Jinx: Third Circuit Rules in Favor of Teamsters in Withdrawal Case
July 28, 2018 —
Wally Zimolong - Supplemental ConditionsBad omen. Last week, I wrote about a Appeals Court decision that affirmed a contractor’s escape from an over $600,000 withdrawal liability assessment from the Laborers Union. The next day the Third Circuit (which covers PA, NJ, and DE) handed down a decision affirming a federal court’s decision to assess withdraw liability. This one shows the dark side of not reading and understanding your CBA.
The belligerents in the litigation were, Penn Jersey, a construction material supplier, and Teamsters Local 676. Their collective bargaining agreement contained a clause purportedly covering withdrawal liability. Specifically, the clause stated “should the Employer withdraw from the Agreement in the future, there will be no withdrawal liability. The CBA expired and Penn Jersey did not renew its agreement with the Teamsters.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Changes to Pennsylvania Mechanic’s Lien Code
July 13, 2017 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome Jim Fullerton. Jim is the President of the law firm of Fullerton & Knowles, P.C., which has attorneys licensed in Virginia, Maryland, Pennsylvania, and the District of Columbia, is a Martindale Hubbell Peer Rated Lawyer AV® Preeminent.™ The firm represents owners, lenders, design professionals, suppliers, subcontractors, general contractors and other members of the real estate and construction industries, filing mechanic’s liens, surety bond and other construction claims across all of the states in the Mid Atlantic region. He also represents creditors in bankruptcy issues nationwide, particularly defense of bankruptcy preference claims; advises owners and lenders in real estate lending and acquisition transactions; on all real estate and construction law issues; contract formation and disputes.
The firm’s Construction Law Survival Manual is well known and widely used by participants in the construction process. The 550 page manual provides valuable information about construction contract litigation, mechanic’s liens, payment bond claims, bankruptcy and credit management and contains over 30 commonly used contract forms. All of this information and recent construction law issues are constantly updated on the firm’s website.
There are two changes to the Pennsylvania Mechanic’s Lien Code that became effective September 2014. First, residential properties built by an owner for their own residence will now have a defense of payment to subcontractor mechanic’s liens. This protects homeowners from mechanic’s liens if they have paid their general contractors in full. Second, construction loan open end mortgages will have priority over mechanic’s liens, as long as at least sixty per cent (60%) of the loan proceeds are used for construction costs. This change was pushed by Pennsylvania lenders in response to a recent court case.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Fannie Mae Says Millennials Are Finally Leaving Their Parents' Basements
December 17, 2015 —
Julie Verhage – BloombergParents, rejoice. Your offspring may finally be moving out of the family basement.
A new report (PDF) from Fannie Mae, the U.S. government-backed mortgage company, suggests that the millennial generation is getting a move on.
"According to the ACS [Census Bureau’s American Community Survey], the number of homeowners aged 25-34 fell by more than 250,000 in each year between 2007 and 2012, but has declined by less than 100,000 annually since then," Fannie Mae said. "In fact, the decline between 2013 and 2014 was statistically insignificant, the first indication of stability in the number of young homeowners since the onset of the Great Recession." So while the number of homeowners in that age range is still on the decline, the trend looks poised for a reversal, and Fannie Mae said it won't take much to see positive growth in millennial homeownership in the near future.
Read the court decisionRead the full story...Reprinted courtesy of
Julie Verhage, Bloomberg
Ruling Dealing with Constructive Changes, Constructive Suspension, and the Implied Covenant of Good Faith and Fair Dealing
January 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA dispute pending in the Armed Services Board of Contract Appeals (ASBCA) dealt with interesting legal issues on a motion to dismiss. See Appeals of McCarthy Hitt-Next NGA West JV, ASBCA No. 63571, 2023 WL 9179193 (ASBCA 2023). The dispute involves a contractor passing through subcontractor claims due to impacts caused by the COVID-19 pandemic and the government’s response to the pandemic. More particularly, the claim centers on the premise that the government “failed to work with [the contractor] in good faith to develop a collaborative and cooperative approach to manage and mitigate the impacts and delays arising from the COVID-19 pandemic.” See Appeals of McCarthy Hitt.
The contractor (again, submitting pass through claims from subcontractors) claimed: (a) constructive changes to the contract entitling it to an equitable adjustment under the Changes clause of Federal Acquisition Regulation (F.A.R.) 52.243-4; (b) construction suspensions of the contractor’s work entitling it to an equitable adjustment under the Suspensions of Work clause of F.A.R. 52-242-14; and (c) the government breached the implied covenant of good faith and fair dealing. Each of these legal issues and theories will be discussed below because they are need-to-know legal issues. Keep these legal issues in mind, and the ASBCA’s ruling on the motion to dismiss as its analysis may demonstrate fruitful in other applications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Property Damage, Occurrences, Delays, Offsets and Fees. California Decision is a Smorgasbord of Construction Insurance Issues
November 21, 2017 —
Garret Murai - California Construction Law BlogOriginally published by CDJ on November 15, 2017
I read once that 97 percent of cases never go to trial. However, there are still the ones that do. And, then, there are the ones that do both. The following case, Global Modular, Inc. v. Kadena Pacific, Inc., California Court of Appeals for the Fourth District, Case No. E063551 (September 8, 2017), highlights some of the issues that can arise when portions of cases settle and other portions go to trial, the recovery of delay damages on a construction project through insurance, and the recovery of attorneys’ fees.
Global Modular, Inc. v. Kadena Pacific, Inc.
The U.S. Department of Veterans Affairs contracted with general contractor Kadena Pacific, Inc. (Kadena) to oversee construction of its Center for Blind Rehabilitation in Menlo Park, California. Kadena, in turn, contracted with subcontractor Global Modular, Inc. (Global) to construct, deliver and install 53 modular units totaling more than 37,000 square feet for a contract price of approximately $3.5 million.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Construction Contract Clauses That May or May Not Have Your Vote – Part 3
November 23, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The third in a multi-part series, here are some other important construction contract clauses that may determine whether you come out a winner.
Provision: Supervisory Personnel, Employees, and Authority to Bind Provisions
- Typical Provision: ”At all times during performance of the Work, Subcontractor shall have at the job site a competent supervisor approved by Owner. Subcontractor’s supervisor shall be deemed a representative of Subcontractor and all communications given to Subcontractor’s supervisor shall be as binding as if such communications were given to Subcontractor. Should Contractor object to Subcontractor’s supervisor’s presence at the job site, or the presence at the job site, or the presence at the job site of any other employee or agent of Subcontractor or any employee or agent of Subcontractor of Subcontractor, Subcontractor shall cause such persons to be replaced immediately as directed by Contractor.”
- What it Means: Higher-tiered parties have a legitimate interest in ensuring that only competent individuals are allowed to perform work on a project and in ensuring that there are peaceable relations at a job site. Higher-tiered parties also have an interest in ensuring that directives and agreements made and reached in the field are followed. However, it is unreasonable for higher-tiered party or to require that such personnel be able to bind that lower-tiered party to agreements best decided by others.
- What You Can Do: Lower-tiered parties should seek to include language which provides that only “reasonable” changes to personnel are allowed and, as necessary, limit by category or issue the types of items on-site personnel can bind the lower-tiered party to.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Fraudster Sells 24-Bedroom ‘King’s Speech’ London Mansion
May 20, 2015 —
Neil Callanan – BloombergEdward Davenport, jailed for fraud for his role in a fake lender, sold a 24-bedroom mansion in London’s Marylebone district that was featured in the film “The King’s Speech.”
The money raised from the sale will be used to repay 13 million pounds ($20 million) from a confiscation order by Her Majesty’s Courts and Tribunals Service, the Serious Fraud Office said in a statement Wednesday.
Davenport was jailed for more than seven years in October 2011 for his role in Gresham Ltd., a company that said it offered to provide commercial funding in return for advance fees, the SFO said. After securing the payments, employees would make deceptive assertions to extract further fees, the SFO said in 2011.
Read the court decisionRead the full story...Reprinted courtesy of
Neil Callanan, Bloomberg
Lumber Drops to Nine-Month Low, Extending Retreat From Record
August 30, 2021 —
Marcy Nicholson - BloombergLumber futures slid to the lowest in more than nine months after sawmills ramped up production and demand from builders stabilized.
September futures in Chicago fell as much as 4.4% to $482.90 per thousand board feet, the lowest for a most-active contract since Oct. 30. Prices have dropped more than 70% from the record high reached just three months ago.
The tumble marks a stark turnaround for the common building material after strong U.S. construction demand during the pandemic spurred a surge in orders for lumber, causing prices to more than quadruple to their May peak and fueling inflation concerns. Sawmills have since increased output, and a shortage of other building supplies such as siding and windows has slowed the pace of construction, said Brian Leonard, an analyst with RCM Alternatives.
Read the court decisionRead the full story...Reprinted courtesy of
Marcy Nicholson, Bloomberg