of Two” Doctrine Limits Recoverable Damages in Subrogation Actions
September 23, 2019 —
Michael L. DeBona - The Subrogation StrategistIn New York Cent. Mut. Ins. Co. v. TopBuild Home Servs., Inc., 2019 U.S. Dist. LEXIS 69634 (April 24, 2019), the United States District Court for the Eastern District of New York recently held that the “lesser of two” doctrine applies to subrogation actions, thereby limiting property damages to the lesser of repair costs or the property’s diminution in value.
In New York Cent. Mut. Ins. Co., New York Central Mutual Insurance Company’s (New York Central) insureds, Paul and Karen Mazzola, suffered a fire to their home. After the fire, New York Central paid the Mazzolas $708,465.74 to repair the property. New York Central brought a subrogation action against TopBuild Home Services, Inc. (TopBuild), alleging that the fire was caused by negligent work performed by TopBuild. New York Central sought to recover the repair costs it paid to the Mazzolas. TopBuild conceded liability but disputed the proper measure of damages.
TopBuild filed a motion for partial summary judgment, arguing that under the “lesser of two” doctrine, New York Central could recover only the lesser of the costs to repair the property or the property’s diminution in value. TopBuild, therefore, asserted that New York Central was not entitled to the repair costs of $708,465.74 but, rather, could recover only the property’s decline in value following the fire – approximately $250,000.[1] In response, New York Central argued that New York’s “lesser of two” doctrine does not apply to subrogation actions because an insurance company cannot mitigate the payment it makes to its insured.
Read the court decisionRead the full story...Reprinted courtesy of
Michael L. DeBona, White and Williams LLPMr. DeBona may be contacted at
debonam@whiteandwilliams.com
KB Homes Sues Condo Buyers over Alleged Cybersquatting and Hacking
October 22, 2013 —
CDJ STAFFWillowbrook, a condominium complex in Lakewood Ranch, Florida has had problems with water intrusion. Now the builder is having problems with some of the residents. National home builder KB Homes is alleging that a pair of Willowbrook home owners who created a web site about their problems have violated federal cybersquatting laws, as the web site names they have registered are close to that KB Homes. The suit alleges that Andrew Smith and Daniel Koehler hope to either get KB Homes to purchase the web site or to buy back their homes.
The lawsuit also alleges that three other individuals, William Crismon, Patrick McGettigan, and Armando Oyola-Delgado, conspired to intercept e-mails between KB Home and Dueall Construction. KB Homes claims that the three gained access to a WiFi hotspot used by Dueall.
Read the court decisionRead the full story...Reprinted courtesy of
Highest Building Levels in Six Years in Southeast Michigan
December 11, 2013 —
CDJ STAFFMacomb Township in southeast Michigan has had $122 million in new development in 2013, all of which helped the region reach its highest building levels since 2007. The wider area saw 398 permits issued for single-family homes in the last twelve months, fifty-two more than in the twelve months prior.
“The improvement is economically driven,” said Michael Stoskofa, the CEO of the Home Builders Association of Southeast Michigan. As employment improves in the area, “more people are willing and able to purchase a home,” he said. Home inventory in the area is also at a record low. As a result, projects that were put on hold in 2008 are active again.
Read the court decisionRead the full story...Reprinted courtesy of
New Jersey Appeals Court Ruled Suits Stand Despite HOA Bypassing Bylaw
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFIn the case Port Liberte II Condominium Association v. New Liberty Residential Urban Renewal Company, a New Jersey appeals court ruled that a homeowners association (HOA) could bypass a bylaw that requires unit owners to approve litigation before it is filed, the New Jersey Law Journal reported. Two construction-defect suits were reinstated by the appeals court, and both had been “dismissed based on alleged violation of the bylaws.” The first suit “claimed the defendants' negligence contributed to major construction defects at the 225-unit condominium development, which was completed in 2004” while “the second suit claimed that one section of the development is sinking into the ground because of a failure to properly investigate soil conditions at the former industrial site where the buildings sit.”
According to the New Jersey Law Journal, the HOA did not obtain approval from the unit owners prior to commencing litigation because “the statute of limitations was about to expire.” However, the HOA met with the residents in October of 2009 and a vote was cast “72 to 3 to pursue litigation.” In May of 2011 the second suit was dismissed because defendants stated “approval of residents was not obtained.” Another meeting of residents occurred, and another vote cast ratified “both suits by a vote of 65 to 1.” However, Judge Baber, who had previously dismissed both suits, refused to reinstate them.
“The Appellate Division said in its ruling that the Condominium Act, N.J.S.A. 46:8B-1, gives the association the exclusive authority to file suit against builders and other third parties for damage to common areas in the community,” the New Jersey Law Journal reported. “Given its legal responsibility for upkeep of common areas, and its statutory authorization to sue for damages to such areas, the association had standing to file suit, the appeals court said.”
Read the court decisionRead the full story...Reprinted courtesy of
Expansion of Statutes of Limitations and Repose in K-12 and Municipal Construction Contracts
March 27, 2019 —
Henry Bangert - Colorado Construction LitigationThe purpose of this whitepaper is to bring attention to a trend in K-12 and municipal construction contracts, which expands the time periods for law suits against construction professionals.
Introduction and Background
Under Colorado statute, the period of time within which a legal action for construction defects may be brought against a construction professional in Colorado is two years from when the claimant (or its predecessor in interest) discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect (the “Statute of Limitations”), but in no case may an action be brought more than six years after substantial completion of the improvement, unless the claim arises in the fifth or sixth year after substantial completion, in which event the action may be brought within two years of such date, i.e., up to eight years after substantial completion (the “Statute of Repose”). See C.R.S. § 13-80-104. While the triggering events differ for the Statute of Limitations and Statue of Repose, the periods are intended to run concurrently to limit the period of time an action may be brought against construction professionals for construction defects to, at most, eight years after substantial completion. Importantly, these limitations periods may be expanded by agreement.
Prior to 1986, Colorado law provided for a 10-year Statute of Repose. However, in 1986, Colorado’s legislature shortened the Statute of Repose time limit to the current six (or up to eight) year period. In 1986, Colorado also redefined the date the claim arises from the date the defect was discovered or should have been discovered to the date the physical manifestation of a defect was discovered or should have been discovered. Therefore, after 1986, the two-year limitations period could begin to run when a claimant should have discovered the manifestation of a defect, even if the claimant did not recognize that a defect existed.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Additional Insured Is Covered Under On-Going Operations Endorsement Despite Subcontractor's Completion of Work
December 20, 2017 —
Tred Eyerly - Insurance Law HawaiiAlthough the homeowners did not own their homes when the subcontractors completed their work, the general contractor was still covered as an additional insured for the homeowners' suits based on the ongoing operations endorsement in the subcontractors' policies. McMillin Mgmt. Servs. v. Fin. Pac. Ins. Co., 2017 Cal. App. LEXIS 1000 (Cal. Ct. App. Nov. 14, 2017).
McMillin was the developer and general contractor for the project. Among the subcontractors were Martinez Construction Concrete Contractor, Inc. and Rozema Corporation. Martinez performed concrete flatwork between 2003 and November 2005. Rozema performed lath and stucco work between March 2003 and October 2005.
Lexington issued CGL policies to Martinez and Rozema. McMillin was an additional insured under both policies, "but only with respect to liability arising out of your [i.e., Martinez's or Rozema's] ongoing operations performed for [McMillin]." An exclusion provided that the insurance did not apply to property damage occurring after the insured subcontractor had completed operations on behalf of the additional insured.
Read the court decisionRead the full story...Reprinted courtesy of
Tred Eyerly, Insurance Law HawaiiMr Eyerly may be contacted at
te@hawaiilawyer.com