CA Supreme Court: Right to Repair Act (SB 800) is the Exclusive Remedy for Residential Construction Defect Claims – So Now What?
January 31, 2018 —
Steven M. Cvitanovic & Omar Parra - Publications & InsightsA torrent of alerts have been flooding e-mail inboxes regarding the California Supreme Court’s decision in
McMillin v. Superior Court, to reverse the Liberty Mutual Insurance Company v. Brookfield Crystal Cove LLC (2013) case, but with little discussion about the practical effects of the ruling. This alert will discuss how this ruling affects litigation of SB 800 Claims and Builders.
Background on Liberty Mutual Case
In 2002, the California Legislature enacted comprehensive construction defect litigation reform referred to as the Right to Repair Act (the “Act”). Among other things, the Act establishes standards for residential dwellings, and creates a prelitigation process that allows builders an opportunity to cure the construction defects before being sued. Since its enactment, however, the Act’s application has been up for debate. Most notably, in
Liberty Mutual Insurance Company v. Brookfield Crystal Cove LLC (2013), the California Court of Appeal for the Fourth District held the Act was the exclusive remedy only in instances where the defects caused only economic loss, and that homeowners could pursue other remedies in situations where the defects caused actual property damage or personal injuries.
Reprinted courtesy of
Steve Cvitanovic, Haight Brown & Bonesteel LLP and
Omar Parra, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Parra may be contacted at oparra@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.
April 28, 2011 —
Beverley BevenFlorez CDJ STAFFIn the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”
The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”
According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”
The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”
The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”
The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.”The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”
Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”
The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”
In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”
The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”
In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”
The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”
Read the court’s decision… Read the court decisionRead the full story...Reprinted courtesy of
Construction Bright Spot in Indianapolis
March 01, 2012 —
CDJ STAFFThe downtown Indianapolis area is the site of about 85 major building projects that are from groundbreaking to just complete. The Indianapolis Star reports that the cumulative worth of the projects is about $3 billion, a level of construction that Indianapolis has seen only once before.
About thirty of the projects are residential. The main commercial project is a $754 million hospital building. The boom in downtown Indianapolis is not matched elsewhere, with the Indianapolis Star reporting that in the rest of Central Indiana, construction has slowed.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Trial Date Discussed for Las Vegas HOA Takeover Case
February 04, 2014 —
Beverley BevenFlorez-CDJ STAFFJeff German of the Las Vegas Review-Journal reported that Justice Department attorneys filed papers January 28th demanding the trial involving 11 defendants charged in a scheme to take over the Las Vegas Valley homeowners associations to be held no later than September 2nd. The prosecutors claimed “they have gone out of their way to ease the burden on the defense as they have turned over mountains of evidence in the past year.”
However, the defense attorneys allege that they need “at least a year and likely more time” to go through the “more than 3 million pages of documents” and to create a trial strategy, according to German. The defense “asked for an initial late January 2015 trial date.”
The case involves charges against “lawyers, former police officers and corrupt board members” for “packing HOA boards to gain legal and construction defect contracts for themselves.”
Read the court decisionRead the full story...Reprinted courtesy of
We Knew Concrete Could Absorb Carbon—New Study Tells How Much
December 08, 2016 —
Thomas F. Armistead – Engineering News-RecordConcrete’s large carbon footprint—that is, the amount of carbon dioxide emitted during the cement manufacturing process—is estimated to be 5% of industrial CO2 emissions, a source of concern in the battle against human-caused climate change. But last month, an international research team reported that substantial quantities of CO2 are reabsorbed, or sequestered, by cement-based products over their life cycle.
Read the court decisionRead the full story...Reprinted courtesy of
Thomas F. Armistead, Engineering News-RecordENR may be contacted at
enr.com@bnpmedia.com
It’s Time for a Net Zero Building Boom
May 02, 2022 —
James S. Russell - BloombergIs it too much to ask Americans to take their foot off the gas and reset their thermostats? On March 18, the International Energy Agency released a 10-point plan for reducing oil use, arguing that advanced economies can readily cut demand by 2.7 million barrels a day in the next four months, an amount large enough to avoid major supply shortages as Russia’s invasion of Ukraine roils the energy market.
The plan’s major prescriptions will look familiar to anyone who recalls the OPEC shocks of the 1970s: reducing speed limits to improve gas mileage, boosting transit use, and discouraging non-essential car and air travel. But its exclusive focus on the transportation sector overlooks the substantial efficiency gains to be had from the built environment: Buildings consume about 40% of the energy used in the U.S. every year.
Yet reducing energy use in buildings has been stigmatized by fossil-fuel interests as a lifestyle deprivation — an argument that’s been internalized by pundits and politicians even as geopolitical turmoil drive spikes in oil prices and climate change impacts upend millions of lives.
Read the court decisionRead the full story...Reprinted courtesy of
James S. Russell, Bloomberg
COVID-19 Pandemic Preference Amendments to Bankruptcy Code Benefiting Vendors, Customers, Commercial Landlords and Tenants
May 03, 2021 —
Andrew Arthur & Steven Ostrow - White and Williams LLPOver the last three months, Congress has passed major pieces of legislation primarily in response to the COVID-19 pandemic, including the Consolidated Appropriations Act of 2021 (CAA), which was signed into law on December 27, 2020. In addition to funding the federal government and a second round of pandemic relief, the CAA contains several amendments to the Bankruptcy Code. One of the amendments provides preference protection to commercial landlords and suppliers who receive overdue payments from their tenants or customers under agreements made on or after March 13, 2020 to postpone the payment of rent or supplier charges.
The preference amendments encourage these creditors to afford their customers and tenants payment deferment arrangements without the risk that the companies will clawback the payments as preferences if they later file for bankruptcy protection. The amendments should facilitate workouts of distribution and leasing agreements to help distressed businesses recover and repay arrearages as COVID-19 related governmental restrictions are lifted this year.
Reprinted courtesy of
Andrew Arthur, White and Williams LLP and
Steven Ostrow, White and Williams LLP
Mr. Ostrow may be contacted at ostrows@whiteandwilliams.com
Mr. Arthur may be contacted at arthura@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Demand for New Homes Good News for Home Builders
October 01, 2013 —
CDJ STAFFStock prices are up for both KB Homes and Lennar, with shares of KB Homes up 7 % and Lennar up 5.5%. Both home builders are profiting from increased demand for new homes while supplies were scarce. Both firms have seen a strong increase in orders during the last quarter.
Read the court decisionRead the full story...Reprinted courtesy of