You Can Take This Job and Shove It!
June 10, 2015 —
Garret Murai – California Construction Law BlogThat’s it.
You’ve had it.
They can take their job and shove it!
But can you really tell an owner on a construction project to proverbially shove it where the sun don’t shine?
Well, far be it for me to tread on your First Amendment Rights or stick my nose into the subsequently brought public disturbance charges against you. But can you legally tell an owner to shove it, and that you’re no longer going to perform work on their [insert expletive] project? Well, indeed you can, in limited circumstances, and it’s called a “Stop Work Notice.”
Note: A stop work notice is different from a stop payment notice.
What is a stop work notice?
A stop work notice is a notice given by a direct contractor to a project owner that the contractor will stop work if an amount owed to the contract is not paid within 10 days after notice is given.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
General Contractor/Developer May Not Rely on the Homeowner Protection Act to Avoid a Waiver of Consequential Damages in an AIA Contract
August 04, 2011 —
Higgins, Hopkins, McLain & Roswell, LLCRecently, in Caribou Ridge Homes, LLC v. Zero Energy, LLC, et al., Case No. 10CV1094, Boulder County District Court Judge Ingrid S. Bakke entered a ruling and order on the Plaintiff’s Motion for Determination of Question of Law Pursuant to C.R.C.P. 56(h) on Issue of Damages. The Order found that the Plaintiff was not a homeowner intended to be protected by the Homeowner Protection Act (the “HPA”) and thus could not pursue its claims for consequential damages against Defendant.
By way of background, on June 18, 2008, Plaintiff Caribou Ridge Homes, LLC (“Caribou”) entered into a Standard Form Agreement Between Owner and Contractor AIA Document A114-2001 (the “Contract”) with Defendant Zero Energy, LLC (“Zero Energy”). Plaintiff hired Zero Energy to serve as a general contractor for the construction of a single-family home in the Caribou Ridge subdivision in Nederland, Colorado. A provision in the contract contained a mutual waiver of consequential damages (“Waiver”).
Read the full story…
Reprinted courtesy Higgins, Hopkins, McLain & Roswell, LLC
Read the court decisionRead the full story...Reprinted courtesy of
Growing Optimism Among Home Builders
June 28, 2013 —
CDJ STAFFFor the first time since 2006, the number of home builders who are optimistic about home sales exceed those who are pessimistic, with 52 percent optimistic. Just last month, the builder confidence index was at 44. This eight-point jump was the largest change in more than a decade.
Their confidence has increased as economists and others have been seeing signs of an improved economy. There has been an increase in demand for new homes and even though sales are below what economists would like, homebuilders are finding buyers.
Read the court decisionRead the full story...Reprinted courtesy of
Use of Dispute Review Boards in the Construction Process
December 27, 2021 —
Sarah B. Biser - ConsensusDocsDispute Review Boards: Overview
Problems, disagreements and claims arise in most large and complex construction projects regardless of the project delivery method. These disputes can and do delay and significantly increase the cost of the project. Dispute Review Boards, also known as Dispute Resolution Board, Dispute Board, Dispute Avoidance Board or DRB, are often found in large construction projects to assist the parties to minimize, resolve or avoid disputes and mitigate adverse impacts to projects. To date, over $270 billion worth of construction projects have used the dispute review board process to avoid numerous disputes and achieve significant savings.[1]
Unlike mediation and arbitration, a DRB is convened at the very beginning of the project and conducts regular meetings and visits at the project site throughout, allowing the DRB to discuss, observe and monitor construction, progress and potential disputes. At these meetings, DRB members become familiar with many of the facts and acquaint themselves with the job site personnel. If a dispute is submitted to them, the panelists have a great deal of knowledge about the circumstances of the problem to aid them in reaching their recommendations or conclusions. DRBs also encourage open and honest communications among or between the parties during the project, which in turn, encourages avoidance or resolution of disputes before they become formal claims. In short, the DRP process involves real-time discussion of the dispute with highly qualified people who know the particular project from day one and can provide recommendations on how to resolve disputes.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah B. Biser, Fox Rothschild LLPMs. Biser may be contacted at
sbiser@foxrothschild.com
No Coverage for Additional Insured After Completion of Operations
March 26, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Fifth Circuit held there was no duty to defend an additional insured for alleged negligence after completion of the project. Woodward v. Acceptance Indemn. Ins. Co., 2014 U.S. App. LEXIS 2569 (5th Cir. Feb. 11, 2014).
Pass Marianne, L.L.C. contracted for the construction of condominiums. The general contractor was Woodward. DCM Corporation, L.L.C. was a subcontractor for the concrete work. DCM worked on the project from January to October 2006. The entire project was completed in August 2007. Pass Marianne sold the condominiums to Lemon Drop Properties in October 2007.
Lemon Drop sued Pass Marianne and Woodward a year after purchasing the condominium. Pass Marianne filed a cross-claim against Woodward alleging faulty construction and damage arising out of the construction. The claims were arbitrated. A significant issue in the arbitration was the fault of the concrete subcontractor, DCM.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Sureties and Bond Producers May Be Liable For a Contractor’s False Claims Action Violation
October 26, 2017 —
Michael C. Zisa & Susan Elliot – Peckar & Abramson, P.C.Two recent decisions from the United States District Court for the District of Columbia and the United States Court of Federal Claims highlight that sureties and bond producers are not immune to the potentially severe consequences of the False Claims Act (“FCA”) and related federal fraud statutes. In each case, the Court determined that sureties and bond producers can face potential liability under these fraud statutes for direct and indirect submission of false claims to the federal government
Reprinted courtesy of
Michael C. Zisa, Peckar & Abramson, P.C. and
Susan Elliott, Peckar & Abramson, P.C.
Mr. Zisa may be contacted at mzisa@pecklaw.com
Ms. Elliott may be contacted at selliott@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Texas Shortens Its Statute of Repose To 6 Years, With Limitations
October 02, 2023 —
Jason Daniel Feld & Roni Most - Kahana FeldEffective June 9, 2023, Texas has shortened its statute of repose from the existing 10-year statute for builders of new homes to 6-years under specific conditions. The significantly shorter statute of repose bars suits against construction contractors of detached one-and two-family homes and townhomes, filed six years after the substantial completion of such homes, where the contractor also furnished a written warranty in compliance with the statute. Notably, projects including apartments, mixed-use, and hotels are not covered by the new law. It is also noted that a grey area in the law exists as to whether condominiums will be covered by the statute. The statute of repose strictly bars the filing of any action, claim or arbitration demand regardless of when the injury was actually discovered (latent defects) and is separate and distinct from any applicable statute of limitations.
The New Texas Statute of Repose Law
Under the
Texas Civil Practice & Remedies Code § 16.009, persons who construct or repair improvements to real property cannot be sued for defective or unsafe conditions of the property or deficiencies in the construction or repair of the improvement later than 10 years after substantial completion of the improvement, except in certain narrow circumstances. This statute is known as the “statute of repose.” The statute applies not only to suits for construction defects, but also personal injury, wrongful death, contribution, and indemnity.
Reprinted courtesy of
Jason Daniel Feld, Kahana Feld and
Roni Most, Kahana Feld
Mr. Feld may be contacted at jfeld@kahanafeld.com
Mr. Most may be contacted at rmost@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Select the Best Contract Model to Mitigate Risk and Achieve Energy Project Success
October 17, 2022 —
Gregory S. Seador - Construction ExecutivePower and energy projects are inherently complex and risky. Therefore, management and proper allocation of risk among project participants are essential to success.
Careful drafting of the engineering, procurement and construction (EPC) contract is a critical first step in managing risk. The standard contract format used for power and energy construction projects is the EPC contract. In its traditional form, the EPC contract makes the EPC contractor responsible for the entire project, including engineering (design of the power plant), procurement (purchase, installation and performance of all equipment) and construction (construction of the plant).
EPC contracts can, however, employ different contract models and pricing structures, each of which carries differing levels of risk for project participants. Selecting the appropriate contract model and pricing structure to meet the unique needs of the project is important.
Reprinted courtesy of
Gregory S. Seador, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Seader may be contacted at
seador@slslaw.com