Georgia Legislature Passes Additional Procurement Rules
May 30, 2018 —
David R. Cook Jr. - Autry, Hall & Cook, LLPOn May 3, 2018, Governor Nathan Deal signed HB 899 into law, officially making it Act 389. Act 389 modifies O.C.G.A. § 13-10-4 and § 36-91-23 relating to public works bidding and contracts of state and local governments, respectively. Both sections are modified in the same bill because they contain the same language. The bill prohibits the disqualification of bidders based upon lack of previous experience with the project’s desired construction delivery method.
Before the modifications, the code protected a contractor from disqualification only for lack of previous experience on a job of comparable size. After the modification, the law expands to prohibit disqualification based on lack of previous experience with comparable job size and lack of previous experience with the construction delivery method.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Potential Extension of the Statutes of Limitation and Repose for Colorado Construction Defect Claims
April 27, 2020 —
David M. McLain – Colorado Construction LitigationOn January 27th, Senator Robert Rodriguez introduced SB 20-138 into the Colorado Legislature. The bill has been assigned to the Senate Judiciary Committee and has not yet been scheduled for its first hearing in that committee. In short, Senate Bill 20-138, if enacted, would:
- Extend Colorado’s statute of repose for construction defects from 6+2 years to 10+2 years;
- Require tolling of the statute of repose until the claimant discovers not only the physical manifestation of a construction defect, but also its cause; and
- Permit statutory and equitable tolling of the statute of repose.
Colorado’s statute of repose for construction defect claims are codified at C.R.S. § 13-80-104. In 1986, the Colorado Legislature set the statute of repose period at 6+2 years. For the last 34 years, Colorado’s statute of repose for owners’ claims against construction professionals has been substantially the same, to wit:
(1) (a) Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Gordon & Rees Ranked #4 of Top 50 Construction Law Firms in the Nation by Construction Executive Magazine
July 11, 2022 —
GRSM Construction Team - Gordon & Rees Construction Law BlogGordon Rees Scully Mansukhani has been ranked as the No. 4 construction law firm in the nation by Construction Executive in the magazine’s 2022 ranking of The Top 50 Construction Law Firms™. As the only law firm with offices and attorneys in all 50 states, Gordon & Rees’ construction group (with over 150 construction lawyers) delivers maximum value to our clients by understanding their business and combining the resources of a full-service national firm with the local knowledge of a regional firm.
Led by Allen Estes and Angela Richie, the construction lawyers at Gordon & Rees are uniquely situated to serve our construction clients. We have attorneys with professional training and practical experience in related fields such as engineering and construction management, as well as lawyers with leadership experience in various construction industry related trade associations, legal advisory committees and government agencies. “If a client is looking for a legal partner in multiple states who understands their business, Gordon & Rees is that partner,” said Angela Richie.
Read the court decisionRead the full story...Reprinted courtesy of
GRSM Construction Team, Gordon Rees Scully Mansukhani
Elon Musk's Boring Co. Is Feuding With Texas Over a Driveway
July 25, 2022 —
Sarah McBride - BloombergWhile Elon Musk is publicly making a big deal about moving to Texas and cozying up to the governor, behind the scenes his tunnel-building venture, Boring Co., is wrangling with local authorities in the state over a host of seemingly mundane permitting issues.
Since Boring bought land last May to create a research and development center in Bastrop, Texas, a rural area outside Austin, the company has put workers up on mobile homes at the site without authorized sewage facilities, failed to get air and stormwater permits and built a driveway without first getting official approval, according to documents obtained by Bloomberg News through a public records request.
The company’s dealings with Bastrop are yet another illustration of how Musk’s businesses often push the boundaries of or simply ignore regulations that bind other companies. In recent years his Tesla Inc. restarted production at its Fremont plant in defiance of pandemic rules to stay closed, Boring tried to build a tunnel in Los Angeles without going through an environmental review process and the US Securities and Exchange Commission is examining the disclosure of Musk’s stake in Twitter Inc.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah McBride, Bloomberg
Portions of Policyholder's Expert's Opinions Excluded
November 13, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted, in part, the insurer's motion to exclude portions of expert testimony. Tundra M. Holdings, LLC v. Markel Ins. Co., 2023 U.S. Dist. LEXIS 139952 (D. Alaska Aug. 10, 2023).
Plaintiff alleged a building it owned suffered damages consisting of building roof failure due to snow load. Plaintiff submitted a claim to Markel for its loss.
Plaintiff hired an engineering firm to conduct an inspection. The recommendation was to install snow guards and that 28 rafters be replaced with new beams. The evaluation did not state that the recommendation was required by law or ordinance. Nor did the evaluation make mention of replacing the metal roof on the building or anything about the water system or sprinkler system. Plaintiff then obtained an estimate of $687,500 for roof repair/replacement, store front repair, a sprinkler system installer and a water system upgrade.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Arizona Supreme Court Holds a Credit Bid at a Trustee’s Sale Should Not be Credited to a Title Insurer Under a Standard Lender’s Title Policy To the Extent the Bid Exceeds the Collateral’s Fair Market Value
March 01, 2017 —
Richard H. Herold - Snell & Wilmer Real Estate Litigation BlogThe Arizona Supreme Court recently addressed what impact, if any, a lender’s credit bid at an Arizona trustee’s sale has on an insurer’s liability under Sections 2, 7 and 9 of the standard’s lender’s title policy (“Policy”), holding in Equity Income Partners, LP v. Chicago Title Insurance Company, 241 Ariz. 334, 387 P.3d 1263 (February 7, 2017) as follows:
1. Section 2 of the Policy, entitled “Continuation of Insurance,” not Section 9, entitled “Reduction of Insurance; Reduction or Termination of Liability,” applies when a lender acquires property at a trustee sale by “either a full- or partial-credit bid” since Section 2 directly addresses the existence and amount of coverage in such circumstances. Id. at 1267.
Read the court decisionRead the full story...Reprinted courtesy of
Richard H. Herold, Snell & WilmerMr. Herold may be contacted at
rherold@swlaw.com
Construction Contract Basics: Attorney Fee Provisions
November 13, 2023 —
Christopher G. Hill - Construction Law MusingsI have discussed the need for
attorney fee provisions in your construction contracts in prior posts here at Construction Law Musings, but thought it merited a restatement of the reasons for the inclusion of such fee provisions (and changing of such provisions when presented) here with the second of my
construction contract basics posts.
Why would you want such a provision? The answer is that without it, or a statute specifically allowing for such fees, a Virginia court will not award your attorney fees without such a provision. Virginia, and a lot of other states, follow the so-called “American Rule” when it comes to attorney fees and costs. In short, that rule states that the parties to litigation pay their own way unless they agree otherwise. While it may seem unfair to make a successful litigant pay for the privilege of being right, that is the rule in Virginia. Throw in the fact that Virginia courts
strictly construe construction contracts and voila we have a situation where without a provision in the contract stating that one party or both will be able to collect attorney fees should that contractor or subcontractor prevail, a construction professional that gets sued (whether rightly or wrongly) will be left with a hefty attorney fees bill and no way to recoup those fees through the courts or any other method.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Brown Paint Doesn’t Cover Up Construction Defects
April 25, 2012 —
CDJ STAFFIn a decision that describes the case as illustrating “the perils that real estate brokers and their agents assume when acting as a dual listing agent to both the buyers and sellers of the same house,” the California Court of Appeals has issued a decision in William L. Lyon & Associates v. The Superior Court of Placer County. Lyon & Associates sought summary judgment to dismiss the claims of the Henleys who bought a home in a transaction where a Lyon agent represented both sides.
The prior owners of the home, the Costas, had used a Lyon agent in purchasing their home. When they later sought to sell it, that agent “became aware of some of the house’s defects and problems.” In response, the Costas sought the help of another agent, Connie Gidal, also of Lyons & Associates. Photos taken in the presence of Ms. Gidal show defects of the paint and stucco. The Costas also took the step of painting the house dark brown. During the sale process, “rain caused many of the painted-over defects to reappear.” The Costas “purchased more dark brown paint and covered up the newly visible damage prior to inspection by the Henleys.”
With the damage concealed, the Henleys bought the home in May 2006. The agreement with Lyons & Associates noted that “a dual agent is obligated to disclose known facts materially affecting the value or desirability of the property to both parties.” Escrow closed on May 9, 2006. The contract with the broker included a two-year limit on the time to bring legal action.
The Henleys moved in during June 2006, and “began to discover construction defects that had been concealed by the Costas.” In addition to the painted-over stucco problems, the Henleys found that the Costas had “installed quartzite stone overlays on the backyard steps in a manner that caused water intrusion on the house’s stucco walls.”
In May 2009, the Henleys sued the Costas, Ron McKim Construction, Lyons & Associates, and Ms. Gidal. Their complaint alleged that Lyons & Associates had committed breach of contact, negligence, fraud, breach of fiduciary duty, and negligent nondisclosure in connection with the construction defects. The Costas named Lyons in a cross complaint. Lyons moved for summary judgments on the grounds that the two-year statute of limitations had expired before the complaint and cross-complaint were filed. Both the Henleys and the Costas opposed this claim. The court denied the motion and Lyons appealed.
The appeals court upheld the denial, noting that the both California Supreme Court decision and later action by the legislature compels real estate brokers and salespersons “to conduct a reasonably competent and diligent visual inspection of the property offered for sale.” The court noted that under California law, brokers have responsibilities to both sellers and buyers. The section of law cited by Lyons applies to seller’s agents. The court rejected the contention by Lyons that they were “cooperating brokers.” The Henleys were “not constrained by the two-year statute of limitations.”
Lyons contended that even if California’s statute did not apply, there was a contractual limit of two years. The court also rejected this, agreeing with the Henleys that “the two-year limitation period must be extended by the discovery rule.”
The court noted that “Lyon & Associates may not reap the benefit of a shortened contractual limitation period when its own alleged malfeasance contributed to the delay in the discovery of the buyer’s injury.” The court found that the Henleys could proceed with their breach of contract claim, because, “when a breach of contract is committed in secret, such as the intentional nondisclosure of a real estate broker regarding a previously visible construction defect, the contractual limitations period is properly held subject to the discovery rule.” The court felt that the interpretation favored by the California Association of Realtors would “halve the applicable statute of limitations period.”
In addition to rejecting Lyon request for summary judgment on the claims made by the Henleys, the court also rejected the request of summary judgment on the claims made by the Costas, concluding that neither claim is time-barred. Costs were awarded to both the Henleys and Costas.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of