Ownership is Not a Conclusive Factor for Ongoing Operations Additional Insured Coverage
November 15, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn McMillin Management Services v. Financial Pacific Ins. Co. (No. D069814, filed 11/14/17), a California appeals court held that an insurer had a duty to defend a general contractor under an “ongoing operations” additional insured (AI) endorsement for damage occurring after the named insured subcontractor completed its work, because the endorsement did not limit coverage solely to liability during the subcontractors’ ongoing operations, but rather, broadly provided coverage for liability “arising out of” such operations.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Indemnification Provisions Do Not Create Reciprocal Attorney’s Fees Provisions
November 21, 2018 —
CDJ STAFFIn a good, recent decision, the Eleventh Circuit in International Fidelity Insurance Co. v. Americabe-Moriarity, JV, 2018 WL 5306683 (11th Cir. 2018), held that Florida Statute s. 57.105(7) cannot be used to shift attorney’s fees in a contractual indemnification clause in a dispute between a general contractor and subcontractor’s performance bond surety, when the dispute does not involve an actual indemnification claim stemming from a third-party.
In this case, a prime contractor terminated a subcontractor and looked to the subcontractor’s performance bond surety to pay for the completion work. The subcontractor had a standard AIA A312 performance bond that requires the prime contractor to comply with the terms of the bond, as well as the incorporated subcontract, in order to trigger the surety’s obligations under the bond. The surety filed an action for declaratory relief against the prime contractor arguing that the prime contractor breached the terms of the performance bond through non-compliance thereby discharging the surety’s obligations. The trial court agreed and the surety moved for attorney’s fees.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
TLSS Partner Burks Smith and Associate Katie Keller Win Summary Judgment on Late Reported Water Seepage Case in South Florida
November 18, 2019 —
Burks A. Smith, III & Kathryn Keller - Traub LiebermanOn July 9, 2019, Traub Lieberman Straus & Shrewsberry LLP Partner, Burks A. Smith, III and Associate, Kathryn A. Keller, secured Summary Judgment on behalf of a major homeowners’ insurer in a breach of contract action in the United States District Court for the Southern District of Florida. See Lehrfield v. Liberty Mutual Fire Insurance Company, 2019 WL2994270 (S.D. Fla. 2019). The underlying claim involved a water loss at the Plaintiffs’ residence allegedly resulting in $91,147.32 worth of damage to their home. The claim was reported eight (8) months after the alleged date of loss, and during the inspection, the adjuster observed rot, decay, mold, and warping wood, prompting the carrier to deny the claim based on the Seepage Endorsement. The Plaintiffs filed a breach of contract action alleging that the insurer breached the Policy by denying the claim.
Mr. Smith and Ms. Keller argued that Plaintiffs’ Policy with the insurer imposes a duty on the Plaintiffs to comply with the Duties After Loss conditions of the Policy, including the requirement to provide prompt notice of the loss and show the damaged property. As mentioned above, the Plaintiffs provided notice of the claim eight (8) months late, and performed various repairs prior to notifying the insurer of the claim. After the close of discovery, Mr. Smith and Ms. Keller filed a Motion for Summary Judgment on behalf of the insurer based on the late reporting, and further argued that the Plaintiffs had the burden of proving direct physical loss to property within the first 13 days of the loss, given the recent decision of Hicks v. American Integrity Insurance Company of Florida, 241 So.3d 925 (Fla. 3d DCA 1018). In Florida, when an insured fails to comply with their Duties After Loss, a presumption of prejudice to the insurer arises. Bankers Ins. Co. v. Macias, 475 So. 2d 1216, 1218 (Fla. 1985)). In order to recover, the Plaintiffs bear the burden of overcoming the presumption, and must prove that no prejudice existed. Id. Mr. Smith and Ms. Keller’s comprehensive arguments successfully proved to the Court that the Plaintiffs’ failure to timely report the claim prejudiced the insurer by prohibiting the insurer from being able to independently validate the loss, or distinguish between multiple causes of loss. Mr. Smith and Ms. Keller further argued that Plaintiffs did not meet their burden to prove that the insurer was not prejudiced by the Plaintiffs’ failure to comply with the Duties After Loss provision of the Policy. The Motion cited numerous cases and extensive analysis supporting the insurer’s position.
Reprinted courtesy of
Burks A. Smith, III, Traub Lieberman and
Kathryn Keller, Traub Lieberman
Mr. Smith, may be contacted at bsmith@tlsslaw.com
Ms. Keller may be contacted at kkeller@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Lightstone Committing $2 Billion to Hotel Projects
February 26, 2015 —
Nadja Brandt – Bloomberg(Bloomberg) -- David Lichtenstein, whose real estate company owned Extended Stay Hotels when the chain went bankrupt, is committing $2 billion to developing and investing in lodging properties.
Lightstone Group is choosing “top-branded” select-service properties, those with limited amenities, in proven U.S. markets for its projects, Lichtenstein said in an interview. As part of the strategy, Lightstone has teamed up with Marriott International Inc. to build five Moxy hotels in New York -- four in Manhattan and one in Brooklyn. The “micro” lodgings, with high-tech features and smaller-than-average rooms, are geared toward younger travelers.
Read the court decisionRead the full story...Reprinted courtesy of
Nadja Brandt, BloombergMs. Brandt may be contacted at
nbrandt@bloomberg.net
In Florida, Exculpatory Clauses Do Not Need Express Language Referring to the Exculpated Party's Negligence
October 02, 2015 —
Edward Jaeger & William Doerler – White and Williams LLPIn Sanislo v. Give Kids the World, Inc., 157 So.3d 256 (Fla. 2015), the Supreme Court of Florida considered whether a party to a contract, in order to be released from liability for its own negligence, needs to include an express reference to negligence in an exculpatory clause. The court held that, unlike an indemnification clause, so long as the language in an exculpatory clause is clear, the absence of the terms “negligence” or “negligent acts” in an exculpatory clause does not, for that reason alone, render the exculpatory clause ineffective.
Background
Give Kids the World, Inc. (“GKW”) is a non-profit organization that provides free vacations to seriously ill children and their families at GKW’s resort village. To use the resort, vacationers have to fill out an application. Stacy and Eric Sanislo filled out an application to bring their seriously ill child to the village for a vacation and GKW accepted their application. Upon arriving at the resort, the Sanislos filled out a liability release form.
Reprinted courtesy of
Edward Jaeger, White and Williams LLP and
William Doerler, White and Williams LLP
Mr. Jaeger may be contacted at jaegere@whiteandwilliams.com
Mr. Doerler may be contacted at doerlerw@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Federal District Court Denies Motion for Remand
December 21, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court refused to remand the insureds' case after the insurer removed from state court. Maui Land & Pineapple Co. v. Liberty Ins. Underwriters, 2016 U.S. Dist. LEXIS 15681 (D. Haw. Nov. 10, 2016).
The underlying case was filed in state court on Maui. The underlying plaintiffs were condominium owners who brought claims against the insured, Maui Land and Pineapple Co., Inc. (MLP), and other defendants allegedly involved in the development of the project. Ryan Churchill, one of the named defendants, served as president of MLP and was on the board of the project's Association of Apartment Owners (AOAO). The underlying plaintiffs asserted claims for: breach of fiduciary duty; seeking access to books and records of the AOAO; and for injunctive/declaratory relief against MLP, Mr. Churchill, and all other defendants.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insurance Tips for Contractors
December 08, 2016 —
Patrick McNamara - Porter Law GroupMany contractors contentedly accept the insurance policies presented to them by their insurance carriers. However, it is a much better practice to be an active participant in choosing the most appropriate coverage for your business and the specific jobs that you are performing. Use the following tips to be sure your company has the best and most comprehensive coverage.
- Never purchase a Commercial General Liability (“CGL”) policy with a “sunset” provision limiting coverage under Products & Completed Operations liability (P&CO) to a 2, 3 or 4-year term. Why? Because the California statute of limitations for construction defect claims is generally 10 years.
- Never consider a “Claims-made” or “Modified Occurrence” coverage form which also have a built-in limitation as to the length or term of P&CO coverage. Example: If you purchase a claims-made policy and decide to “switch” your insurance to the preferred “occurrence” coverage form, unless a special provision is made prior to the new purchase, the claims-made coverage would become worthless after the sixty (60) day claims-reporting period.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Design Professional Liens: A Blueprint
March 12, 2015 —
Garret Murai – California Construction Law BlogIf you work in the construction industry in California you’re likely familiar with
mechanics liens.
But there’s one other type of lien available on construction projects in California: The design professional lien.
So, here’s a blueprint of what you need to know.
What is a design professional lien?
A design professional lien, like a mechanics lien, creates a security interest in real property for services rendered by a design professional prior to commencement of construction. If the design professional is not paid, the design professional can file a lawsuit to foreclose on the design professional lien to have the property sold and the proceeds from the sale used to satisfy the amount of the design professional lien.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at