General Contractor Supporting a Subcontractor’s Change Order Only for Owner to Reject the Change
December 09, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe opinion in Westchester Fire Ins. Co, LLC v. Kesoki Painting, LLC, 260 So.3d 546 (Fla. 3d DCA 2018) leads to a worthy discussion because it involves a common scope of work occurrence on construction projects involving a general contractor and subcontractor. The contractor submits a subcontractor’s change order request to the owner and the owner rejects the change order. What happens next is a scope of work payment dispute between the general contractor and subcontractor. Yep, a common occurrence.
In this case, a general contractor hired a subcontractor to perform waterproofing and painting. A scope of work issue arose because the specifications did not address how the window gaskets should be cut and then sealed. The owner wanted the window gaskets cut at a 45-degree angle and the subcontractor claimed this resulted in increased extra work. The general contractor agreed and submitted a change order to the owner to cover these costs. The owner rejected the change order claiming it was part of the general contractor’s scope of work even though the cutting of window gaskets at a 45-degree angle was not detailed in the specifications.
After the subcontractor filed a suit against the general contractor’s payment bond surety, the project architect further rejected the change order because gasket cutting was part of the specification requirements. (Duh! What else was the architect going to say? It was not going to concede there was an omission that resulted in a change order to the owner, right?)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Trial Court’s Grant of Summary Judgment On Ground Not Asserted By Moving Party Upheld
December 17, 2015 —
Laura C. Williams & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Marlton Recovery Partners, LLC v. County of Los Angeles, et al. (filed 11/20/15), the California Court of Appeal, Second Appellate District, affirmed summary judgment in favor of the defendants County of Los Angeles, the County Treasurer-Tax Collector and Board of Supervisors (collectively the “County”) despite the fact summary judgment was granted on grounds not raised by the County. The Court of Appeal determined that because the plaintiff could not have shown a triable issue of material fact on the ground of law relied upon by the trial court, summary judgment was proper.
In the underlying case, plaintiff sought cancellation of penalties on delinquent property taxes for 26 parcels under Revenue and Taxation Code §4985.2, which allows the tax collector to cancel such penalties under certain circumstances. The County denied the request prompting plaintiff to challenge the denial on a petition for peremptory writ of mandate to the trial court.
Reprinted courtesy of
Laura C. Williams, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Ms. Williams may be contacted at lwilliams@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
An Occurrence Under Builder’s Risk Insurance Policy Is Based on the Language in the Policy
April 03, 2023 —
David Adelstein - Florida Construction Legal UpdatesBuilder’s risk insurance coverage is a vital property insurance coverage during the course of construction. Builder’s risk insurance is not a one-size-fits-all product so please make sure you are working with your insurance broker to procure this product that factors in and covers risk associated with the project.
Builder’s risk insurance is typically an occurrence-based policy. No different than other occurrence-based policies (such as commercial general liability), a dispute may arise as to the occurrence. This could be due to the triggering of the actual policy during the coverage period or it could be due deductible obligations, as in the case discussed below. When dealing with a builder’s risk insurance policy–again, no different than any policy–the language in the policy matters. Definitions used in the policy to define specific terms matter and, in numerous cases, the ordinary dictionary meanings of terms matter. But it all starts with the policy language.
In KT State & Lemon, LLP v. Westchester Fire Insurance Co., 2023 WL 2456499 (M.D.Fla. 2023), a builder’s risk policy provided coverage from April 2018 through the end of November 2019. There was a $50,000 per occurrence deductible for loss caused by or from water damage. An extension to the builder’s risk policy was negotiated through the end of January 2020 that increased this water damage deductible to $250,000 per occurrence. During construction and the testing of the fire suppression (sprinkler) system, leaks started to occur resulting in water damage. Two leaks occurred in September 2019, one leak in October 2019, one leak in November 2019, and two leaks in December 2019 (during the extension and higher water damage deductible period).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Real Estate & Construction News Round-Up 05/04/22
May 23, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogConstruction payment apps are on the rise, the European Union proposes to block Russians from buying European real estate, warehouse vacancy rates hit a 27-year low, and more.
- The Metaverse Group has made itself one of the most prominent virtual land owners, having invested more than $10 million into digital real estate purchases. (Katie Canales, Business Insider)
- The European Union proposed to block Russians from buying European real estate in its six package of sanctions following Russia’s invasion of Ukraine. (Jorge Valero and Alberto Nardelli, Bloomberg)
- Although smart office buildings are able to easily identify viruses, they are susceptible to hacks, raising privacy and cybersecurity concerns in the market. (Konrad Putzier, The Wall Street Journal)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Colorado Legislative Update: HB 20-1155, HB 20-1290, and HB 20-1348
August 03, 2020 —
Jean Meyer - Colorado Construction LitigationThis year’s Colorado State Legislative session was cut short. However, in the period of time Colorado’s Legislature was in session, it passed and evaluated important legislation for Colorado homebuilders. This article highlights relevant legislation for Colorado homebuilders.
1. HB 20-1155
This Bill creates new requirements on new homebuilders to offer renewable energy systems to the buyer of a new home. Specifically, the Bill requires homebuilders to offer each of the following:
- A solar panel system, a solar thermal system, or both;
- Prewiring or pre-plumbing for the above solar systems; and,
- A chase or conduit for future installation of such systems.
The Bill further requires Colorado homebuilders to offer homebuyers one of the following:
- An electric vehicle charging system;
- Prewiring for the future installation for such a system; or,
- A plug-in receptacle in a place accessible to a vehicle parking area.
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
Jury Could Have Found That Scissor Lift Manufacturer Should Have Included “Better” Safety Features
January 02, 2024 —
Garret Murai - California Construction Law BlogA few years ago I listened to an NPR segment called “
What Can Kids Learn by Doing Dangerous Things?” It was about a summer program called the Tinkering School where kids can learn to build things, using tools of course, including power tools.
The founder of the program, Gever Tulley, also wrote a book entitled
50 Dangerous Things (You Should Let Your Children Do), in which he argued that while well-intentioned, children today are overly protected, and that giving children exposure to “slightly” dangerous things can help foster independence, responsibility, and problem-solving as well as a healthy dose of caution.
The plaintiff in the next case might have benefitted from that program.
In
Camacho v. JLG Industries Inc., 93 Cal.App.5th 809 (2023), the Court of Appeals examined whether the manufacturer of a scissor lift should have incorporated “better” safety features when a construction worker fell from the lift.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Terminating the Notice of Commencement (with a Notice of Termination)
July 19, 2017 —
David Adelstein - Florida Construction Legal UpdatesThe notice of commencement is important for purposes of construction lien priority. Stock Bldg. Supply of Florida, Inc. v. Soares Da Costa Const. Services, LLC, 76 So.3d 313, 317 (Fla. 3d DCA 2011) (“[A] notice of commencement serves to determine the priority of liens under the Construction Lien Law.”). A lien relates back in time to the date the notice of commencement was recorded assuming the notice of commencement is still in effect when the lien is recorded (or an amended noticed of commencement is recorded). Lien priority is very important and the reason why a contractor should always want to ensure there is an effective notice of commencement in place rather than an expired notice of commencement.
For the same reasons why a contractor wants to ensure there is an effective notice of commencement, there are times an owner wants to terminate a notice of commencement. An owner may want to terminate the potential priority of a construction lien. For instance, say the owner is refinancing or obtaining a construction loan in the midst of construction. A lender will want to ensure its mortgage maintains first priority and certainly priority over a potential construction lien. Otherwise, why would a lender finance the construction if it does not maintain first priority. It generally will not. Thus, an owner needs to terminate the notice of commencement so that the closing occurs on the loan and the mortgage recorded before a new notice of commencement is recorded and construction continues.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Water Damage: Construction’s Often Unnoticed Threat
November 02, 2020 —
Yaron Dycian - Construction ExecutiveFire damage to commercial buildings might get headlines, but water damage, whether to projects under construction or completed buildings, delivers massive financial blows to owners, developers and contractors. The impact is massive, reaching many billions of dollars per year. One water leak on the 19th floor at a construction site of a high-end apartment building in New York City resulted in $30 million in property damage and millions in delayed delivery penalties.
Imagine this all-too-typical scenario: A 20-story building has thousands of pipe connections and many tens of thousands throughout the entire building. It only takes one of those joints failing, perhaps due to human oversight. Early on a Saturday morning when no one is onsite, one of the connections inside a wall begins to leak, slowly at first. In a couple hours the connection fails completely, sending a cascade of water into the building. The site is located next to a highway, so the security guards don’t hear the water flowing.
The leak goes undetected until crews come back onsite on Monday morning. By that point, lower levels of the building have been inundated with thousands of gallons of water that has destroyed construction material, carpeting and electrical switchgear. It’s flowed into the elevator pits and mechanical room.
Reprinted courtesy of
Yaron Dycian, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of